QRS Corp. is designing a product layout for a new product. They plan to use this...

QRS Corp. is designing a product layout for a new product. They plan to use this production line ten hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product:

Task

Time (Secs)

Immediate Predecessor

a

34

none

b

20

a

c

10

b

d

16

b

e

10

c

f

24

d,e

g

38

f

For output to equal forecasted demand, what will be the idle time at the fourth workstation of the assembly line that uses the least number of workstations?

Homework Answers

Answer #1

Step1 :

Draw Prededence adiagram

step 2:

Calculate desired output rate = Demand per day / No. of hours in day = 900/10 = 90 unit per hour

Step3 :

Calculate Cycle time

Cycle time = 1/ Desired output = 1/90 hour = 60*60/90 sec = 40 sec per unit

Step4

Calculate Minimum no of workstation

TM = Sum of all task time /(Cycle time ) = 152/40 = 3.8 = 4 workstation

So Minimum number of workstation should be 4

Step 4 :

Assigning tasks to 4 Workstation without violating the predecessor relationship and sum of the processing time in any workstation should not be greater than cycle time ( 40 Sec)


Output


For 4th Workstation Idle time is 2 Seconds

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Wild Widget must set up an assembly line for widgets. Forecasts show that 52 units per...
Wild Widget must set up an assembly line for widgets. Forecasts show that 52 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: Task Time (seconds) Predecessors A 10 – B 33 A C 23 A D 24 C,B E 20 D F 18 D G 36 E,F b. What is the takt time? (Round your answer to the nearest whole number.) c. What is the theoretical number of workstations? (Round up...
As part of a major plant renovation project, the industrial engineering department has been asked to...
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as you know you can follow: Task Duration (minutes) Immediate Predecessor A 0.3 - B 0.6 A C 0.3 B D 0.5 - E 1.2 D F 0.8 C G 1.2 E, F Do each of the following: Draw the precedence diagram. Determine...
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 100 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 120 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a forecasted demand of 50 units/hour. Find an assembly line that will produce the necessary output. Task Time (in seconds) Immediate Predecessor A 55 - B 30 A C 35 A D 22 B E 50 B,C F 15 C G 5 F H 10 G Part 2. Complete this exercise again, but this time the company expects a forecasted demand of 20 units/hour. Find...
Please solve the following problem related to Chapter 6 1. As part of a major plant...
Please solve the following problem related to Chapter 6 1. As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight- hour day. Task times and precedence relationships are as you know you can follows: Task                 Duration (minutes)             Immediate Predecessor _____________________________________________________________ A                             0.3                               - B                             0.6                                A C                              0.3                                B D                             0.5                                  - E                              1.2                                  D F                              0.8                                  C G                             ...
The pizza-making process at Mama’s is outlined in the table below. The shop is open 8...
The pizza-making process at Mama’s is outlined in the table below. The shop is open 8 hours a day to fulfill a typical daily demand of 40 pizzas. Sketch the process and balance the assembly to answer the questions below. Task Predecessor Minutes A. Roll Dough -- 12 B. Spread Sauce A 4 C. Prepare Toppings -- 7 D. Put Toppings on Pizza B,C 3 E. Sprinkle Cheese D 2 F. Bake Pizza E 10 1. What is the maximum...
Question 2: A Muscat Tools company manufactures toolkits and supplies to the local and overseas market...
Question 2: A Muscat Tools company manufactures toolkits and supplies to the local and overseas market within the GCC region. In the assembly line, the kits are packed in the tool boxes. The company produces the specified demand rate of toolkit in 8 hours per day with tasks, description of tasks, and time for each task shown in Table Q2a. Draw the precedence diagram and determine the cycle time, and number of workstations;     iii) Balance the line using the longest...
Q1    Barton Sounds, Inc., produces high quality but expensive headsets for audio mania group. Manufacturing...
Q1    Barton Sounds, Inc., produces high quality but expensive headsets for audio mania group. Manufacturing the headsets involves fourteen production tasks. Below is shown each task with its required time to finish it and its preceding task or tasks.    The Barton Sounds determines that there are 480 productive minutes of work available per day. Furthermore, the production schedule requires that 40 units be completed as output form the assembly line each day.    Please answer the following questions...
A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of...
A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of this process are listed below. Task Duration (hours) Predecessor 1 Predecessor 2 Predecessor 4 A 4 -- B 6 -- C 2 A D 6 A E 3 B C F 3 B C G 5 D E F H 1 G Draw the appropriate network for this project. What would the cycle time be if the goal is to produce 20 units per...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT