Question

Budgeted Variable overhead for the year is $120000. Expected activity is 20000 standard direct labour hours....

Budgeted Variable overhead for the year is $120000. Expected activity is 20000 standard direct labour hours. Actual hours work were 18000 and standard hours allowed for actual production were 19500.

What is the variable overhead efficiency variance?

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour...
Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour hours as the cost driver to apply overhead costs. The following amounts were budgeted for the year: Planned production—units 50 000 Direct labour hours 200 000 Variable overhead $ 1 000 000 Fixed overhead $ 600 000 The following were the actual results Actual production—units 48 000 Direct labour hours 195 000 Variable overhead $ 950 000 Fixed overhead $ 610 000 Calculate the...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per direct labour hour. The overhead rate is based on 10,600 hours. Actual results were: Standard direct labour hours allowed 9,070 Actual direct labour hours 10,600 Fixed overhead $179,000 Variable overhead $174,400 Calculate the fixed overhead production volume variance. Fixed overhead production volume variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate the variable overhead spending variance. Variable overhead spending variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,900 units. Manufacturing overhead is budgeted at $124,600 for the period (20% of this cost is fixed). The 16,830 hours worked during the period resulted in the production of 8,240 units. The variable manufacturing overhead cost incurred was $101,200 and the fixed manufacturing overhead cost was $28,900. a.Calculate the variable overhead...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,300 units. Manufacturing overhead is budgeted at $124,500 for the period (20% of this cost is fixed). The 16,290 hours worked during the period resulted in the production of 8,000 units. The variable manufacturing overhead cost incurred was $100,800 and the fixed manufacturing overhead cost was $28,400. Calculate the variable overhead...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,730 hours worked during the period resulted in the production of 8,190 units. The variable manufacturing overhead cost incurred was $98,300 and the fixed manufacturing overhead cost was $28,100. 1.Calculate the variable overhead...
Maxima Corp. uses a standard cost system with machine-hours as the activity base for both variable...
Maxima Corp. uses a standard cost system with machine-hours as the activity base for both variable and fixed manufacturing overhead (VMOH & FMOH). The following information relates to production for last year: Variable Fixed Total budgeted overhead (at the denominator level of activity) $14,000 ? Total applied overhead $15,400 $28,600 Total actual overhead $15,700 $31,800 The actual machine-hours incurred were 2,300. VMOH Efficiency Variance was $700 Unfavorable. What was Maxima's FMOH Volume Variance?
Maxima Corp. uses a standard cost system with machine-hours as the activity base for both variable...
Maxima Corp. uses a standard cost system with machine-hours as the activity base for both variable and fixed manufacturing overhead (VMOH & FMOH). The following information relates to production for last year: Variable Fixed Total budgeted overhead (at the denominator level of activity) $14,000 ? Total applied overhead $15,400 $28,600 Total actual overhead $15,700 $31,800 The actual machine-hours incurred were 2,300. VMOH Efficiency Variance was $700 Unfavorable. What was Maxima's FMOH Volume Variance?
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills for the coming year. The company uses direct labour hours to assign overhead to products. Each drill requires 0.5 standard hour of labour for completion. The total budgeted overhead was $2,700,000. The total fixed overhead budgeted for the coming year is $1,320,000. Predetermined overhead rates are calculated using expected production, measured in direct labour hours. Actual results for the year are: Actual production (units)   ...
GreatGreat Fender allocates manufacturing overhead to production based on standard direct labor hours. GreatGreat Fender reported...
GreatGreat Fender allocates manufacturing overhead to production based on standard direct labor hours. GreatGreat Fender reported the following actual results for 2016​: actual number of fenders​ produced ,20,000​; actual variable​ overhead,$5,300​; actual fixed​ overhead,$27,000​; actual direct labor​ hours,370. Read the requirements . Requirement 1. Compute the overhead variances for the​ year: variable overhead cost​ variance, variable overhead efficiency​ variance, fixed overhead cost​ variance, and fixed overhead volume variance. Begin with the variable overhead cost and efficiency variances. Select the required​...
GreatGreat Fender allocates manufacturing overhead to production based on standard direct labor hours. GreatGreat Fender reported...
GreatGreat Fender allocates manufacturing overhead to production based on standard direct labor hours. GreatGreat Fender reported the following actual results for 2016​: actual number of fenders​ produced ,20,000​; actual variable​ overhead,$5,300​; actual fixed​ overhead,$27,000​; actual direct labor​ hours,370. Read the requirements . Requirement 1. Compute the overhead variances for the​ year: variable overhead cost​ variance, variable overhead efficiency​ variance, fixed overhead cost​ variance, and fixed overhead volume variance. Begin with the variable overhead cost and efficiency variances. Select the required​...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT