Question

A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of...

A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of this process are listed below.

Task

Duration (hours)

Predecessor 1

Predecessor 2

Predecessor 4

A

4

--

B

6

--

C

2

A

D

6

A

E

3

B

C

F

3

B

C

G

5

D

E

F

H

1

G

Draw the appropriate network for this project.

What would the cycle time be if the goal is to produce 20 units per month (the plant operates 160 hours per month)?

What is the theoretical minimum number of workstations needed?

Balance with the most following tasks heuristic. What tasks are assigned to which stations?

What is the efficiency of the line obtained in part d?

please write the the answer, no pic :)

Homework Answers

Answer #1

Network:

.

Task Duration (in hours) Predecessors ES EF
A 4 none 0 4
B 6 none 0 6
C 2 A 4 6
D 6 A 4 10
E 3 B,C 6 9
F 3 B,C 6 9
G 5 D,E,F 10 15
H 1 G 15 16
Total cycle time 30 30
Task Task followed
A 6
B 4
C 4
D 2
E 2
F 2
G 1
H 0
TCT Total cycle time 30
TC Target cycle time 8 160/20 Ans B
(TCT/TC) Min Workstation 3.75 4 Ans C

Balancing:

Task Time (in minutes) Work station IDLE TIME
A 4 1 4
B 6 2 2
C 2 2 0
D 6 3 2
E 3 1 1
F 3 4 5
G 5 4 0
H 1 1 0
TCT Total cycle time 30
TC Target cycle time 8 160/20 Ans B
(TCT/TC) Min Workstation 3.75 4 Ans C
Idle time 2 mins Sum of spare
TCT/(6*8) Efficiency of general cycle 62.50% Theoretical Ans D
TCT/(4*8) Efficiency of general cycle 93.75% Actual
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
As part of a major plant renovation project, the industrial engineering department has been asked to...
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as you know you can follow: Task Duration (minutes) Immediate Predecessor A 0.3 - B 0.6 A C 0.3 B D 0.5 - E 1.2 D F 0.8 C G 1.2 E, F Do each of the following: Draw the precedence diagram. Determine...
TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C...
TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C Beans -B 10 sec D Meat -B 10 sec E Salsa -C, D 10 sec F Cheese -E 5 sec G Sour Cream -E 10 sec H Lettuce -E 10 sec I Wrap -F, G, H 15 sec J Bag -I 5 sec K Checkout/pay -J 25 sec Achieving the above cycle time and output, what is the theoretical number of workstations? Assign tasks...
The pizza-making process at Mama’s is outlined in the table below. The shop is open 8...
The pizza-making process at Mama’s is outlined in the table below. The shop is open 8 hours a day to fulfill a typical daily demand of 40 pizzas. Sketch the process and balance the assembly to answer the questions below. Task Predecessor Minutes A. Roll Dough -- 12 B. Spread Sauce A 4 C. Prepare Toppings -- 7 D. Put Toppings on Pizza B,C 3 E. Sprinkle Cheese D 2 F. Bake Pizza E 10 1. What is the maximum...
Please solve the following problem related to Chapter 6 1. As part of a major plant...
Please solve the following problem related to Chapter 6 1. As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight- hour day. Task times and precedence relationships are as you know you can follows: Task                 Duration (minutes)             Immediate Predecessor _____________________________________________________________ A                             0.3                               - B                             0.6                                A C                              0.3                                B D                             0.5                                  - E                              1.2                                  D F                              0.8                                  C G                             ...
QRS Corp. is designing a product layout for a new product. They plan to use this...
QRS Corp. is designing a product layout for a new product. They plan to use this production line ten hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Task Time (Secs) Immediate Predecessor a 34 none b 20 a c 10 b d 16 b e 10 c f 24 d,e g 38 f For output to equal forecasted demand, what will be the...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
Wild Widget must set up an assembly line for widgets. Forecasts show that 52 units per...
Wild Widget must set up an assembly line for widgets. Forecasts show that 52 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: Task Time (seconds) Predecessors A 10 – B 33 A C 23 A D 24 C,B E 20 D F 18 D G 36 E,F b. What is the takt time? (Round your answer to the nearest whole number.) c. What is the theoretical number of workstations? (Round up...
Pirmin's bike shop is behind on a custom bike and needs to crash 8 hours of...
Pirmin's bike shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash. Activity Normal Duration (hr) Normal Cost ($) Crash Duration (hr) Crash Cost ($) Immediate Predecessors A 2 10 2 N/A NONE B 3 15 2 23 A C 5 25 4 30 B D 3 20 1 24 C...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a forecasted demand of 50 units/hour. Find an assembly line that will produce the necessary output. Task Time (in seconds) Immediate Predecessor A 55 - B 30 A C 35 A D 22 B E 50 B,C F 15 C G 5 F H 10 G Part 2. Complete this exercise again, but this time the company expects a forecasted demand of 20 units/hour. Find...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT