Question

Provide a narrative justifying each task and subtask that is part of your work breakdown structure...

Provide a narrative justifying each task and subtask that is part of your work breakdown structure for the iPhone with expandable memory.

Homework Answers

Answer #1

  • Iphone with Expandable Memory
    • User Interface: It builds relationship with the user through data base management and alert management activities.
      • Data Management: here, we will do primary set up, build set up for data log, there would be option to view, next we could update information under such log.
      • Alert Management: it could give us various alerts; such could include our heart rate, BP pressure, any task that is pending, time that we have covered on the screen, etc.
    • Testing
      • Unit testing: here, each unit testing could include testing using algorithm or machine learning.
      • Integration Testing: this testing could include build integration with other apple devices like integration of iphone with I watch.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
What is the difference between project task plan and WBS (work breakdown structure)? Please explain in...
What is the difference between project task plan and WBS (work breakdown structure)? Please explain in simple terms. Please do not copy words from other source.
Similarities and differences between task lists or task plan and WBS work breakdown strucure.
Similarities and differences between task lists or task plan and WBS work breakdown strucure.
Briefly describe the five approaches to generating a Work Breakdown Structure
Briefly describe the five approaches to generating a Work Breakdown Structure
Identify the TWO (2) fundamental ideas behind Work Breakdown Structure.
Identify the TWO (2) fundamental ideas behind Work Breakdown Structure.
I need to develop a work breakdown structure (WBS) for building a fence around the backyard
I need to develop a work breakdown structure (WBS) for building a fence around the backyard
I need to develop a work breakdown structure (WBS) for building a fence around the backyard
I need to develop a work breakdown structure (WBS) for building a fence around the backyard
I need to develop a work breakdown structure (WBS) for building a fence around the backyard
I need to develop a work breakdown structure (WBS) for building a fence around the backyard
Develop a work breakdown structure for a house construction project a. Identify the predecessors and successors...
Develop a work breakdown structure for a house construction project a. Identify the predecessors and successors for activities in house construction project.    b. Draw a network diagram. (You can draw in paper, scan it and insert to your assignment or use computer to draw the diagram).
please submit a brief narrative summary of the work of your teammate(s) as well as your...
please submit a brief narrative summary of the work of your teammate(s) as well as your own contributions. These narratives should amplify the ratings you gave in the table, by (a) identifying the strengths and weaknesses of each individual and (b) suggesting ways in which his / her work can be more effective. Also, evaluate the team as a whole
(Project Management) Q1) Create WBS (Work-breakdown structure) for Mobile Application Development Project. Application should be able...
(Project Management) Q1) Create WBS (Work-breakdown structure) for Mobile Application Development Project. Application should be able to allow passengers to have self-check-in at airports. Q2) Create Design Structure Matrix (DSM) using listed tasks created in Q1. Find the activities which are dependent upon each other.
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT
Active Questions
  • Identifying Activity Bases in an Activity-Based Cost System Comfort Foods Inc. uses activity-based costing to determine...
    asked 15 minutes ago
  • Solve y'' + 2y' + 4y = 1 subject to y(0) = y'(0) = 0 (differential...
    asked 49 minutes ago
  • A school psychologist wants to know if a popular new hypnosis technique impacts depression. The psychologist...
    asked 58 minutes ago
  • Two identical sedimentation tanks are to be designed for an activated sludge plant with a flow...
    asked 1 hour ago
  • Hello, could you provide an original example of a security flaw or vulnerability related to strings....
    asked 1 hour ago
  • Let f(x)=5−log(x+1), g(x)=x2−2x−4 and k(x)=5/(x−4). (a) Find (fog)(x)(fog)(x) and its domain using the interval notation. (b)...
    asked 1 hour ago
  • List the main load transfer mechanisms in pile foundation and comment about the optimal spacing of...
    asked 1 hour ago
  • An athlete swings a 6.50-kg ball horizontally on the end of a rope. The ball moves...
    asked 2 hours ago
  • 1. Observation research must be systematic, not casual or haphazard, in its design. True or False...
    asked 2 hours ago
  • "Thinking as skill". Dr. Edward de Bono gave Lateral Thinking its name and developed techniques for...
    asked 2 hours ago
  • Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance...
    asked 2 hours ago
  • 11.3.2 Levi-Strauss Co manufactures clothing. The quality control department measures weekly values of different suppliers for...
    asked 2 hours ago