Question

2 All _______ activities have been _______ when a new activity is started in a project....

2

All _______ activities have been _______ when a new activity is started in a project.

Multiple Choice

  • successor, started

  • successor, completed

  • predecessor, started

  • predecessor, completed

17

A ________ organization is one with ________ of reporting relationships.

Multiple Choice

  • dedicated, multiple lines

  • dedicated, a single line

  • matrix, multiple lines

  • matrix, a single line

20

Which of the following is NOT a project management tool for project planning?

Multiple Choice

  • Dependency matrix

  • Activity network

  • Gantt chart

  • Flow chart

COURSE : OPERATIONS MANAGEMENT

Homework Answers

Answer #1

2.

predecessor, completed

The activities that need to be completed before a new activity can be started are known as predecessors.

17.

matrix, multiple lines

In a matrix organization, a person reports to his/ her functional manager for the function he/ she is in. But he/ she also reports to a project manager in which he/ she is a member. {dedicated, a single line} could have been also correct bit note the plural term 'relationships' in the sentence.

20.

Flow chart

A flow chart is used for process analysis, not for a project.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly interconnected B. Activity times are random C. The project contains simple activity sequences D. All of the above Reset Selection Question 9 of 21 Which of the following is NOT included in project control? A. Monitoring costs, time, and performance B. Adhering to the budget C. Correcting the plan as necessary D. All of the above are included Reset Selection Question 10 of 21...
You work for Microsoft in their global smart phone group. You have been made project manager...
You work for Microsoft in their global smart phone group. You have been made project manager for the design of a new smart phone. Your supervisors have already scoped the project so you have a list showing the work breakdown structure and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!      You have been given the information in Exhibit 5.13. It includes all the...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by 10 percent rather than the target of 25 to 35 percent. Internal resources were reduced by only 5 percent. The reduction in prototype time and cost was 15 percent rather than the expected 30 to 35 percent. Como’s automotive customers were not pleased with the slow progress and relatively immature performance of the company’s’ project management system. Change was taking place, but not fast...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by 10 percent rather than the target of 25 to 35 percent. Internal resources were reduced by only 5 percent. The reduction in prototype time and cost was 15 percent rather than the expected 30 to 35 percent. Como’s automotive customers were not pleased with the slow progress and relatively immature performance of the company’s’ project management system. Change was taking place, but not fast...
Como Tool and Die was a second-tier component supplier to the auto industry. Its largest customer...
Como Tool and Die was a second-tier component supplier to the auto industry. Its largest customer was Ford Motor Company. Como had a reputation for delivering a quality product. During the 1980s and the early 1990s, Como’s business grew because of its commitment to quality. Emphasis was on manufacturing operations, and few attempts were made to use project management. All work was controlled by line managers who, more often than not, were overburdened with work. The culture at Como underwent...
Como Tool and Die was a second-tier component supplier to the auto industry. Its largest customer...
Como Tool and Die was a second-tier component supplier to the auto industry. Its largest customer was Ford Motor Company. Como had a reputation for delivering a quality product. During the 1980s and the early 1990s, Como’s business grew because of its commitment to quality. Emphasis was on manufacturing operations, and few attempts were made to use project management. All work was controlled by line managers who, more often than not, were overburdened with work. The culture at Como underwent...
CASE STUDY - LG Electronics From its origins as the progenitor of South Korea’s electronics industry...
CASE STUDY - LG Electronics From its origins as the progenitor of South Korea’s electronics industry and then its first global exporter, LG Electronics has evolved to a respected global brand with manufacturing facilities in China, India, Mexico, Brazil, Poland, and Russia and a presence in 49 countries. Headquartered in Seoul, South Korea, the company has 84,000 employees in 112 locations around the world, including 81 subsidiaries. Perhaps best known today for its quality mobile phones, LG Electronics is also...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT