Question

Given this net requirements schedule for a product for the next six weeks, if it cost...

Given this net requirements schedule for a product for the next six weeks, if it cost $3,000 to set up the production line to produce this product and it costs $6 to carry one unit of the product in inventory for one week, develop a schedule of completed production lots for the product and compute the cost of your schedule by using these methods:

Week (Net Requirements)

1 (500

2 (700)

3 (500)

4 (700)

5 (400)

6 (600)

a. Lot-for-lot (LFL)

b. Economic order quantity (EOQ).

c. Period order quantity (POQ).

You may disregard the effects of initial inventory and safety stock on your calculations.  

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 85 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 20 55 10 22 70 87 19 63 210 58 Use the least total cost and the least unit cost lot-sizing methods to determine...
The time-phased net requirements for the base assembly in a table lamp over the next six...
The time-phased net requirements for the base assembly in a table lamp over the next six weeks are: Week 1 2 3 4 5 6 Requirements 335 240 180 340 320 200 The setup cost for the construction of the base assembly is $200, and the holding cost is $0.30 per assembly per week. What lot sizing do you obtain from the EOQ formula? Determine the lot sizes using the Silver–Meal heuristic. Determine the lot sizes using the least unit...
Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7...
Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7 8 Gross requirements 0 200 200 500 0 400 0 400 Beginning inventory = 500 units Setup cost = $500 per setup Lead time = 1 week Holding cost = $3 per unit per week a. Develop the lot-for-lot MRP table. b. Calculate the total relevant costs. Answer: Period 1 2 3 4 5 6 7 8 Gross requirements 0 200 200 500 0...
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $9. There is a carrying cost of $0.02 per unit per week. Beginning inventory is 75 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 20 10 15 45 10 30 90 20 45 160 Use the least total cost lot-sizing method to determine the quantity to order with...
Product Y is made from one component P, three components Q, and one 2 components R.  P...
Product Y is made from one component P, three components Q, and one 2 components R.  P is made from two parts S, Q is made from one S, and R is made from two part S and three part T.  Other data includes: Part                 Lead time             Lot size                   On hand                 Scheduled receipts         Safety Stock Y                         1                                 lot-for-lot               30                                              none                                          5 P                        2                                   40                              15                                              none                                          none Q                        2                                 100                               8                                               none                                          8 R                        3                                 120                             30                                              none                                          none S                         2                                 500                             20                                              500, week 1                          20 T                         2                                 600                           370                                             none                                          50 a.    Draw the BOM for product Y. b. Complete the MRP explosion for product Y.  Identify any problems, and discuss possible solutions Master Production Schedule Finished...
Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the...
Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the time-phased inventory status record below. Its lead time is 3 weeks. Item D 1 2 3 4 5 6 Gross Requirements 100 300 100 400 100 50 On Hand/ Scheduled Receipts 700 Net Requirements A Planned Order Releases B The value of entry A is: A. 100 B. 200 C. 300 D. 700 E. None of the above. Reset Selection Question 19 Product D...
Calculate the cost of operating under the different MRP lot sizing techniques: Lot-for-Lot (L4L) Economic Order...
Calculate the cost of operating under the different MRP lot sizing techniques: Lot-for-Lot (L4L) Economic Order Quantity (EOQ) Least Total Cost (LTC) Least Unit Cost (LUC) Compare your results and state which method is the most cost efficient in this situation. Consider the following MRP lot sizing problem: Cost per item $50 Order/setup cost $75 Inventory carrying cost per item per week $1 Weekly net requirements: 1 2 3 4 5 6 7 8 75 90 100 90 80 95...
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
McCartney Company produces a number of products and provides the following information: Annual demand for Product...
McCartney Company produces a number of products and provides the following information: Annual demand for Product C 20,000 Cost of setting up to make Product C $45 Cost of carrying one unit of Product C in inventory $5 Currently, McCartney produces 1,000 units of Product C per production run. Inventory-related cost for Product C under the current inventory policy is a.$900. b.$2,500. c.$3,400. d.$45,000. e.$100,000. The economic order quantity (EOQ) for Product C is a.500. b.600. c.700. d.800. What is...