Question

Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...

Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,300 units. Manufacturing overhead is budgeted at $124,500 for the period (20% of this cost is fixed). The 16,290 hours worked during the period resulted in the production of 8,000 units. The variable manufacturing overhead cost incurred was $100,800 and the fixed manufacturing overhead cost was $28,400.

Calculate the variable overhead spending variance for the period.
Variable overhead spending variance $

Neither favourable nor unfavourableFavourableUnfavourable

Calculate the variable overhead efficiency (quantity) variance for the period.
Variable overhead efficiency variance $

FavourableNeither favourable nor unfavourableUnfavourable

Calculate the fixed overhead budget (spending) variance for the period.
Fixed overhead budget variance $

Neither favourable nor unfavourableUnfavourableFavourable

Calculate the fixed overhead volume variance for the period.
Fixed overhead volume variance $

Neither favourable nor unfavourableFavourableUnfavourable

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,730 hours worked during the period resulted in the production of 8,190 units. The variable manufacturing overhead cost incurred was $98,300 and the fixed manufacturing overhead cost was $28,100. 1.Calculate the variable overhead...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,900 units. Manufacturing overhead is budgeted at $124,600 for the period (20% of this cost is fixed). The 16,830 hours worked during the period resulted in the production of 8,240 units. The variable manufacturing overhead cost incurred was $101,200 and the fixed manufacturing overhead cost was $28,900. a.Calculate the variable overhead...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per direct labour hour. The overhead rate is based on 10,600 hours. Actual results were: Standard direct labour hours allowed 9,070 Actual direct labour hours 10,600 Fixed overhead $179,000 Variable overhead $174,400 Calculate the fixed overhead production volume variance. Fixed overhead production volume variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate the variable overhead spending variance. Variable overhead spending variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate...
GreatGreat Fender allocates manufacturing overhead to production based on standard direct labor hours. GreatGreat Fender reported...
GreatGreat Fender allocates manufacturing overhead to production based on standard direct labor hours. GreatGreat Fender reported the following actual results for 2016​: actual number of fenders​ produced ,20,000​; actual variable​ overhead,$5,300​; actual fixed​ overhead,$27,000​; actual direct labor​ hours,370. Read the requirements . Requirement 1. Compute the overhead variances for the​ year: variable overhead cost​ variance, variable overhead efficiency​ variance, fixed overhead cost​ variance, and fixed overhead volume variance. Begin with the variable overhead cost and efficiency variances. Select the required​...
GreatGreat Fender allocates manufacturing overhead to production based on standard direct labor hours. GreatGreat Fender reported...
GreatGreat Fender allocates manufacturing overhead to production based on standard direct labor hours. GreatGreat Fender reported the following actual results for 2016​: actual number of fenders​ produced ,20,000​; actual variable​ overhead,$5,300​; actual fixed​ overhead,$27,000​; actual direct labor​ hours,370. Read the requirements . Requirement 1. Compute the overhead variances for the​ year: variable overhead cost​ variance, variable overhead efficiency​ variance, fixed overhead cost​ variance, and fixed overhead volume variance. Begin with the variable overhead cost and efficiency variances. Select the required​...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg of plastic at $5 per kilogram) $10.00 Direct labour (2 hours at $12 per hour) 24.00 Variable manufacturing overhead 11.45 Fixed manufacturing overhead 7.05 Total standard cost per unit $52.50 Actual costs for producing 2,710 units were as follows: Direct materials used 5,990 kg Direct materials purchased (6,440 kg) $30,912 Direct labour (6,820 hours) $68,882 Variable manufacturing costs $32,300 Fixed manufacturing costs $17,600 Calculate...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to the production of 18 000 tiles during the past month. The entity allocates fixed overhead costs at a standard rate of $19 per direct labour hour. Direct Labour: Standard cost is 6 tiles per hour at $24 per hour Actual cost per hour was $24.50 Labour efficiency variance was $6720 F Fixed overhead costs: Estimated = $60,000 Actual = $58,720 Required (a)    How many...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to the production of 18 000 tiles during the past month. The entity allocates fixed overhead costs at a standard rate of $19 per direct labour hour. Direct Labour: Standard cost is 6 tiles per hour at $24 per hour Actual cost per hour was $24.50 Labour efficiency variance was $6720 F Fixed overhead costs: Estimated = $60,000 Actual = $58,720 Required (a)    How many...
Aaha Inc. produces premium protective automotive covers. The direct materials and direct labour standards for one...
Aaha Inc. produces premium protective automotive covers. The direct materials and direct labour standards for one car cover are as follows: Standard Quantity or Hours Standard Price or Rate Standard Cost   Direct materials 9.0 metres of cloth $ 10 per metre $ 90.00   Direct labour 0 hours $ 20 per hour $ 7   Variable overhead 0 hours $ 8 per hour $ 3 Budgeted fixed overhead cost is $17,400, and the normal production volume is 2,885 car covers. Overhead is...
If overhead is applied to production using direct labor hours and the direct labor efficiency variance...
If overhead is applied to production using direct labor hours and the direct labor efficiency variance is favorable, then the variable overhead efficiency variance is: favorable unfavorable either favorable or unfavorable. neither favorable nor unfavorable.