Question

A work plan is created before a project manager estimates the size and schedule of the...

A work plan is created before a project manager estimates the size and schedule of the project.

Homework Answers

Answer #1

False

The scheduling of the Project is part of the Project Scheduling task while that of deciding the size of the project, is part of the ‘Project initiation and Planning phase’. A work plan in Project management does not replace the project files that details each of the tasks involved in the entire project but it is rather created with the intention of recording the important tasks that gives the Project manager an overall idea about the scheduling of the project activities and the estimated time for completion of the same. The significant project records and completion of the project as per the schedule are hence taken care of, in a work plan whereas the scheduling and sizing of the Project is not part of a work plan.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
if a project manager is able to obtain reasonable estimates of the probabilities of the states...
if a project manager is able to obtain reasonable estimates of the probabilities of the states of nature for each alternative that we solve a particular in a project then project manager is making decisions under
What are the Activity Duration Estimates, Gantt Chart, and Activity Network Diagram used for project schedule?
What are the Activity Duration Estimates, Gantt Chart, and Activity Network Diagram used for project schedule?
How does a project manager utilize a Schedule-Cost chart to display changes in the scope/cost of...
How does a project manager utilize a Schedule-Cost chart to display changes in the scope/cost of an ongoing project?
Question: The project’s progress has fallen behind schedule on the critical path. The project manager has...
Question: The project’s progress has fallen behind schedule on the critical path. The project manager has decided to recover the schedule by crashing the project’s schedule. What is the expected consequence of this project’s triple constraints?
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
You have been assigned as a project manager for a project. The work statement of this...
You have been assigned as a project manager for a project. The work statement of this project is design, develop and manage a website for e-Learning. Answer the following: A. Define the proper type of stakeholder that you need. B. Create your team and assign the tasks for each member. C. Create your timeline, assuming that the website SHOULD be online in 6 months. D. Explain: how are you going to creating a work breakdown structure (WBS) for the project.
List and define five of the key sections of a start-up business plan created for the...
List and define five of the key sections of a start-up business plan created for the purpose of attracting outside investors. For each of the key sections you chose to list, describe in 1 to 2 sentences what assumptions your project team is making about that key section for your team’s class project topic, and what work your project team has done, will be doing, or could consider doing to test those assumptions.
You are a project manager for a small construction project. Your project was budgeted for U.S....
You are a project manager for a small construction project. Your project was budgeted for U.S. $82,000 over a six-week period. As of today, you have spent U.S. $32,000. The earned value is U.S. $34,000. According to your schedule, you should have spent U.S. $40,000 by this time. Based on these circumstances, your project could be BEST described as: A.) Ahead of schedule B.) Behind schedule C.) On schedule D.) Not enough information is provided
A manager at a furniture production plant created an incentive plan for her carpenters in order...
A manager at a furniture production plant created an incentive plan for her carpenters in order to decrease the number of defects in the furniture production. She wants to check if the incentive plan worked. The manager selected 11 carpenters at random, recorded their annual defects before and after the incentive and came up with the following: Salesperson Before After Sanjeev Shippy 38 16 Cody Finney 20 32 Becky Braddy 27 16 Calvin Morrill 33 20 Becky Gilbert 33 21...
Discuss three (3/6) documents that a project manager, and / or project team needs to create...
Discuss three (3/6) documents that a project manager, and / or project team needs to create a stakeholder Engagement plan. The explain the roles of a sponsor and project manager in the completion of a project.
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT