Q1

   Barton Sounds, Inc., produces high quality but expensive headsets for audio mania group. Manufacturing the headsets involves fourteen production tasks. Below is shown each task with its required time to finish it and its preceding task or tasks.

   The Barton Sounds determines that there are 480 productive minutes of work available per day. Furthermore, the production schedule requires that 40 units be completed as output form the assembly line each day.

   Please answer the following questions and show all your work for partial credits.

Production Task

Time (min)

Immediate Follower (s)

A

10

B

B

11

D

C

5

D

D

4

G

E

12

F

F

3

G

G

10

H

H

9

I

I

3

END

Total Time

67 min

  1. Draw the precedence diagram for this assembly line.
  2. Given the demand, what is the cycle time for this operation?
  3. Determine the theoretical minimum number of work stations required.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a forecasted demand of 50 units/hour. Find an assembly line that will produce the necessary output. Task Time (in seconds) Immediate Predecessor A 55 - B 30 A C 35 A D 22 B E 50 B,C F 15 C G 5 F H 10 G Part 2. Complete this exercise again, but this time the company expects a forecasted demand of 20 units/hour. Find...
Question 2: A Muscat Tools company manufactures toolkits and supplies to the local and overseas market...
Question 2: A Muscat Tools company manufactures toolkits and supplies to the local and overseas market within the GCC region. In the assembly line, the kits are packed in the tool boxes. The company produces the specified demand rate of toolkit in 8 hours per day with tasks, description of tasks, and time for each task shown in Table Q2a. Draw the precedence diagram and determine the cycle time, and number of workstations;     iii) Balance the line using the longest...
Fine’s Furniture is known for its fine cedar chests. The tasks necessary to assemble the cedar...
Fine’s Furniture is known for its fine cedar chests. The tasks necessary to assemble the cedar chests, the length of time needed to perform each task, and the operations that must be complete prior to subsequent operations are given below. With a production quota of 300 units in a 35 hour week, the desired cycle time is closest to ______. Element Time (min) Predecessors A 2 NONE B 3 A C 5 B D 5 NONE E 4 D F...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary rivals? How will the acquisition of Reebok by Adidas impact the structure of the athletic shoe industry? Is this likely to be favorable or unfavorable for New Balance? 2- What issues does New Balance management need to address? 3-What recommendations would you make to New Balance Management? What does New Balance need to do to continue to be successful? Should management continue to invest...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT