Question

Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly...

Question 8 of 21

Gantt charts are effective for project scheduling if:
A. Activities are highly interconnected
B. Activity times are random
C. The project contains simple activity sequences
D. All of the above
Reset Selection

Question 9 of 21

Which of the following is NOT included in project control?
A. Monitoring costs, time, and performance
B. Adhering to the budget
C. Correcting the plan as necessary
D. All of the above are included
Reset Selection

Question 10 of 21

"Estimating the time required for each task" is an example of ______ management decision in project management.
A. Planning
B. Control
C. Scheduling
D. Both A and B
E. Both B and C
Reset Selection

Question 11 of 21

The advantage(s) of the network method over the Gantt chart is (are) that:
A. Network method is easy to use and quite widely understood
B. Network method show precedence relationships explicitly when compared to Gantt Charts.
C. Network methods are less costly to use.
D. Both A and B
E. Both B and C
Reset Selection

Question 12 of 21

The purpose of performing a forward pass is to:
A. Identify the shortest path
B. Determine the slack available in the process
C. Determine the late start and the late finish times
D. Determine the early start and the early finish times
Reset Selection

Question 13 of 21

Which of the following statements is true about a critical path?
A. A critical path consists of activities for which early start time equals late start time.
B. The activities along the critical path take the longest time.
C. A critical path consists of activities for which early finish time equals late finish time.
D. There is no slack in the activities along the critical path.
E. All of the above
Reset Selection

Question 14 of 21

=
The information calculated from the forward and backward pass can be used for:
A. Identifying the critical path
B. Calculating slack
C. Determining the completion date of the project
D. Both A and C
E. A, B, and C
F. Both A and B
Reset Selection

Question 15 of 21

Homework Answers

Answer #1

Gantt charts are effective for project scheduling if:

Answer = (C) The project contains simple activity sequences

  • A Gantt chart is a graphical depiction of a project schedule

Which of the following is NOT included in project control?

Answer = (D) All of the above are included

  • Project control includes Monitoring costs, time, and performance, budget and correcting plan

"Estimating the time required for each task" is an example of ______ management decision in project management.

Answer = (A) Planning

  • The main purpose is to plan time, cost and resources adequately to estimate the work needed

The advantage(s) of the network method over the Gantt chart is (are) that:

Answer = (A) Network method show precedence relationships explicitly when compared to Gantt Charts.
  • the precedence relationships in network scheduling are explicitly shown

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Below are the project steps for the creation of a television advertisement for Foolio, which is...
Below are the project steps for the creation of a television advertisement for Foolio, which is a new energy drink that the musician Coolio has created.    Consider the following data for questions 1 through 5: Activity Duration (days) Description Preceding Activity(ies) A 6 Create script for advertisement - B 4 Book technical crew A C 4 Book actors A D 3 Create props and costumes B,C E 6 Book location C F 5 Filming and editing D,E How many paths...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There can be multiple critical paths on the same project, all with different durations. B) The early finish of an activity is the latest early start of all preceding activities. C) The late start of an activity is its late finish plus its duration. D) If a specific project has multiple critical paths, all of them will not have the same duration. E) B) and...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3 A Dennis D 3 B Kate E 8 D William F 10 C Sam G 8 F William H 3 E, G Jane 1. Draw the network diagram and indicate the critical path. 2. Draw the network diagram by specifying Early Start, Early Finish, Late Start, Late Finish, and slacks. 3. Indicate all the activities, duration, start and finish dates, predecessors, resources in a...
Work with your group to practice the critical path method of scheduling Draw the network diagram...
Work with your group to practice the critical path method of scheduling Draw the network diagram using the SmartArt tool in any Microsoft Office application Follow the convention for drawing each node, allowing space for ES, EF, LS, LF and float Identify all the paths in the schedule Use the enumeration method to identify the critical path Make a forward pass to find the early schedule dates Make a backward pass to find the late schedule dates Define the float...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times: Immediate Activity Predecessor Time A — 3 B — 4 C — 2 D A, B, C 2 E A, D 8 F C, D 7 G D, E 5 H F...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site Selection and Preparation B D Drilling, Engineering and other Works B, C E Installation of other Equipment, Testing, and Analysis D F Project Commission and Handing over to the community E G Demonstrate safety usage and practices E, F H Preclosure safety analysis F, G 1. create an activity precedence diagram showing the network logic for each project activity you have identified; 2.    prepare...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8 13 B 5 7 9 C 5 12 19 D 2 5 8 E 5 9 19 F 4 8 18 G 9 15 21 H 4 6 14 If required, round your answers to two decimal places. A.) Find the critical path. Activity Expected Time Variance A B C D E F G H Earliest Latest Earliest Latest Critical Activity Start Start Finish...