Question

The pizza-making process at Mama’s is outlined in the table below. The shop is open 8...

The pizza-making process at Mama’s is outlined in the table below. The shop is open 8 hours a day to fulfill a typical daily demand of 40 pizzas. Sketch the process and balance the assembly to answer the questions below.

Task Predecessor Minutes
A. Roll Dough -- 12
B. Spread Sauce A 4
C. Prepare Toppings -- 7
D. Put Toppings on Pizza B,C 3
E. Sprinkle Cheese D 2
F. Bake Pizza E 10

1. What is the maximum cycle time? (in minutes)

2. What is the theoretical minimum number of workstations? (round appropriately)

3. How many workers (actual workstations) are needed?

4. What is the idle time per cycle? (in minutes)

5. What is the efficiency? (nearest whole number)

Homework Answers

Answer #1

Answer 1: cycle time= 8 hours/40pizzas= 8*60/40= 12 mins

Answer 2: Theoretical no. of workstations= sum of task times/cycle time= 38/12 = 3.16~4 workstations

Answer 3: Actual no. of workstation= 4 only

Workstation

Task

Explanation

Idle time

1

A

12=12, no space for other tasks

0

2

B, C

Because the sum time taken by all mentioned process is less than cycle time, 11<12

1

3

D, E

5<12

7

4

F

10<12

2

Answer 4: total idle time = 10 mins, average idle time= 10/4= 2.5 mins

Answer 5: percentage of idle time = idle time/ no. of workstation* cycle time = 10/(4*12)=0.208 i.e 20.8%

Efficiency = 1-idle %= 1-0.208= 79.2%

Please ask, if you have any doubts through comment section, Kindly rate the answer

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of...
A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of this process are listed below. Task Duration (hours) Predecessor 1 Predecessor 2 Predecessor 4 A 4 -- B 6 -- C 2 A D 6 A E 3 B C F 3 B C G 5 D E F H 1 G Draw the appropriate network for this project. What would the cycle time be if the goal is to produce 20 units per...
TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C...
TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C Beans -B 10 sec D Meat -B 10 sec E Salsa -C, D 10 sec F Cheese -E 5 sec G Sour Cream -E 10 sec H Lettuce -E 10 sec I Wrap -F, G, H 15 sec J Bag -I 5 sec K Checkout/pay -J 25 sec Achieving the above cycle time and output, what is the theoretical number of workstations? Assign tasks...
What costs are relevant when determining how many pizzas a month Zume Pizza must sell to...
What costs are relevant when determining how many pizzas a month Zume Pizza must sell to break even? Zume Pizza uses a combination of robots, artificial intelligence (AI), and GPS in its food trucks to deliver pizzas to customers’ houses just as the pizza is finished baking. Pizzas are actually prepared and baked in the Zume pizza truck by an employee assisted by robots. Zume Pizza started operations in April 2016 and is currently selling about 250 pizzas per day....
Review and submit the Donatos: Finding the New Pizza case study below. Answer the following two...
Review and submit the Donatos: Finding the New Pizza case study below. Answer the following two questions: 2. Evaluate the Wassup meeting as an exploratory methodology to help define the research question. 4. What measurement scales would you have used on the survey that was part of the in-restaurant product tests? Abstract and Written Case: The pizza segment of the fast-food industry is very aggressive. As people’s tastes change and new diets become the rage, restaurant chains must decide if...
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 100 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 120 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a forecasted demand of 50 units/hour. Find an assembly line that will produce the necessary output. Task Time (in seconds) Immediate Predecessor A 55 - B 30 A C 35 A D 22 B E 50 B,C F 15 C G 5 F H 10 G Part 2. Complete this exercise again, but this time the company expects a forecasted demand of 20 units/hour. Find...
for the scenario below: 1) Apply the qualitative analysis by identifying at least 3 issues in...
for the scenario below: 1) Apply the qualitative analysis by identifying at least 3 issues in the above process. Analyse these issues by using a. Adding-value and Waste Analysis b. Issue register, If you find that there are more than three issues, you can focus on the three issues that have the highest impact. 2). Calculate the cycle time efficiency of the as-is process. You can assume a working week of 40 hours. In case there is missing information, you...