I need to develop a work breakdown structure (WBS) for building a fence around the backyard
work breakdown structure (WBS) for building a fence around the backyard :
Work breakdown structure is an organized methodology used to split an overall project into non overlapping component and identify deliverables for each component .
Work breakdown structure ------
For building a fence around the backyard. days
A-General conditions. ( 11 days)
to proceed and sign contract 3 days
Prepare and submit project schedule 2 days
Obtain building a fence permit 4 days
Submit preliminary drawing 2 days
B-Long lead procurement 2 days
Submit fence drawing and order items 2 days
C mobilize on site 2 days
Prepare site and lay down fence 2 days
Site grading and utilities 10 days
We can easily give the shape of graph for easy understanding.