Prepare a master schedule like that shown in Figure 11.11 given this information: The forecast for each week of an eight-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows:
Week | Customer Orders |
1 | 52 |
2 | 35 |
3 | 20 |
4 | 12 |
Use a production lot size of 75 units and no beginning inventory.
1. Prepare a master schedule like that shown in Figure 11.11, in which weeks do we need to make production? The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Select all that apply. 1, 2, 3, 4, 5, 6, 7, and/or 8?
2. Prepare a master schedule like that shown in Figure 11.11. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. What is the projected on-hand inventory by the end of week 4?
Master Production Schedule (MPS) is as follows