Question

In 2018, Omega Construction began work on a contract with a price of $850,000 and estimated...

In 2018, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows:

2018

2019

2020

Costs incurred during the year

$238,000

$319,600

$105,000

Estimated costs to complete

357,000

139,400

-0-

Partial billings

260,000

210,000

380,000

Collections

240,000

200,000

410,000

Assuming the performance obligation is satisfied over time, what would be the gross profit in 2018?

Group of answer choices

$255,000

$425,000

$260,000

$102,000

Homework Answers

Answer #1

Answer:

Gross profit Recognised in year 2018 is $102000.

Explanation:

percentage of completion =

(Cost incurred in 2018 / Total cost in year 2018) x 100

Cost incurred in 2018 =$238000

Total cost in 2018 = Cost incurred +Estimated cost = $238000 + $357000 = $595000

Percentage of completion =

($238000 / $595000)x100= 40%

Revenue recognised in year 2018 = Contract Revenue x Percentage of completion = $850000 x 40% = $340000

Gross profit in year 2018 = Revenue Recognise in year 2018 - Cost incurred in year 2018 = $340000 - $238000 = $102000.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
In 2016 the ole construction corp began construction work under a 3 year contract. The contract...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract price was $1,600,000. The Job was completed in 2018.                                                                                 2016                       2017                       2018 Costs incurred to date                                    400000                  935000                  1070000 Estimated costs to complete                       700000                  165000                  0 Billings to date                                                  300000                  900000                  1600000 Collections to date                                           270000                  810000                  1525000 Compute the amount of Gross Profit to be recognized for 2016 and 2017 assuming that ole is required to recognize revenue overtime. Compute the...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 –0– Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 (a) What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $...
During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m....
During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m. ESAU incurred costs of $4m in 2018 and estimated at the end of the year that the remaining costs to complete the job would be $5.5m. During 2019 the company expended $3.0m and at year-end estimated that an additional $3.5m of costs would be incurred in 2020 to finish the project. Assuming that ESAU books $3.0m of expenses for this project in 2019, provide...
During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m....
During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m. ESAU incurred costs of $4m in 2018 and estimated at the end of the year that the remaining costs to complete the job would be $5.5m. During 2019 the company expended $3.0m and at year-end estimated that an additional $3.5m of costs would be incurred in 2020 to finish the project. Assuming that ESAU books $3.0m of expenses for this project in 2019, provide...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows:...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows: 2018     2019 Costs incurred to date €9,000,000 €14,000,000 Estimated costs to complete 6,000,000 — Billings to date 7,000,000 21,000,000 Collections to date 5,000,000 18,000,000 8. If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2018 is A. €3,600,000. B. €4,000,000. C. €5,400,000. D. €6,000,000. 9. If Kiner uses the cost-recovery method, the gross profit to be recognized in 2019 is...
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract...
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract #E2-D2, which provided for a contract price of $2,165,000. Other details follow: 2020 2021 Costs incurred during the year $590,520 $1,409,000 Estimated costs to complete, as of December 31 1,005,480 –0– Billings during the year 428,000 2,165,000 Collections during the year 349,000 1,509,000 What portion of the total contract price would be recognized as revenue in 2020? In 2021? Revenue recognized in 2020 $...
Evans Construction, Inc. experienced the following construction activity in 2018, the first year of operations. Contract...
Evans Construction, Inc. experienced the following construction activity in 2018, the first year of operations. Contract Total Contract Price Billings Through 12/31/18 Cash Collections Through 12/31/18 Costs Incurred Through 12/31/18 Estimated Additional Costs to Complete X $261,000 $171,000 $156,000 $184,000 $  64,000 Y 331,000 116,000 116,000 102,000 253,000 Z 234,000 234,000 200,000 160,000 -0- $826,000 $521,000 $472,000 $446,000 $317,000 Prepare a partial income statement to indicate how the above contract information would be reported. Evans uses the completed-contract method Prepare a...
Gomez, Inc. began work in 2010 on contract #3814, which provided for a contract price of...
Gomez, Inc. began work in 2010 on contract #3814, which provided for a contract price of $7,200,000. Other details follow: 2010 2011 Costs incurred during the year $1,200,000 $3,675,000 Estimated costs to complete, as of December 31 3,600,000 0 Billings during the year 1,350,000 5,400,000 Collections during the year 900,000 5,850,000 14. Assume that Gomez uses the percentage-of-completion method of accounting. The portion of the total gross profit to be recognized as income in 2010 is a. $450,000. b. $600,000....
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract #E2-D2, which provided for a contract price of $2,170,000. Other details follow: 2020 2021 Costs incurred during the year $615,810 $1,422,000 Estimated costs to complete, as of December 31 963,190 –0– Billings during the year 426,000 2,170,000 Collections during the year 343,000 1,520,000 (a) New attempt is in progress. Some of the new entries may impact the last attempt grading.Your answer is incorrect. What...
Indiana Co. began a construction project in 2018 with a contract price of $162 million to...
Indiana Co. began a construction project in 2018 with a contract price of $162 million to be received when the project is completed in 2020. During 2018 Indiana Incurred $32 million of costs and estimates and additional $85 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Supposed that in 2019, Indiana Incurred additional costs of $63 million...