The Leto Construction Company began work on a $12,000 contract
on 1/1/15. Planned completion was in 2017. The Percentage-of
Completion method is used.
.......................................................................2015.................2016................2017......
costs incurred to date................................$2,500...............4,200................11,550....
estimated costs to complete......................$7500...............6300................0...........
billing to date...............................................$4000................5100................12,000....
collection to date........................................3800..................5000................11900....
The Gross Profit or (loss) recognized in 2017 is:
Select one:
a. $(150)
b. $150
c. $450
d. $(450)
Gross profit recognized in 2015 = (Costs to date / Estimated total costs * Expected profit) - Previously recognized profits
= [$2,500 / ($2,500 + $7,500) * ($12,000 - $2,500 - $7,500)] - $0
= $2,500 / $10,000 * $2,000 - $0
= $500
Gross profit recognized in 2016 = (Costs to date / Estimated total costs * Expected profit) - Previously recognized profits
= [$4,200 / ($4,200 + $6,300) * ($12,000 - $4,200 - $6,300)] - $500
= $4,200 / $10,500 * $1,500 - $500
= $100
Gross profit recognized in 2017 = (Costs to date / Estimated total costs * Expected profit) - Previously recognized profits
= [$11,550 / $11,550 * ($12,000 - $11,550)] - $500 - $100
= $(150)
The answer is Option a
Get Answers For Free
Most questions answered within 1 hours.