A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of this process are listed below.
Task |
Duration (hours) |
Predecessor 1 |
Predecessor 2 |
Predecessor 4 |
A |
4 |
-- |
||
B |
6 |
-- |
||
C |
2 |
A |
||
D |
6 |
A |
||
E |
3 |
B |
C |
|
F |
3 |
B |
C |
|
G |
5 |
D |
E |
F |
H |
1 |
G |
Draw the appropriate network for this project.
What would the cycle time be if the goal is to produce 20 units per month (the plant operates 160 hours per month)?
What is the theoretical minimum number of workstations needed?
Balance with the most following tasks heuristic. What tasks are assigned to which stations?
What is the efficiency of the line obtained in part d?
please write the the answer, no pic :)
Network:
.
Task | Duration (in hours) | Predecessors | ES | EF |
A | 4 | none | 0 | 4 |
B | 6 | none | 0 | 6 |
C | 2 | A | 4 | 6 |
D | 6 | A | 4 | 10 |
E | 3 | B,C | 6 | 9 |
F | 3 | B,C | 6 | 9 |
G | 5 | D,E,F | 10 | 15 |
H | 1 | G | 15 | 16 |
Total cycle time | 30 | 30 |
Task | Task followed |
A | 6 |
B | 4 |
C | 4 |
D | 2 |
E | 2 |
F | 2 |
G | 1 |
H | 0 |
TCT | Total cycle time | 30 | ||
TC | Target cycle time | 8 | 160/20 | Ans B |
(TCT/TC) | Min Workstation | 3.75 | 4 | Ans C |
Balancing:
Task | Time (in minutes) | Work station | IDLE TIME |
A | 4 | 1 | 4 |
B | 6 | 2 | 2 |
C | 2 | 2 | 0 |
D | 6 | 3 | 2 |
E | 3 | 1 | 1 |
F | 3 | 4 | 5 |
G | 5 | 4 | 0 |
H | 1 | 1 | 0 |
TCT | Total cycle time | 30 | ||
TC | Target cycle time | 8 | 160/20 | Ans B |
(TCT/TC) | Min Workstation | 3.75 | 4 | Ans C |
Idle time | 2 | mins | Sum of spare | |
TCT/(6*8) | Efficiency of general cycle | 62.50% | Theoretical | Ans D |
TCT/(4*8) | Efficiency of general cycle | 93.75% | Actual |
Get Answers For Free
Most questions answered within 1 hours.