Question

Please solve the following problem related to Chapter 6 1. As part of a major plant...

Please solve the following problem related to Chapter 6

1. As part of a major plant renovation project, the industrial

engineering department has been asked to balance a revised

assembly operation to achieve an output of 240 units per eight-

hour day. Task times and precedence relationships are as you

know you can follows:

Task                 Duration (minutes)             Immediate Predecessor

_____________________________________________________________

A                             0.3                               -

B                             0.6                                A

C                              0.3                                B

D                             0.5                                  -

E                              1.2                                  D

F                              0.8                                  C

G                              1.2                                 E,F

                      

Do each of the following:

a. Draw the precedence diagram.

b. Determine the minimum cycle time, the maximum cycle time, and

the calculated cycle time.

c. Determine the minimum number of stations needed.

d. Assign tasks to workstations on the basis of most following

tasks. Use shortest processing time as a tiebreaker. If ties

still exist, assume indifference in choice.

e. Compute the percentage of idle time for the assignment in part d.

[Hint: Please read page 262-264 in the textbook. Please read Example

1 on page 264-266, and Example 2 on page 267-269.]

Please type your answer and the steps of computation in a Word or

Excel file.

Homework Answers

Answer #1

(a)

(b)

CTmin = the longest task time = 1.2 minutes
CTmax = sum of all the task times = 4.9 minutes

Calculated cycle time = 8 x 60 / 240 = 2 minutes

(c)

Minimum number of stations = CTmax / Calculated cycle time = 4.9/2 = 2.45 i.e. 3 stations

(d)

Sattions Task Duration
(minutes)
Time left
(minutes)
Ready tasks
(# followers)
A(4),D(2)
1 A 0.3 1.7 D(2),B(3)
B 0.6 1.1 D(2),C(2)
C 0.3 0.8 D(2),E(1)
D 0.5 0.3 E(1),F(1)
2 F 0.8 1.2 E(1)
E 1.2 0 G(0)
3 G 1.2 0.8

(e)

% idle time = 1 - (Flow time / (# stations x cycle time)) = 1 - (4.9/(3*2)) = 18.33%

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
As part of a major plant renovation project, the industrial engineering department has been asked to...
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as you know you can follow: Task Duration (minutes) Immediate Predecessor A 0.3 - B 0.6 A C 0.3 B D 0.5 - E 1.2 D F 0.8 C G 1.2 E, F Do each of the following: Draw the precedence diagram. Determine...
A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of...
A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of this process are listed below. Task Duration (hours) Predecessor 1 Predecessor 2 Predecessor 4 A 4 -- B 6 -- C 2 A D 6 A E 3 B C F 3 B C G 5 D E F H 1 G Draw the appropriate network for this project. What would the cycle time be if the goal is to produce 20 units per...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a forecasted demand of 50 units/hour. Find an assembly line that will produce the necessary output. Task Time (in seconds) Immediate Predecessor A 55 - B 30 A C 35 A D 22 B E 50 B,C F 15 C G 5 F H 10 G Part 2. Complete this exercise again, but this time the company expects a forecasted demand of 20 units/hour. Find...
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 100 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 120 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
Do the following crashing problem “from scratch” Develop the time reduction and cost per unit time...
Do the following crashing problem “from scratch” Develop the time reduction and cost per unit time columns in the table. Units: Time is in days, cost is in $. Activity Immediate predecessor(s) Time Cost Crash Time Crash Cost Time Reduction Cost to Crash A -- 10 5000 10 5000 B A 12 1200 11 1300 C A 11 3600 9 4800 D B 5 300 4 600 E C 8 1000 6 2000 F E 9 2400 7 5400 G...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary rivals? How will the acquisition of Reebok by Adidas impact the structure of the athletic shoe industry? Is this likely to be favorable or unfavorable for New Balance? 2- What issues does New Balance management need to address? 3-What recommendations would you make to New Balance Management? What does New Balance need to do to continue to be successful? Should management continue to invest...
Please read the article and answear about questions. Determining the Value of the Business After you...
Please read the article and answear about questions. Determining the Value of the Business After you have completed a thorough and exacting investigation, you need to analyze all the infor- mation you have gathered. This is the time to consult with your business, financial, and legal advis- ers to arrive at an estimate of the value of the business. Outside advisers are impartial and are more likely to see the bad things about the business than are you. You should...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT