You work for Microsoft
in their global smart phone group. You have been made project
manager for the design of a new smart phone. Your supervisors have
already scoped the project so you have a list showing the work
breakdown structure and this includes major project activities. You
must plan the project schedule and calculate project duration. Your
boss wants the schedule on his desk tomorrow morning!
You have been given the information
in Exhibit 5.13. It includes all the activities required in the
project and the duration of each activity. Also, dependencies
between the activities have been identified. Remember that the
preceding activity must be fully completed before work on the
following activity can be started.
Your project is divided into five major
subprojects. Subproject “P” involves developing specifications for
the new smart phone. Here decisions related to such things as
battery life, size of the phone, and features need to be made.
These details are based on how a customer uses the smart phone.
These user specifications are redefined in terms that have meaning
to the subcontractors that will actually make the new smart phone
in subproject “S” supplier specifications. These involve
engineering details for how the product will perform.
The individual components that make
up the product are the focus of subproject “D.” Subproject “I”
brings all the components together, and a working prototype is
built and tested.
Finally in subproject “V,” suppliers
are selected and contracts are negotiated.
Exhibit 5.13: Work Breakdown Structure and Activities for the Smart
phone Design Project
MAJOR SUBPROJECTS/ACTIVITIES | ACTIVITY IDENTIFICATION | DEPENDENCY | DURATION (WEEKS) | |
Product Specifications (P) | ||||
Market research | P1 | — | 2 | |
Overall product specifications | P2 | P1 | 4 | |
Hardware | P3 | P2 | 5 |
|
Software | P4 | P3 | 5 | |
Supplier specifications (S) | ||||
Hardware | S1 | P4 | 5 | |
Software | S2 | P4 | 6 | |
Product design (D) | ||||
Battery | D1 | S1 | 1 | |
Display | D2 | S1 | 2 | |
Camera | D3 | S1 | 1 | |
Outer cover | D4 | D1, D2, D3 | 4 | |
Product integration (I) | ||||
Hardware | I1 | D4 | 3 | |
User interface | I2 | D2 | 4 | |
Software coding | I3 | I2 | 4 | |
Prototype testing | I4 | I1, I3 | 4 | |
Subcontracting (V) | ||||
Suppliers selection | V1 | S1 ,S2 | 10 | |
Contract negotiation | V2 | I4, V1 | 2 | |
a. Determine the minimum number of weeks for completing the project.
Minimum number of weeks
b.
Your boss would like you to study the impact of making two changes
to how the project is organized. The first change involves using
dedicated teams that would work strictly in parallel on the
activities in each subproject. For example, in subproject P
(product specifications) the team would work on P1, P2, P3, and P4
all in parallel. In other words, there would be no precedence
relationships within a subproject—all tasks within a subproject
would be worked on at the same time and each would take the same
amount of time as originally specified. With this new design, all
the subprojects would be done sequentially with P done first, then
S, D, I, and finally V.
The second change your boss would like you to
consider would be to select the suppliers during subproject P and
have them work directly with the dedicated teams as described in
the first change. This would involve adding an additional activity
to subproject P called supplier selection and contract negotiation
(P5) with a duration of 12 weeks. This new activity would be done
in parallel with P1, P2, P3, and P4. Subprojects S and V would be
eliminated from the project. What would be the expected impact on
how long it would take to complete the project if this additional
change were made?
The duration of the project will (Click to select)decreaseincrease to weeks.
DIAGRAM:-
A). earlier,latest and start, finish schedule activity calculation.
the slack activity equal to zero from critical path
the critical path is : P1 -P2 -P3 -P4 -SI - D2 - I2 - I3 - I4 - V2
Thus, the minimum number of weeks is 37.
B).
The exercises of subproject are done in parallel to finish the term of each subproject that will be equivalent to biggest length of action inside subproject.
the duration of the project is =5+4+4+10=23 weeks.
thus, the duration is decreases to 23 weeks.