Question

On December 31, 2019, Mass Construction Inc. signs a contract with the state of Massachusetts Department...

On December 31, 2019, Mass Construction Inc. signs a contract with the state of Massachusetts Department of Transportation to manufacture a bridge over the Merrimack. Mass Construction anticipates the construction will take three years. The company's accountants provide the following contract details relating to the project:

Contract price

$520 million

Estimated construction costs

$300 million

Estimated total profit

$220 million


During the three-year construction period, Tri-State incurred costs as follows:

2020

$ 60 million

2021

$150 million

2022

$ 90 million


Tri-State uses the percentage of completion method to recognize revenue. Which of the following represent the profits recognized in 2020, 2021, and 2022?

A.

$44 million, $110 million, $66 million

B.

$52 million, $312 million, $156 million

C.

None of the above

D.

$104 million, $260 million, $156 million

E.

$104 million, $110 million, $66 million

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On December 31, 2019, Shawshank Construction Inc. signs a contract to manufacture a bridge which it...
On December 31, 2019, Shawshank Construction Inc. signs a contract to manufacture a bridge which it anticipates the construction will take three years. The company’s accountants provide the following contract details relating to the project: Contract price: $780 million Estimated construction costs: $600 million Estimated total profit: $180 million During the three-year construction period, Shawshank incurred costs as follows: 2020 $ 60 million 2021 $360 million 2022 $180 million Shawshank uses the cost-to-cost method to recognize revenue. Which of the...
On December 31 of the current year, State Construction Inc. signs a contract with the state...
On December 31 of the current year, State Construction Inc. signs a contract with the state of West Virginia Department of Transportation to manufacture a bridge over the New River. State Construction anticipates the construction will take three years. The company’s accountants provide the following contract details relating to the project: Contract price $624 million Estimated construction costs $480 million Estimated total profit $144 million During the three-year construction period, State Construction incurred costs as follows: Year 1 $48 million...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
During 2020, Indigo Corporation started a construction job with a contract price of $5.46 million. Indigo...
During 2020, Indigo Corporation started a construction job with a contract price of $5.46 million. Indigo ran into severe technical difficulties during construction but managed to complete the job in 2022. The contract is non-cancellable. Under the terms of the contract, Indigo sends billings as revenues are earned. Billings are non-refundable. The following information is available Costs incurred to date 2020 : $780,000 2021: $2,730,000 2022: $5,360,000 Estimated costs to complete: 2020: $4,095,000 2021: $2,730,000 2022: $ -0- Required: Calculate...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,225,000. During 2021, costs of $2,090,000 were incurred, with estimated costs of $4,090,000 yet to be incurred. Billings of $2,608,000 were sent, and cash collected was $2,340,000. In 2022, costs incurred were $2,608,000 with remaining costs estimated to be $3,735,000. 2022 billings were $2,858,000, and $2,565,000 cash was collected. The project was completed in 2023 after additional costs of...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.4 million and was expected to be completed in July 2022 at a total estimated cost of $82.4 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer...
During 2019, Almon Inc. started a construction job with a contract price of $8000. The job...
During 2019, Almon Inc. started a construction job with a contract price of $8000. The job was completed in 2019 and information for the three years of construction is as follows: 2019 2020 2021 TOTAL costs incurred to date (ie sum of all costs, for all years, incurred at the end of the year) $2,000 $4,500 $7,600 Estimated costs to complete (as estimated at year end) 5,000 2900 -0- Billings to date 2,200 6,000 8,000 Collections to date 1,600 4,800...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $760,380 $1,059,000 Estimated costs to complete 616,100 341,620 –0– Billings to date 299,000 905,000 1,610,000 Collections to date 268,000 818,000 1,421,000 (a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar...
During 2020, Blossom Company started a construction job with a contract price of $1,184,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,184,000. The job was completed in 2022. The following information is available. The contract is non-cancellable. 2020 2021 2022 Costs incurred to date $296,000 $610,500 $791,800 Estimated costs to complete 444,000 203,500 0 Billings to date (non-refundable) 222,000 666,000 1,184,000 Collections to date 199,800 599,400 1,054,500 (a) Partially correct answer iconYour answer is partially correct. Calculate the amount of gross profit to be recognized each year, assuming...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT