Question

ch 15 How is a master production schedule created, and how is it used?

ch 15 How is a master production schedule created, and how is it used?

Homework Answers

Answer #1

Master Production Schedule :- A MPS is plan for individual products to be created in each time interval. It is basically the set-up using which the plan indicates when & how much of each commodity will be demanded & as per that production is carried out. There are various inputs to the schedule creation, such as Forecasting the demand, cost involved in productions, inventory cost, staffing, so that bottlenecks can be identified & a plan can be conducted which yields details about amount of inventories to be managed, staffing to be done etc.

How MPS is created:- As stated above, it is plan which creates outputs that helps in decision making. A set of assigned inputs acts as variable for MPS & a set of outputs is generated accordingly. Inputs might be directly generated with the help of an database & that helps in evaluating the demands with help of sales data. For Example, ERP shows sudden increase in sales of a particular commodity, this acts as input. Now as per sales forecast, the demand is increasing, this is the outcome of the schedule. Basis on the outcome, decision can be made whether we have to raise our production? If yes what is the amount & at what intervals. Inputs usually are production costs, supply, sales information, inventory/shelf cost, customer requirements etc. The outputs which could be yielded are quantity to be available in inventory, production rate, production of quantity etc.

How MPS is used:-

  1. It gives an estimate of capacity planning of commodity.
  2. Strategically align the departments like, planning, forecasting & production.
  3. Increases effectiveness of company’s manufacturing & production.
  4. Proper & practical decisions are made.
  5. Helps in avoiding shortages.
  6. Effecient allocation of resources.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Prepare a master schedule like that shown in Figure 11.11 given this information: The forecast for...
Prepare a master schedule like that shown in Figure 11.11 given this information: The forecast for each week of an eight-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows: Week Customer Orders 1 52 2 35 3 20 4 12 Use a production lot size of 75 units and no beginning inventory. 1.  Prepare a master schedule like that shown in Figure...
describe the relationship among aggregate planning, the master production schedule (MPS) and material requirements planning (MRP)....
describe the relationship among aggregate planning, the master production schedule (MPS) and material requirements planning (MRP). what are the key inputs and outputs for each system? what is the purpose of each of these tools?
A company that makes industrial pumps wants to prepare a master production schedule for June and...
A company that makes industrial pumps wants to prepare a master production schedule for June and July. Market forecast is given below. The weekly demand forecast is given as shown in the table. The customer order (already committed) are also shown. The beginning inventory level is 64. Determine Available-to-promise inventory under the condition that “schedule production when the projected on-hand inventory would be negative without production”. Suppose the production lot size is 70.    June    July 1 2 3...
Regarding the master production schedule (MPS): a. the external suppliers are sent copies of the MPSs...
Regarding the master production schedule (MPS): a. the external suppliers are sent copies of the MPSs in advance. b. the time horizon of the MPSs must equal the time horizon of the selected aggregate plan. c. the capacity requirements of the MPSs must equal or exceed the available capacity of the selected aggregate plan. d. all of the above. e. none of the above.
If the engineer approved the master schedule of the general contractor, is the contractor allowed to...
If the engineer approved the master schedule of the general contractor, is the contractor allowed to change its schedule without informing the engineer? Can the engineer request an updated programme? Explain.
A work plan is created before a project manager estimates the size and schedule of the...
A work plan is created before a project manager estimates the size and schedule of the project.
The engineer has approved the master schedule of the general contractor which reflects a completion date...
The engineer has approved the master schedule of the general contractor which reflects a completion date 10 weeks before the stipulated date in the contract. Shall the engineer plan towards this early completion date? Explain.
9-10 What is an amortized loan? What is an amortization schedule and how is it used?
9-10 What is an amortized loan? What is an amortization schedule and how is it used?
discuss the purpose of control charts, how they are created, what calculations are used, and why...
discuss the purpose of control charts, how they are created, what calculations are used, and why they are important in measuring quality. Then, create a control chart based on criteria that you come up with and explain it.
What is a master budget? How is the master budget prepared and why do companies create...
What is a master budget? How is the master budget prepared and why do companies create it? Do you have a master budget in your personal life? Why or why not?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT