- The project has been performing as planned, and the team
members have been exhibiting increasing levels of trust between
each other. The sponsor and the buyer have been satisfied with the
delivery of business value, and user acceptance testing results are
positive. A technical expert consulting with the team has expressed
concerns that the team is not in agreement on the best way to
deliver to the next review. If the project manager wants to support
the team in reaching a decision, she must be involved in which
process?
A. Manage Stakeholder Engagement
B. Develop Team
C. Manage Communications
D. Manage Team
- A team member asks to tell you something in confidence. He
advises you that he has been performing illegal activities within
the company for the last year. He is feeling guilty about it and is
telling you in order to receive advice as to what he should do.
What should you do?
A. Inform your manager of the illegal activities.
B. Confirm that the activities are really illegal.
C. Tell the employee to inform his manager.
D. Ask for full details.
- The team has to follow detailed communications ground rules to
support clarity and understanding among the geographically
dispersed team. Some of the team members are hired only for the
project. There is concern from sponsors that past problems of team
dynamics should be anticipated and managed proactively. Within the
project, special efforts are being made by the project manager to
encourage cohesiveness, professionalism, and trust. The main
purpose of the Manage Team process is to:
A. Complete the project according to the project management
plan.
B. Acquire the best resources available.
C. Assess the viability of the project's ground rules.
D. Make sure each team member has a clearly assigned role.
- The company has just announced there will be layoffs in the
next month, and there's a good chance it will include some of the
people from your project team. The team is discussing the layoff to
the exclusion of everything else. If you tell the team, "Let's calm
down and get back to work, maybe our performance in the next month
will help keep us from losing our jobs," which conflict resolution
technique are you using?
A. Collaborating
B. Withdrawal
C. Compromising
D. Smoothing
- The team has been working together on three consecutive
projects. They have been increasingly successful in estimating the
work and completing the deliverables to the product owner's
satisfaction with each iteration. On the last iteration, some
difficult and unexpected problems occurred. This increased the
tension among the team, so they are looking for ways to do a better
job of dealing with issues and risks. All the following are parts
of effective problem-solving except:
A. Reviewing the decision
B. Confirming that the decision solved the problem
C. Waiting to make decisions
D. Analyzing the problem
- A team member comes to you to admit he is having trouble with
his activity. Although not yet in serious trouble, the team member
admits he is uncertain of how to perform part of the work on the
activity. He suggests a training class available next week. What
should you do?
A. Investigate whether the required training will benefit the
organization in future projects.
B. Get money from the team member's functional department
budget.
C. Switch to a trained resource to avoid the cost.
D. Determine if anyone else needs training.
- You have been reviewing the results of several projects'
rewards and recognition systems to help you decide what would be
the best plan for the new project you have been assigned to manage.
Recent organizational growth has resulted in added responsibilities
for many employees and has made communications more challenging.
Leadership of the organization has expressed a concern that team
members do not understand why they are having to do project work in
addition to their daily responsibilities. The sponsor of your new
project believes the team will perform better with good motivation.
Which of the following is the best method to make reward systems
most effective?
A. Pay a large salary increase to the best workers.
B. Make the link between performance and reward clear.
C. Give the team a choice of rewards.
D. Present notification of rewards within the company.
- A project manager is assigned to a new project and is supplied
with a preselected team. What is the first thing the project
manager should find out about the team?
A. Each team member's history with the organization
B. Each team member's role in the project management plan
C. Each team member's project activities
D. What each team member wants to get out of the project
- DAThe project work has begun when the project manager notices
how many times meetings and discussions are disrupted by power
outages and the lack of a warm place to meet. She turns her
attention to influencing the organization to improve the team's
working conditions. She is following the concepts of which
motivational theorist?
A. McGregor
B. Theory Y
C. Herzberg
D. Maslow's hierarchy
- A seller has withdrawn from a project midway through the
project executing processes, and another seller is taking over. The
project manager meets with the replacement seller and his crew. In
this meeting, what should the project manager do first?
A. Communicate the objectives of the project.
B. Review the schedule.
C. Introduce the team members, and identify the roles and
responsibilities.
D. Create a communications management plan.
- You are working on elements of the resource management plan.
The project requires a large number of people to complete the work,
and you have learned from past projects the importance of having
clarity on who project team members report to within the project.
The balance of work and available time are considerations. You need
to make certain the right resources are available when needed and
can complete the work. It is also important that team members know
when and how fast they need to complete the work they are assigned.
A responsibility assignment matrix helps by documenting which two
data points?
A. Activity and resource
B. Resource and usage each month
C. Resource and duration estimate
D. Activity and calendar date
- The engineering resource group has a policy of no salary
bonuses for project work. The project manager's current project has
an aggressive schedule and a difficult technical obstacle to
overcome. A new product offering is dependent on this project's
success in the current schedule. The project manager has heard
grumbling from his team members about the fact that they cannot be
rewarded for their effort. What is the first thing the project
manager should do?
A. The project manager should determine whether team members
from another department can help with the project.
B. The project manager should talk with the team about the
importance of getting this done on time and explain the company
policy.
C. The project manager should negotiate a less aggressive
schedule from the client.
D. The project manager should talk to management to determine
other rewards that can be given.
- A project team member has just completed work on the
microprocessor for the new human system performance monitor and is
now finished with the project. The project manager should:
A. Provide input to the team member's performance appraisal.
B. Reevaluate the activity duration estimates.
C. Evaluate the project's resource requirements.
D. Change the resource management plan.
- What does a resource histogram show that a responsibility
assignment matrix does not?
A. The person in charge of each activity
B. Time
C. Activities
D. Interrelationships
- Two stakeholders are disagreeing via a series of emails as to
whether a deliverable meets the acceptance criteria. One of the
stakeholders wanted different criteria, but the cost-benefit
analysis done in planning did not support delivering that level of
performance. The stakeholders agreed that the higher level of
performance was not required and was not cost-effective. A team
member has just informed you that that a problem with his work has
occurred. The deliverable he is working on must be shipped today,
or there will be a project breach. One of the stakeholders having
the email disagreement comes to you to complain about the other.
You say, "I cannot deal with this issue now!" Which of the
following techniques are you using?
A. Problem-solving
B. Withdrawal
C. Compromising
D. Forcing
- You take over a project from a colleague. In the process of
getting familiarized with the team, you hear complaints about
timelines and overtime. Which tool may your colleague have
neglected to use?
A. RACI matrix
B. Responsibility assignment matrix
C. Project organizational chart
D. Resource histogram
- You are hired to do a business process improvement project
which includes new policies, processes, procedures, and software
tools. The functional managers have assigned their staff for very
limited periods to accept deliverables and provide operational
information as required. As a result, your team will be mainly
temporary resources hired to be part of your team, making resource
management on this project extremely critical. The procurement
manager assisting you in this sourcing effort asks you for your
resource management plan. Which of the following is included in a
resource management plan?
A. When and how people will be brought into and taken off the
project team
B. If independent estimates are needed, who will prepare them
and when
C. What details about the project should go to whom and when the
details need to be sent
D. How the team will implement the plans for ensuring the
project will satisfy the needs for which it was undertaken
- A project manager needs to determine the resources needed for
the project. Select the primary process from the following
choices.
A. Plan Resource Management
B. Identify Stakeholders
C. Solicit expert advice from functional managers
D. Estimate Activity Resources
- Your organization is having difficulty managing all of its
projects. You have been asked to help senior management get a
better understanding of the problems. What do you do first?
A. Meet with senior managers to help them develop a new tracking
system for managing projects.
B. Meet with individual project managers to get a better sense
of what is happening.
C. Review the project charters and bar charts for all
projects.
D. Send a formal memo to all project managers requesting their
project management plans.
- Another project manager has a family emergency and must leave.
He has asked you to fill in for him during a team meeting to
discuss a minor problem with the project. He has already
distributed a detailed agenda and provided you with a copy. When
you attend the meeting, several members of the team are making fun
of the absent project manager's ethnic heritage. Your company does
not have a formal diversity policy covering such behavior. What
should you do?
A. Report the incident to the other project manager.
B. Hold the meeting as if nothing happened.
C. Begin the meeting with a discussion of diversity and
professional behavior.
D. Because your company does not have a written diversity
policy, there is nothing you can do.
- A scheduled performance review of project progress indicates a
variance from the planned utilization of paint on the project. The
paint is a high quality custom blend designed specifically for the
project. It is expensive and has a lead time of 3 weeks to reorder
it. The project manager might do any of the following to help
determine the root cause of this issue except:
A. Revisit the Create WBS process.
B. Perform benchmarking.
C. Perform alternatives analysis.
D. Review the basis of estimates.
- For the last three months, a customer has been from two to four
days late with her approvals on deliverables. After analyzing the
situation, the project manager decides withdrawal is the best
conflict resolution technique to use. Which of the following
reflects withdrawal?
A. Call the customer and demand that you receive the approvals
today.
B. Postpone a decision.
C. Inform the customer that late approvals are not a problem,
but ask him or her to try to get them in on time in the future.
D. Meet with the customer to determine a new due date for
approvals.