Question

Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...

Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,730 hours worked during the period resulted in the production of 8,190 units. The variable manufacturing overhead cost incurred was $98,300 and the fixed manufacturing overhead cost was $28,100.

1.Calculate the variable overhead spending variance for the period. Favourable or unfavourable ?

2.Calculate the variable overhead efficiency (quantity) variance for the period. Favourable or unfavourable ?

3.Calculate the fixed overhead budget (spending) variance for the period.Favourable or unfavourable ?

4. Calculate the fixed overhead volume variance for the period.Favourable or unfavourable ?

Homework Answers

Answer #1

Solution 1:

Standard rate of variable overhead = ($120,400*80%) / (8600*2) = $5.60 per DLH

Actual rate of variable overhead = $98,300 / 16730 = $5.875672 per DLH

Variable overhead spending variance = (SR - AR) * AH = ($5.60 - $5.875672) * 16730 = $4,612 Unfavorable

Solution 2:

Variable overhead efficiency variance = (SH - AH) * SR = (8190*2 - 16730) * $5.60 = $1,960 unfavorable

Solution 3:

Fixed overhead spending variance = Budgeted fixed overhead - actual fixed overhead = ($120,400*20%) - $28,100

= $4,020 Unfavorable

Solution 4:

Fixed overhead rate = ($120,400*20%) / (8600*2) = $1.40 per DLH

Fixed overhead volume variance = Fixed overhead applied - Budgeted fixed overhead

= (8190*2*$1.40) - ($120,400*20%)

= $1,148 Unfavorable

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,300 units. Manufacturing overhead is budgeted at $124,500 for the period (20% of this cost is fixed). The 16,290 hours worked during the period resulted in the production of 8,000 units. The variable manufacturing overhead cost incurred was $100,800 and the fixed manufacturing overhead cost was $28,400. Calculate the variable overhead...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,900 units. Manufacturing overhead is budgeted at $124,600 for the period (20% of this cost is fixed). The 16,830 hours worked during the period resulted in the production of 8,240 units. The variable manufacturing overhead cost incurred was $101,200 and the fixed manufacturing overhead cost was $28,900. a.Calculate the variable overhead...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg of plastic at $5 per kilogram) $10.00 Direct labour (2 hours at $12 per hour) 24.00 Variable manufacturing overhead 11.85 Fixed manufacturing overhead 6.15 Total standard cost per unit $52.00 Actual costs for producing 2,690 units were as follows: Direct materials used 5,920 kg Direct materials purchased (6,730 kg) $32,304 Direct labour (6,950 hours) $67,415 Variable manufacturing costs $32,200 Fixed manufacturing costs $17,700 1....
Aaha Inc. produces premium protective automotive covers. The direct materials and direct labour standards for one...
Aaha Inc. produces premium protective automotive covers. The direct materials and direct labour standards for one car cover are as follows: Standard Quantity or Hours Standard Price or Rate Standard Cost   Direct materials 9.0 metres of cloth $ 10 per metre $ 90.00   Direct labour 0 hours $ 20 per hour $ 7   Variable overhead 0 hours $ 8 per hour $ 3 Budgeted fixed overhead cost is $17,400, and the normal production volume is 2,885 car covers. Overhead is...
Juliet Pants standard cost per pants included 0.20 direct labour hours per pants at $16.00 per...
Juliet Pants standard cost per pants included 0.20 direct labour hours per pants at $16.00 per hour. Juliet Pants actually used 10,350 direct labour hours at a cost of $15.80 per hour to produce 50,000 pants. a) Calculate the direct labour rate variance: $ b) Is the direct labour rate variance favourable or unfavourable? c) Calculate the direct labour efficiency variance: $ d) Is the direct labour efficiency variance favourable or unfavourable? e) Calculate the total direct labour variance: $...
Sanford Ltd. produces a product with the following standard cost card Variable overhead (9 hours)   $18.91...
Sanford Ltd. produces a product with the following standard cost card Variable overhead (9 hours)   $18.91 The fixed overhead rate is based on a standard monthly volume of 15634 units. The actual results for the month of July 20x5 are as follows: Direct labour (92621 hours) $1023000 Variable overhead $333194 Fixed overhead $580000 Units produced and sold 15383 units What is Sanford’s variable overhead spending variance for July 20x5? Note: a negative number represents an unfavourable variance and a positive...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per direct labour hour. The overhead rate is based on 10,600 hours. Actual results were: Standard direct labour hours allowed 9,070 Actual direct labour hours 10,600 Fixed overhead $179,000 Variable overhead $174,400 Calculate the fixed overhead production volume variance. Fixed overhead production volume variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate the variable overhead spending variance. Variable overhead spending variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate...
Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour...
Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour hours as the cost driver to apply overhead costs. The following amounts were budgeted for the year: Planned production—units 50 000 Direct labour hours 200 000 Variable overhead $ 1 000 000 Fixed overhead $ 600 000 The following were the actual results Actual production—units 48 000 Direct labour hours 195 000 Variable overhead $ 950 000 Fixed overhead $ 610 000 Calculate the...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg of plastic at $5 per kilogram) $10.00 Direct labour (2 hours at $12 per hour) 24.00 Variable manufacturing overhead 11.45 Fixed manufacturing overhead 7.05 Total standard cost per unit $52.50 Actual costs for producing 2,710 units were as follows: Direct materials used 5,990 kg Direct materials purchased (6,440 kg) $30,912 Direct labour (6,820 hours) $68,882 Variable manufacturing costs $32,300 Fixed manufacturing costs $17,600 Calculate...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows:   Direct materials: 5 kg at $8.00 per kg $ 40.00     Direct labour: 3 hours at $15 per hour 45.00     Variable overhead: 3 hours at $9 per hour 27.00     Total standard cost per unit $ 112.00   The company planned to produce and sell 21,000 units in March. However, during March the company actually produced and...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT