Week |
1 |
2 |
3 |
4 |
5 |
6 |
Requirements |
335 |
240 |
180 |
340 |
320 |
200 |
The setup cost for the construction of the base assembly is $200, and the holding cost is $0.30 per assembly per week.
ANSWER :- (a) first we have to understand what is EOQ.
EOQ is known as Economic Order Quantity. In accounting EOQ is the order quantity that minimizes the total holding costs & ordering costs.
here we have to find lot size from eoq formula.
set up cost is $200.
holding cost is $0.30 per assembly per week.
EOQ =
Where
D = annual requirement of lot
= 335+240+180+340+320+200 *52 week per year/6 week
= 3997.
K = no of week
= 6
h = holding cost per unit
= $0.30*52
=15.6 units /year
so EOQ =^2*3997*6/15.6
= 374.61 unit/ year
= 375 units/year ( rounded off)
SO WITH EOQ Formula lot size is 375 unit.