Question

If the engineer approved the master schedule of the general contractor, is the contractor allowed to...

If the engineer approved the master schedule of the general contractor, is the contractor allowed to change its schedule without informing the engineer? Can the engineer request an updated programme? Explain.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The engineer has approved the master schedule of the general contractor which reflects a completion date...
The engineer has approved the master schedule of the general contractor which reflects a completion date 10 weeks before the stipulated date in the contract. Shall the engineer plan towards this early completion date? Explain.
The City of Atlanta awarded a contract to a general contractor to construct an irrigation dam....
The City of Atlanta awarded a contract to a general contractor to construct an irrigation dam. The contract stipulates some amount for liquidated damages for delay. After the construction has started, the City had to make some corrections to the plan which consequently affected the contractor's schedule. The contractor did not ask for extension of time or propose a change order to the contract. The contractor completed the work 15 days behind the schedule. The City sued for liquidated damages...
1. A general contractor performed work for company X without a written agreement between them. Company...
1. A general contractor performed work for company X without a written agreement between them. Company X instructed the contractor to submit the payment applications to company Y (which is a subsidiary to company X) but company Y did not pay the contractor back. Is the contractor entitled to any payments and what actions can he/she take? Explain.
If contract termination occurred, can the general contractor ask for a certificate of practical completion? Explain....
If contract termination occurred, can the general contractor ask for a certificate of practical completion? Explain. In regards to construction contracts.
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the prime contract for the construction of a new waste water treatment plant for Dimwit County DPW. The Contract Price has grown to $115 million after Dimwit made adjustments to the scope of the Work and issued the appropriate Change Orders. Wackinsmack’s contract with Dimwit is based on the ConsensusDOCs, CD 200, “Owner/Prime Contractor” Form. You have successfully negotiated the subcontract with Acme Mechanical, Inc....
1) In a recent general election, the city of Perrier citizens approved plans for the city...
1) In a recent general election, the city of Perrier citizens approved plans for the city to build a public swimming pool. The city plans to charge fees to swimmers to cover the cost of building and operating the pool and to generate resources to repair and replace equipment when needed. In what fund type should the city report its new swimming pool activities? A) The General Fund, Because the pool was approved by the citizens B) In an Enterprise...
1. Concerning the Master Production Schedule (MPS), which of the following statements are true? Select all...
1. Concerning the Master Production Schedule (MPS), which of the following statements are true? Select all correct answers. A. A Level Production Strategy minimizes the need for extra capacity and allows for smooth labor operations. B. The MPS is the tie between production and sales. C. A drawback about applying a Chase Demand Strategy is that it may lead to high levels of inventory when demand is low. D. The MPS allows sales to know the Availability to Promise (ATP)...
What were the critical errors the RDH general manager made after the departure of HI in...
What were the critical errors the RDH general manager made after the departure of HI in 2000? At the urgent meeting of government officials and the RDH board, stakeholders decided to request the PHS leaders be allowed to address the RDH board and explain how they thought they could solve the RDH service problems. As the senior project manager for PHS, what issues would you want to discuss during this meeting? The RDH board has asked you to design a...
Problem 1 (40 pts). The Stellar Federation consists of n + 1 planets. The Federal Government...
Problem 1 (40 pts). The Stellar Federation consists of n + 1 planets. The Federal Government is on the planet Alpha. It provides services for all planets sending identical spaceships to them. Each spaceship has a schedule that says for each day of the Federal Month, which of the planet it is currently visiting or whether it is in the outer space. The Federal Month has m days and m > n. Each spaceship visits each planet exactly one day...
In-Class Illustration #1 Norman, general manager of the XYZ subsidiary of Innovation Inc., is considering the...
In-Class Illustration #1 Norman, general manager of the XYZ subsidiary of Innovation Inc., is considering the purchase of new industrial equipment to improve efficiency at its Cordoba plant. The equipment has an estimated useful life of five years. The estimated cash flows for the equipment are shown in the table that follows, with no anticipated change in working capital. Innovation has a 12% required rate of return. Assume amortization is calculated on a straight line basis. Assume all cash flows...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT