Question

As part of a major plant renovation project, the industrial engineering department has been asked to...

As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as you know you can follow:

Task

Duration (minutes)

Immediate Predecessor

A

0.3

-

B

0.6

A

C

0.3

B

D

0.5

-

E

1.2

D

F

0.8

C

G

1.2

E, F

Do each of the following:

Draw the precedence diagram.

Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time.

Determine the minimum number of stations needed.

Assign tasks to workstations on the basis of most following tasks. Use shortest processing time as a tiebreaker. If ties still exist, assume indifference in choice.

Compute the percentage of idle time for the assignment in part d.

Homework Answers

Answer #1

b) Minimum cycle time = Maximum task time= 1.2 mins

Maximum cycle time =Total duration = 4.9 mins

Calculated cycle time = OT/output = 8*60/240 = 2 mins

  1. Minimum no of stations required= Total duration/cycle time = 4.9/2 = 2.45 = 3 stations

So, task precedence on basis of most following task and shortest processing time as tiebreaker is:

A-B-C-D-F-E-G

Total time at workstation= cycle time = 2 kins

Workstation 1: Task 1: A

Time left = 2-0.3 = 1.7

Task 2: B

Time left= 1.7-0.6 = 1.1

Task 3:C

Time left: 1.1-0.3= 0.8

Task 4:D

Time left=0.8-0.5=0.3

Workstation 2:

Task 1: F

Time left=2-0.8=1.2

Task 2: E

Time left= 1.2-1.2=0

Workstation 3:

Task 1: G

Time left=2-1.2=0.8

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Please solve the following problem related to Chapter 6 1. As part of a major plant...
Please solve the following problem related to Chapter 6 1. As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight- hour day. Task times and precedence relationships are as you know you can follows: Task                 Duration (minutes)             Immediate Predecessor _____________________________________________________________ A                             0.3                               - B                             0.6                                A C                              0.3                                B D                             0.5                                  - E                              1.2                                  D F                              0.8                                  C G                             ...
A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of...
A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of this process are listed below. Task Duration (hours) Predecessor 1 Predecessor 2 Predecessor 4 A 4 -- B 6 -- C 2 A D 6 A E 3 B C F 3 B C G 5 D E F H 1 G Draw the appropriate network for this project. What would the cycle time be if the goal is to produce 20 units per...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a forecasted demand of 50 units/hour. Find an assembly line that will produce the necessary output. Task Time (in seconds) Immediate Predecessor A 55 - B 30 A C 35 A D 22 B E 50 B,C F 15 C G 5 F H 10 G Part 2. Complete this exercise again, but this time the company expects a forecasted demand of 20 units/hour. Find...
Wild Widget must set up an assembly line for widgets. Forecasts show that 52 units per...
Wild Widget must set up an assembly line for widgets. Forecasts show that 52 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: Task Time (seconds) Predecessors A 10 – B 33 A C 23 A D 24 C,B E 20 D F 18 D G 36 E,F b. What is the takt time? (Round your answer to the nearest whole number.) c. What is the theoretical number of workstations? (Round up...
TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C...
TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C Beans -B 10 sec D Meat -B 10 sec E Salsa -C, D 10 sec F Cheese -E 5 sec G Sour Cream -E 10 sec H Lettuce -E 10 sec I Wrap -F, G, H 15 sec J Bag -I 5 sec K Checkout/pay -J 25 sec Achieving the above cycle time and output, what is the theoretical number of workstations? Assign tasks...
QRS Corp. is designing a product layout for a new product. They plan to use this...
QRS Corp. is designing a product layout for a new product. They plan to use this production line ten hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Task Time (Secs) Immediate Predecessor a 34 none b 20 a c 10 b d 16 b e 10 c f 24 d,e g 38 f For output to equal forecasted demand, what will be the...
Q1    Barton Sounds, Inc., produces high quality but expensive headsets for audio mania group. Manufacturing...
Q1    Barton Sounds, Inc., produces high quality but expensive headsets for audio mania group. Manufacturing the headsets involves fourteen production tasks. Below is shown each task with its required time to finish it and its preceding task or tasks.    The Barton Sounds determines that there are 480 productive minutes of work available per day. Furthermore, the production schedule requires that 40 units be completed as output form the assembly line each day.    Please answer the following questions...
The pizza-making process at Mama’s is outlined in the table below. The shop is open 8...
The pizza-making process at Mama’s is outlined in the table below. The shop is open 8 hours a day to fulfill a typical daily demand of 40 pizzas. Sketch the process and balance the assembly to answer the questions below. Task Predecessor Minutes A. Roll Dough -- 12 B. Spread Sauce A 4 C. Prepare Toppings -- 7 D. Put Toppings on Pizza B,C 3 E. Sprinkle Cheese D 2 F. Bake Pizza E 10 1. What is the maximum...
Mega Mart Store is a discount department store badly in need of renovation. To avoid loss...
Mega Mart Store is a discount department store badly in need of renovation. To avoid loss of sales and disruption of customer shopping habits, Mega Mart wants to complete this renovation without closing the store itself, by temporarily co-locating goods from one area of the store into another, creating open spaces for renovation and re-occupation. Mega Mart is divided into four basic areas of goods: Clothing, Electronics, House Wares and Foodstuffs. Each of these areas will need to be temporarily...
Question 2: A Muscat Tools company manufactures toolkits and supplies to the local and overseas market...
Question 2: A Muscat Tools company manufactures toolkits and supplies to the local and overseas market within the GCC region. In the assembly line, the kits are packed in the tool boxes. The company produces the specified demand rate of toolkit in 8 hours per day with tasks, description of tasks, and time for each task shown in Table Q2a. Draw the precedence diagram and determine the cycle time, and number of workstations;     iii) Balance the line using the longest...