Question

Maxima Corp. uses a standard cost system with machine-hours as the activity base for both variable...

Maxima Corp. uses a standard cost system with machine-hours as the activity base for both variable and fixed manufacturing overhead (VMOH & FMOH). The following information relates to production for last year:

Variable Fixed
Total budgeted overhead (at the denominator level of activity) $14,000 ?
Total applied overhead $15,400 $28,600
Total actual overhead $15,700 $31,800

The actual machine-hours incurred were 2,300. VMOH Efficiency Variance was $700 Unfavorable.

What was Maxima's FMOH Volume Variance?

Homework Answers

Answer #1
Variable Overhead applied = standard rate * actual hours
$15400 =standard rate * 2300 hours
Standard Rate =6.6957
Budgeted hours = Budgeted Overhead /* standard rate
=$14000/6.6957
=2091 hours
Standard Rate for fixed overhead = $28600/2300
=$12.43478
Budgeted Fixed overhead =$12.43478*2091
=$26000
Fixed overhead volume variance = Overhead Incurred - Budgeted Overhead
=$26000-28600
=$2600 ( Favorable)
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Maxima Corp. uses a standard cost system with machine-hours as the activity base for both variable...
Maxima Corp. uses a standard cost system with machine-hours as the activity base for both variable and fixed manufacturing overhead (VMOH & FMOH). The following information relates to production for last year: Variable Fixed Total budgeted overhead (at the denominator level of activity) $14,000 ? Total applied overhead $15,400 $28,600 Total actual overhead $15,700 $31,800 The actual machine-hours incurred were 2,300. VMOH Efficiency Variance was $700 Unfavorable. What was Maxima's FMOH Volume Variance?
Question 4: Eric Co. uses machine hours to apply standard overhead cost to production. The following...
Question 4: Eric Co. uses machine hours to apply standard overhead cost to production. The following data pertain to October: Master budget data: Units 2,500 Total machine hours (denominator volume) 100,000 Total variable overhead cost $ 250,000 Total fixed overhead cost $ 50,000 Actual operating results: Variable overhead cost incurred $ 265,000 Fixed overhead cost incurred $ 54,000 Units manufactured 2,250 Total machine hours 96,000 Required: Compute the following variances using machine hours as the activity variable used to assign...
The following information is available for Baxter Manufacturing for April: Actual machine hours 980 Standard machine...
The following information is available for Baxter Manufacturing for April: Actual machine hours 980 Standard machine hours allowed 1,040 Denominator activity (machine hours) 1,700 Actual fixed overhead costs $ 6,600 Budgeted fixed overhead costs $ 6,800 Predetermined overhead rate ($1 variable + $4 fixed) $ 5 Is the fixed overhead price (spending) variance for April favorable or unfavorable? show work
Rodarta Corporation applies manufacturing overhead to products on the basis of standard machine-hours. The company's predetermined...
Rodarta Corporation applies manufacturing overhead to products on the basis of standard machine-hours. The company's predetermined overhead rate for fixed manufacturing overhead is $4.10 per machine-hour and the denominator level of activity is 4,300 machine-hours. In the most recent month, the total actual fixed manufacturing overhead was $17,730 and the company actually worked 4,230 machine-hours during the month. The standard hours allowed for the actual output of the month totaled 4,250 machine-hours. What was the overall fixed manufacturing overhead volume...
Answer questions 18-21 using the information below: Thinnews Co., uses machine hours to allocate manufacturing overhead...
Answer questions 18-21 using the information below: Thinnews Co., uses machine hours to allocate manufacturing overhead cost to outputs: Actual total overhead cost incurred $ 24,000 Actual fixed overhead cost incurred $ 10,000 Budgeted fixed overhead cost $ 11,000 Actual machine hours 5,000 Standard machine hours allowed for the units manufactured 4,800 Denominator level — machine hours 5,500 Standard variable overhead rate per machine hour $ 3.00 What is variable overhead spending variance? Group of answer choices $960 favorable $1,000...
Wangerin Corporation applies overhead to products based on machine-hours. The denominator level of activity is 8,700...
Wangerin Corporation applies overhead to products based on machine-hours. The denominator level of activity is 8,700 machine-hours. The budgeted fixed manufacturing overhead costs are $319,290. In April, the actual fixed manufacturing overhead costs were $325,380 and the standard machine-hours allowed for the actual output were 9,000 machine-hours. Required: a. Compute the budget variance for April. b. Compute the volume variance for April. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no...
Wangerin Corporation applies overhead to products based on machine-hours. The denominator level of activity is 7,300...
Wangerin Corporation applies overhead to products based on machine-hours. The denominator level of activity is 7,300 machine-hours. The budgeted fixed manufacturing overhead costs are $257,690. In April, the actual fixed manufacturing overhead costs were $262,800 and the standard machine-hours allowed for the actual output were 7600 machine-hours. Required: a. Compute the budget variance for April. b. Compute the volume variance for April. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no...
Citi Company uses a standard cost system in which manufacturing overhead is applied to units of...
Citi Company uses a standard cost system in which manufacturing overhead is applied to units of product on the basis of standard machine-hours. During February, the company used a denominator activity of 60,000 machine-hours in computing its predetermined overhead rate. However, 75,000 standard machine-hours were allowed for the month's actual production. If the fixed manufacturing overhead volume variance for February was $6,800 unfavorable, then the total budgeted fixed manufacturing overhead cost for the month was (closest to ) Select one:...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $7.50 Standard fixed-overhead rate per hour: $12.40 Planned activity during the period: 19,000 machine hours Actual production: 12,200 finished units Machine-hour standard: Two completed units per machine hour Actual variable overhead: $153,180 Actual total overhead: $432,900 Actual machine hours worked: 22,200 Required: 1. Calculate the...
Neptune Inc. uses a standard cost system and has the following information for the most recent...
Neptune Inc. uses a standard cost system and has the following information for the most recent month, April: Actual direct labor hours (DLHs) worked 17,000 Standard direct labor hours allowed for good output produced this period 18,000 Actual total factory overhead costs incurred $45,400 Budgeted fixed factory overhead costs $10,800 Denominator activity level, in direct labor hours (DLHs) 15,000 Total factory overhead application rate per standard direct labor hour $2.70 The variable factory overhead efficiency variance for Neptune, Inc. in...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT