Question

Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...

Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,900 units. Manufacturing overhead is budgeted at $124,600 for the period (20% of this cost is fixed). The 16,830 hours worked during the period resulted in the production of 8,240 units. The variable manufacturing overhead cost incurred was $101,200 and the fixed manufacturing overhead cost was $28,900.

a.Calculate the variable overhead spending variance for the period.

b.Calculate the variable overhead efficiency (quantity) variance for the period.

c.Calculate the fixed overhead budget (spending) variance for the period.

d. Calculate the fixed overhead volume variance for the period.

Homework Answers

Answer #1

Budgeted manufacturing overhead = $124600
​Budgeted fixed manufacturing overhead = $124600 x 20% = $24920
Budgeted variable manufacturing overhead = $124600 x 80% = $99680

Budgeted hours = 8900 units x 2 = 17800 hrs
​Standard variable overhead rate = 99680 / 17800 = $5.60
​Recovery rate per hour of fixed overheads = 24920 / 17800 = $1.40

Standard hours = 8240 units x 2 hrs per unit = 16480 hrs
​Actual rate of variable overheads = $101200 / 16830 = $6.01

1. Variable overhead spending variance​ = (SR - AR) x AH
= [$5.60 - (101200 / 16830)] x 16830
= $6952 U

2. Variable overhead efficiency variance​ = (SH - AH) x SR
​= (16480 - 16830) x $5.60
​= $1960 U

3. Fixed overhead budget variance = Budgeted fixed overhead - Actual fixed overhead
​= $24920 - 28900
​= $3980 U

4. Fixed overhead volume variance = Recovered - Budgeted fixed overhead
​= (16480 x $1.40) - $24920
= $848 U

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,730 hours worked during the period resulted in the production of 8,190 units. The variable manufacturing overhead cost incurred was $98,300 and the fixed manufacturing overhead cost was $28,100. 1.Calculate the variable overhead...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,300 units. Manufacturing overhead is budgeted at $124,500 for the period (20% of this cost is fixed). The 16,290 hours worked during the period resulted in the production of 8,000 units. The variable manufacturing overhead cost incurred was $100,800 and the fixed manufacturing overhead cost was $28,400. Calculate the variable overhead...
Lamp Light Limited (LLL) manufactures lampshades. It applies variable overhead on the basis of direct labor...
Lamp Light Limited (LLL) manufactures lampshades. It applies variable overhead on the basis of direct labor hours. Information from LLL’s standard cost card follows: Standard Quantity Standard Rate Standard Unit Cost Variable manufacturing overhead 0.6 $0.80 $0.48 During August, LLL had the following actual results: Units produced and sold 22,100 Actual variable overhead $ 9,490 Actual direct labor hours 16,000 Lamp Light Limited (LLL) calculates a fixed overhead rate based on budgeted fixed overhead of $60,300 and budgeted production of...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows:   Direct materials: 5 kg at $8.00 per kg $ 40.00     Direct labour: 3 hours at $15 per hour 45.00     Variable overhead: 3 hours at $9 per hour 27.00     Total standard cost per unit $ 112.00   The company planned to produce and sell 21,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $10.00 per kg $ 50.00 Direct labour: 4 hours at $16 per hour 64.00 Variable overhead: 4 hours at $7 per hour 28.00 Total standard cost per unit $ 142.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to the production of 18 000 tiles during the past month. The entity allocates fixed overhead costs at a standard rate of $19 per direct labour hour. Direct Labour: Standard cost is 6 tiles per hour at $24 per hour Actual cost per hour was $24.50 Labour efficiency variance was $6720 F Fixed overhead costs: Estimated = $60,000 Actual = $58,720 Required (a)    How many...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to the production of 18 000 tiles during the past month. The entity allocates fixed overhead costs at a standard rate of $19 per direct labour hour. Direct Labour: Standard cost is 6 tiles per hour at $24 per hour Actual cost per hour was $24.50 Labour efficiency variance was $6720 F Fixed overhead costs: Estimated = $60,000 Actual = $58,720 Required (a)    How many...
The Littlefield Company applies manufacturing overhead costs to products on the basis of direct labor-hours. The...
The Littlefield Company applies manufacturing overhead costs to products on the basis of direct labor-hours. The standard cost card shows that 12 direct labor-hours are required per unit of product. For August, the company budgeted to work 360,000 direct labor-hours and to incur the following total manufacturing overhead costs: Total fixed overhead costs $475,200 Total variable overhead costs $396,000 During August, the company completed 28,000 units of product, worked 344,000 direct labor-hours, and incurred the following total manufacturing overhead costs:...
Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour...
Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour hours as the cost driver to apply overhead costs. The following amounts were budgeted for the year: Planned production—units 50 000 Direct labour hours 200 000 Variable overhead $ 1 000 000 Fixed overhead $ 600 000 The following were the actual results Actual production—units 48 000 Direct labour hours 195 000 Variable overhead $ 950 000 Fixed overhead $ 610 000 Calculate the...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $5 per hour 15.00 Total standard cost per unit $ 105.00 The company planned to produce and sell 19,000 units in March. However, during March the company actually produced and...