2
All _______ activities have been _______ when a new activity is started in a project.
Multiple Choice
successor, started
successor, completed
predecessor, started
predecessor, completed
17
A ________ organization is one with ________ of reporting relationships.
Multiple Choice
dedicated, multiple lines
dedicated, a single line
matrix, multiple lines
matrix, a single line
20
Which of the following is NOT a project management tool for project planning?
Multiple Choice
Dependency matrix
Activity network
Gantt chart
Flow chart
COURSE : OPERATIONS MANAGEMENT
2.
predecessor, completed
The activities that need to be completed before a new activity can be started are known as predecessors.
17.
matrix, multiple lines
In a matrix organization, a person reports to his/ her functional manager for the function he/ she is in. But he/ she also reports to a project manager in which he/ she is a member. {dedicated, a single line} could have been also correct bit note the plural term 'relationships' in the sentence.
20.
Flow chart
A flow chart is used for process analysis, not for a project.