Question

Prepare a master schedule like that shown in Figure 11.11 given this information: The forecast for...

Prepare a master schedule like that shown in Figure 11.11 given this information: The forecast for each week of an eight-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows:

Week Customer Orders
1 52
2 35
3 20
4 12

Use a production lot size of 75 units and no beginning inventory.

1.  Prepare a master schedule like that shown in Figure 11.11, in which weeks do we need to make production? The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Select all that apply. 1, 2, 3, 4, 5, 6, 7, and/or 8?

2.  Prepare a master schedule like that shown in Figure 11.11. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. What is the projected on-hand inventory by the end of week 4?

Homework Answers

Answer #1

Master Production Schedule (MPS) is as follows

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company that makes industrial pumps wants to prepare a master production schedule for June and...
A company that makes industrial pumps wants to prepare a master production schedule for June and July. Market forecast is given below. The weekly demand forecast is given as shown in the table. The customer order (already committed) are also shown. The beginning inventory level is 64. Determine Available-to-promise inventory under the condition that “schedule production when the projected on-hand inventory would be negative without production”. Suppose the production lot size is 70.    June    July 1 2 3...
Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for...
Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. ?(Enter your responses as integers. A response of? "0" is equivalent to being not? applicable.) ?Item: Ball bearings Order? Policy: 500 units Lead? Time: 1 week Quantity on? Hand: 400 Week 1 2 3 4 5 6 7 8 9 10 Forecast 550 300 350 400 300 400 150 300 400 350 Customer orders? (booked) 300 350 250 250 150 150 150...
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
TASK:   Complete the MRP record for component C as it would appear at the beginning of...
TASK:   Complete the MRP record for component C as it would appear at the beginning of week 2. MRP record for component C as it would appear at the beginning of week 1. Week 1 2 3 4 5 6 Gross Requirements 15 30 25 25 10 20 Scheduled Receipts 40 0 0 0 0 0 Projected Available Balance 50 20 35 10 0 20 Planned Order Receipts 0 0 40 0 0 40 Planned Order Releases 40 0 0...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory,...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time and overtime, subcontracting and backorders. The plan must wind up with no units in ending inventory in Period 6. Regular time capacity is 150 units per month. Overtime capacity and subcontracting capacity are 20 units per month each. Overtime cost is $30 per unit, subcontracting cost is 40 per unit, and backorder cost is $20 per unit, inventory holding cost is $5...
Required: Prepare a master budget for San Marcos Collectibles for the third quarter of 2016. The...
Required: Prepare a master budget for San Marcos Collectibles for the third quarter of 2016. The following component budgets must be included: Sales Budget Cost of Goods Sold, Inventory and Purchases Budget Operating Expense Budget Budgeted Income Statement Schedule of Expected Cash Collections Schedule of Expected Cash Disbursements - Merchandise Purchases Schedule of Expected Cash Disbursements - Operating Expenses Combined Cash Budget Budgeted Balance Sheet San Marcos Collectibles is a merchandising business located downtown in San Marcos, Texas. The owners...
No. 2: Master Budget #2. A Cyber Security Systems had sales of 3,500 units at $75...
No. 2: Master Budget #2. A Cyber Security Systems had sales of 3,500 units at $75 per unit last year. The marketing manager projects a 30 percent increase in unit volume sales this year with a 40 percent price increase. Returned merchandise will represent 8 percent of total sales. What is your net dollar SALES PROJECTION for this year? #2. B Sales for Ross Pro’s Sports Equipment are expected to be 4,800 units for the coming month. The company likes...
1. Concerning the Master Production Schedule (MPS), which of the following statements are true? Select all...
1. Concerning the Master Production Schedule (MPS), which of the following statements are true? Select all correct answers. A. A Level Production Strategy minimizes the need for extra capacity and allows for smooth labor operations. B. The MPS is the tie between production and sales. C. A drawback about applying a Chase Demand Strategy is that it may lead to high levels of inventory when demand is low. D. The MPS allows sales to know the Availability to Promise (ATP)...
Evergreen Corporation is preparing the master budget for the third quarter ending March 31, 2009.  It sells...
Evergreen Corporation is preparing the master budget for the third quarter ending March 31, 2009.  It sells a single product for $20 a unit.  Sales are 25% cash and 75% credit.  The credit sales are collected 30% in the month of the sale and the remaining 70% is collected in the next month.  No credit sales occurred in December 2008. The December 31 inventory of finished goods is 15,000 units and projected sales are 20,000, 55000, 65,000, 75,000, and 85,000 units for the first  months...
[The following information applies to the questions displayed below.] Phoenix Company’s 2017 master budget included the...
[The following information applies to the questions displayed below.] Phoenix Company’s 2017 master budget included the following fixed budget report. It is based on an expected production and sales volume of 15,000 units. PHOENIX COMPANY Fixed Budget Report For Year Ended December 31, 2017 Sales $ 3,150,000 Cost of goods sold Direct materials $ 930,000 Direct labor 225,000 Machinery repairs (variable cost) 60,000 Depreciation—Plant equipment (straight-line) 300,000 Utilities ($60,000 is variable) 180,000 Plant management salaries 210,000 1,905,000 Gross profit 1,245,000...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT