Question

Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour...

Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour hours as the cost driver to apply overhead costs. The following amounts were budgeted for the year:

Planned production—units

50 000

Direct labour hours

200 000

Variable overhead

$

1 000 000

Fixed overhead

$

600 000

The following were the actual results

Actual production—units

48 000

Direct labour hours

195 000

Variable overhead

$

950 000

Fixed overhead

$

610 000

Calculate the amount of variable overhead efficiency variance

Homework Answers

Answer #1

Solution: Variable overhead efficiency variance = (Standard hours for Actual Output - Actual hours) * Standard Variable Overhead rate per hour

According to the question

Budgeted production = 50,000 units

Budgeted Hours = 200,000 hours

Budgeted Variable Overhead = $1,000,000

Actual production = 48,000 units

Actual Hours = 195,000 hours

Actual Variable Overhead = $950,000

Standard Variable Overhead rate per hour = Budgeted variable overhead / Budgeted hours

= $1,000,000 / 200,000 = $5 per hour

Standard Hours for Actual Output = Budgeted Hours * (Actual production / Budgeted production)

= 200,000 hours * (48,000 / 50,000)

= 200,000 hours * 0.96 = 192,000 hours

Then,

Variable overhead efficiency variance = (192,000 hours - 195,000 hours) * $5 per hour

= -$15,000 or $15,000 Adverse

Please rate positive and comment in case of any doubt. I would be happy to help you further.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Waymire Ltd. currently uses a traditional costing system based on direct labour hours to allocate overhead....
Waymire Ltd. currently uses a traditional costing system based on direct labour hours to allocate overhead. This year, the company has budgeted to produce 1721 units of one of its products. Each unit requires 4 hours of direct labour. For the coming year, the company is considering changing to an activity based costing system by allocating overhead based on 3 activities. The following are the activities, budgeted total cost and cost drivers per activity for the upcoming year: Activity Cost...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,900 units. Manufacturing overhead is budgeted at $124,600 for the period (20% of this cost is fixed). The 16,830 hours worked during the period resulted in the production of 8,240 units. The variable manufacturing overhead cost incurred was $101,200 and the fixed manufacturing overhead cost was $28,900. a.Calculate the variable overhead...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per direct labour hour. The overhead rate is based on 10,600 hours. Actual results were: Standard direct labour hours allowed 9,070 Actual direct labour hours 10,600 Fixed overhead $179,000 Variable overhead $174,400 Calculate the fixed overhead production volume variance. Fixed overhead production volume variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate the variable overhead spending variance. Variable overhead spending variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,730 hours worked during the period resulted in the production of 8,190 units. The variable manufacturing overhead cost incurred was $98,300 and the fixed manufacturing overhead cost was $28,100. 1.Calculate the variable overhead...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,300 units. Manufacturing overhead is budgeted at $124,500 for the period (20% of this cost is fixed). The 16,290 hours worked during the period resulted in the production of 8,000 units. The variable manufacturing overhead cost incurred was $100,800 and the fixed manufacturing overhead cost was $28,400. Calculate the variable overhead...
Budgeted Variable overhead for the year is $120000. Expected activity is 20000 standard direct labour hours....
Budgeted Variable overhead for the year is $120000. Expected activity is 20000 standard direct labour hours. Actual hours work were 18000 and standard hours allowed for actual production were 19500. What is the variable overhead efficiency variance?
Chocolate, Inc., uses a standard costing system and develops its overhead rates from the current annual...
Chocolate, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 145,000 units requiring 620,000 direct labor hours. (Practical capacity is 630,000 hours.) Annual budgeted overhead costs total $802,600, of which $585,800 is fixed overhead. A total of 143,400 units using 619,200 direct labor hours were produced during the year. Actual variable overhead costs for the year were $275,800, and actual fixed overhead costs...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 125,000 units requiring 500,000 direct labor hours. (Practical capacity is 520,000 hours.) Annual budgeted overhead costs total $830,000, of which $585,000 is fixed overhead. A total of 119,100 units using 498,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,100, and...
The Clark Company makes a single product and uses standard costing. Some data concerning this product...
The Clark Company makes a single product and uses standard costing. Some data concerning this product for the month of May follow: Labour rate variance $7,000 favourable Labour efficiency variance $12,000 favourable Variable overhead efficiency variance $4,000 favourable Number of units produced 10,000 Standard labour rate per direct labour hour $12 Standard variable overhead rate per direct labour hour $4 Actual labour hours used 14,000 Actual variable manufacturing overhead costs $58,290 1) What was the variable overhead spending variance for...
Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual...
Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 120,000 units requiring 480,000 direct labor hours. (Practical capacity is 500,000 hours.) Annual budgeted overhead costs total $739,200, of which $532,800 is fixed overhead. A total of 119,400 units using 478,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $241,900, and actual fixed overhead costs...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT