Question

Big Wheel Construction had the following two construction projects which began in year​ 1: Project 1...

Big Wheel Construction had the following two construction projects which began in year​ 1:

Project 1

Project 2

Contract price

$690,000

$425,000

Costs incurred during year 1

200,000

225,000

Estimated costs to complete

400,000

225,000

Billed to customers during year 1

230,000

175,000

Received from customers during year 1

100,000

150,000

What amount of gross profit​ (loss) would Big Wheel report on its year 1 income​ statement?

Percentage of Completion

Completed Contract

A.

​$17,500

​$(12,500)

B.

​$5,000

​$(25,000)

C.

​$5,000

​$(12,500)

D.

​$17,500

​$(25,000)

Homework Answers

Answer #1

Solution: Option-1
Explanation:

   Project-1   Project-2     
Total price   690,000   425000     
Minus: Projected cost   600,000   450000     
Profit   90,000   -25000     
             
Recognized profit:   30,000   -12500     
(200,000 / (200,000 + 400,000) * 90,000 = 30,000             
(225,000 / (225000 + 225000) * -25000 = -12500             

Gross profit​ (loss) Big Wheel report on Year-1 income​ statement: 30,000 - 12500 = 17500; 12,500

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Ayayai Construction Company began operations on January 1, 2020. During the year, Ayayai Construction entered into...
Ayayai Construction Company began operations on January 1, 2020. During the year, Ayayai Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Ayayai estimated that it would take 5 years to complete the facility at a total cost of $4,498,000. The total contract price for construction of the facility is $6,045,000. During the year, Ayayai incurred $1,184,040 in construction costs related to the construction project. The estimated cost to complete the contract is...
During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m....
During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m. ESAU incurred costs of $4m in 2018 and estimated at the end of the year that the remaining costs to complete the job would be $5.5m. During 2019 the company expended $3.0m and at year-end estimated that an additional $3.5m of costs would be incurred in 2020 to finish the project. Assuming that ESAU books $3.0m of expenses for this project in 2019, provide...
During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m....
During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m. ESAU incurred costs of $4m in 2018 and estimated at the end of the year that the remaining costs to complete the job would be $5.5m. During 2019 the company expended $3.0m and at year-end estimated that an additional $3.5m of costs would be incurred in 2020 to finish the project. Assuming that ESAU books $3.0m of expenses for this project in 2019, provide...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017                                                                                                                                                              $35 million Construction in progress (as of 12/31/2017)                                                                                                   $50 million Accounts Receivable from construction billings (as of...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017     $35 million Construction in progress (as of 12/31/2017)                                                                                                    $50 million Accounts Receivable from construction billings (as...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
Consider the following two mutually exclusive projects: Year Project A Project B 0 -180,000 -18,000 1...
Consider the following two mutually exclusive projects: Year Project A Project B 0 -180,000 -18,000 1 60,000 15,000 2 100,000 15,000 3 150,000 12,000 Calculate the internal rate of return, and net present value. Assume a discount rate of 15%. Which project should be selected?
Use the following data to select one best answer to the following question: What is the...
Use the following data to select one best answer to the following question: What is the gross profit for the low-rise office building project by applying Completed Contract method without absorption? A construction company began operations on January 2, 2010. During the year the company was awarded one construction contract of low-rise office building. The company incurred $100,000 operating expenses for the year for which $75,000 has been paid while the balance is owed as of December 31, 2010. Project...
Consider a proposal to invest $8.55 million into a stretch of wild river preservation in Wyoming....
Consider a proposal to invest $8.55 million into a stretch of wild river preservation in Wyoming. The project would require periodic capital expenditures as well as annual maintenance expenditures. Benefits from river restoration range from current recreational use to flood prevention to potential future fishing and floating benefits as well as societal benefits from knowing wild stretches of river exist and will be passed on to future generations. Following current best practices for benefit estimation, the following set of costs...
Use the following data to select one best answer to the following question: Which method shall...
Use the following data to select one best answer to the following question: Which method shall be used to determine percent complete for the low-rise office building project? A construction company began operations on January 2, 2010. During the year the company was awarded one construction contract of low-rise office building. The company incurred $100,000 operating expenses for the year for which $75,000 has been paid while the balance is owed as of December 31, 2010. Project data is summarized...