Question

The engineer has approved the master schedule of the general contractor which reflects a completion date...

The engineer has approved the master schedule of the general contractor which reflects a completion date 10 weeks before the stipulated date in the contract. Shall the engineer plan towards this early completion date? Explain.

Homework Answers

Answer #1

Most sacrosanct document between Contractor and Owner(Engineer) is the contract document signed by both parties at the time of awarding the contract.This contract document and all its clauses etc are binding on both the parties . This includes the very important clause of Stipulated Date of completion of the project.

So though the master schedule of general contractor reflecting completion date 10 weeks before stipulated date in contract is approved by the engineer , still the contractor can complete work by stipulated date by stating reasons for extension  .So the engineer while planning for early completion date must keep the stipulated date in mind as that is the contractually binding date.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
If the engineer approved the master schedule of the general contractor, is the contractor allowed to...
If the engineer approved the master schedule of the general contractor, is the contractor allowed to change its schedule without informing the engineer? Can the engineer request an updated programme? Explain.
The City of Atlanta awarded a contract to a general contractor to construct an irrigation dam....
The City of Atlanta awarded a contract to a general contractor to construct an irrigation dam. The contract stipulates some amount for liquidated damages for delay. After the construction has started, the City had to make some corrections to the plan which consequently affected the contractor's schedule. The contractor did not ask for extension of time or propose a change order to the contract. The contractor completed the work 15 days behind the schedule. The City sued for liquidated damages...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the prime contract for the construction of a new waste water treatment plant for Dimwit County DPW. The Contract Price has grown to $115 million after Dimwit made adjustments to the scope of the Work and issued the appropriate Change Orders. Wackinsmack’s contract with Dimwit is based on the ConsensusDOCs, CD 200, “Owner/Prime Contractor” Form. You have successfully negotiated the subcontract with Acme Mechanical, Inc....
Corporation is a rapidly growing biotech company that has a required rate of return of 14​%....
Corporation is a rapidly growing biotech company that has a required rate of return of 14​%. It plans to build a new facility in Santa Clara County. The building will take 2 years to complete. The building contractor offered New Olgy a choice of three payment​ plans, as​ follows: LOADING...​(Click the icon to view the​ data) Plan​ I: Payment of $325,000 at the time of signing the contract and $4,600,000 upon completion of the building. The end of the second...
New Techno Corporation is a rapidly growing biotech company that has a required rate of return...
New Techno Corporation is a rapidly growing biotech company that has a required rate of return of 12?%. It plans to build a new facility in Santa Clara County. The building will take 2 years to complete. The building contractor offered New Techno a choice of three payment? plans, as? follows Plan? I: Payment of $250,000 at the time of signing the contract and $4,575,000 upon completion of the building. The end of the second year is the completion date....
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Kimmel Gnomes DATE:​March 1, 2018 TO:​CCSU Consulting FROM:​Candice Kimmel, President, Kimmel Gnomes SUBJECT:​Master Budget for the...
Kimmel Gnomes DATE:​March 1, 2018 TO:​CCSU Consulting FROM:​Candice Kimmel, President, Kimmel Gnomes SUBJECT:​Master Budget for the fiscal year July 1, 2018 – June 30, 2019 ---------------------------------------------------------------------------------------------------------------------------------- Our controller, Richard Kimmel is negotiating with potential new Clay suppliers in Kentucky. We need the Large Gnome Division’s Master Budget for the fiscal year ended June 30, 2019 for our corporate strategic planning process, and we cannot wait for Richard’s return from Kentucky. We would like you to prepare the Large Gnome Division’s...
Technical Writing Newtown Creek Memo Assignment 2: Context: You are still the petroleum engineer working as...
Technical Writing Newtown Creek Memo Assignment 2: Context: You are still the petroleum engineer working as the Lead Project Manager for Project Newtown Creek. You have been working for Enviro-Clean for the past 10 years and enjoying it very much because Enviro-Clean’s corporate values deeply reflect your own passion for cleaning up the environment. You are proud of being able to assume the Lead Project Manager position for Project Newtown Creek and hope that Newtown Creek will be cleaned up...
Mini-Case Analysis 2: Excel Hydro Inc. Excel Hydro took a loan contract which requires a payment...
Mini-Case Analysis 2: Excel Hydro Inc. Excel Hydro took a loan contract which requires a payment of $40 million plus interest two years after the contract's date of issue. The interest rate on the $40 million face value is 9.6% compounded quarterly. Before the maturity date, the original lender sold the contract to a pension fund for $43 million. The sale price was based on a discount rate of 8.5% compounded semi-annually from the date of sale. Excel Hydro is...
Mini Case 2: Excel Hydro Inc. Unit 8 (6% of the grade) Excel Hydro took a...
Mini Case 2: Excel Hydro Inc. Unit 8 (6% of the grade) Excel Hydro took a loan contract which requires a payment of $40 million plus interest two years after the contract's date of issue. The interest rate on the $40 million face value is 9.6% compounded quarterly. Before the maturity date, the original lender sold the contract to a pension fund for $43 million. The sale price was based on a discount rate of 8.5% compounded semi-annually from the...