Question

On January 1, Year 1, a contractor began work on a $3.2 million construction contract that...

On January 1, Year 1, a contractor began work on a $3.2 million construction contract that is expected to be completed in 3 years. The contractor concludes that it is appropriate to recognize revenue over time using the input method based on costs incurred (cost-to-cost method). At the inception date, the estimated cost of construction was $2.4 million. The following data relate to the actual and expected construction costs:

Year 1 Year 2 Year 3
Cost incurred $720,000 $1,170,000 $1,110,000
Expected future costs $1,680,000 $810,000 $0

For this long-term construction contract, the contractor needs to calculate the estimated dollar values of the revenue and gross profit (loss) to be recognized each year.

Complete the contractor's long-term construction contract using the information above. Enter the appropriate amounts in the associated cells. Indicate losses by using a leading minus (-) sign. Round all amounts to the nearest dollar. If no entry is necessary, enter a zero (0).

Revenue Gross Profit (loss)
Year 1
Year 2
Year 3

Homework Answers

Answer #1

Solution:

Computation of % of completion, revenue recognition and Gross Profit
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G-A)
1 $720,000 $720,000 $2,400,000 30.00% $3,200,000 $960,000 $960,000 $240,000
2 $1,170,000 $1,890,000 $2,700,000 70.00% $3,200,000 $2,240,000 $1,280,000 $110,000
3 $1,110,000 $3,000,000 $3,000,000 100.00% $3,200,000 $3,200,000 $960,000 -$150,000
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract price was $1,600,000. The Job was completed in 2018.                                                                                 2016                       2017                       2018 Costs incurred to date                                    400000                  935000                  1070000 Estimated costs to complete                       700000                  165000                  0 Billings to date                                                  300000                  900000                  1600000 Collections to date                                           270000                  810000                  1525000 Compute the amount of Gross Profit to be recognized for 2016 and 2017 assuming that ole is required to recognize revenue overtime. Compute the...
A construction company entered into a fixed-price contract to build an office building for $12 million....
A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract?
Indiana Co. began a construction project in 2021 with a contract price of $165 million to...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to be received when the project is completed in 2023. During 2021, Indiana incurred $30 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $65 million...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to be received when the project is completed in 2023. During 2021, Indiana incurred $32 million of costs and estimates an additional $87 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $52 million and estimated...
Georgia Co. began a construction project in 2021 with a contract price of $162 million to...
Georgia Co. began a construction project in 2021 with a contract price of $162 million to be received when the project is completed in 2023. During 2021, Georgia incurred $30 million of costs and estimates an additional $82 million of costs to complete the project. Georgia recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed.    In 2022, Georgia incurred additional costs of $59 million and...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $88 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Multiple Choice: A) Recognized $36.00 million loss on the project in...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $30 million of costs and estimates an additional $83 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $50 million and estimated...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to...
Ayayai Construction Company began operations on January 1, 2020. During the year, Ayayai Construction entered into...
Ayayai Construction Company began operations on January 1, 2020. During the year, Ayayai Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Ayayai estimated that it would take 5 years to complete the facility at a total cost of $4,498,000. The total contract price for construction of the facility is $6,045,000. During the year, Ayayai incurred $1,184,040 in construction costs related to the construction project. The estimated cost to complete the contract is...