Question

On December 31 of the current year, State Construction Inc. signs a contract with the state...

On December 31 of the current year, State Construction Inc. signs a contract with the state of West Virginia Department of Transportation to manufacture a bridge over the New River. State Construction anticipates the construction will take three years.

The company’s accountants provide the following contract details relating to the project:

Contract price $624 million
Estimated construction costs $480 million
Estimated total profit $144 million

During the three-year construction period, State Construction incurred costs as follows:

Year 1 $48 million
Year 2 $288 million
Year 3 $144 million

State Construction uses the cost-to-cost method to recognize revenue.
Which of the following represent the revenue recognized in Year 1, Year 2, and Year 3?

Select one:

a. $62 million, $312 million, $250 million

b. $62 million, $374 million, $187 million

c. $0 million, $0 million, $624 million

d. $60 million, $376 million, $188 million

e. None of these are correct.

Homework Answers

Answer #1

Answer:

Option b. $62 million, $374 million, $187 million

Calculation:

Here we need to calculate the the revenue recognized in Year 1, Year 2, and Year 3.

For that we need to take the Construction costs incurred for the Year 1, Year 2, and Year 3. And then we need to calculate the Percentage to total costs.

Year 1 Year Year 3 Total
Construction costs incurred 48 million 288 million 144 million 480 million
Percentage to total costs 10% 60% 30% 100%

Then we need to find the revenue recognized in Year 1, Year 2, and Year 3 by multiplying the Percentage to total costs with the contract price.

Revenue recognized:

Year 1 = 10% x 624 million = 62 million

Year 2 = 60% x 624 million = 374 million

Year 3 = 30% x 624 million = 187 million

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On December 31, 2019, Mass Construction Inc. signs a contract with the state of Massachusetts Department...
On December 31, 2019, Mass Construction Inc. signs a contract with the state of Massachusetts Department of Transportation to manufacture a bridge over the Merrimack. Mass Construction anticipates the construction will take three years. The company's accountants provide the following contract details relating to the project: Contract price $520 million Estimated construction costs $300 million Estimated total profit $220 million During the three-year construction period, Tri-State incurred costs as follows: 2020 $ 60 million 2021 $150 million 2022 $ 90...
On December 31, 2019, Shawshank Construction Inc. signs a contract to manufacture a bridge which it...
On December 31, 2019, Shawshank Construction Inc. signs a contract to manufacture a bridge which it anticipates the construction will take three years. The company’s accountants provide the following contract details relating to the project: Contract price: $780 million Estimated construction costs: $600 million Estimated total profit: $180 million During the three-year construction period, Shawshank incurred costs as follows: 2020 $ 60 million 2021 $360 million 2022 $180 million Shawshank uses the cost-to-cost method to recognize revenue. Which of the...
On January 1, Year 1, a contractor began work on a $3.2 million construction contract that...
On January 1, Year 1, a contractor began work on a $3.2 million construction contract that is expected to be completed in 3 years. The contractor concludes that it is appropriate to recognize revenue over time using the input method based on costs incurred (cost-to-cost method). At the inception date, the estimated cost of construction was $2.4 million. The following data relate to the actual and expected construction costs: Year 1 Year 2 Year 3 Cost incurred $720,000 $1,170,000 $1,110,000...
In 2021, the Southgate Construction Company entered into a contract to construct a bridge for $12,000,000....
In 2021, the Southgate Construction Company entered into a contract to construct a bridge for $12,000,000. The bridge was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $1,840,000 $3,760,000 $4,500,000 Estimated costs to complete as of year-end $6,160,000 $4,400,000 $0 Billings during the year $3,000,000 $4,000,000 $5,000,000 Cash collections during thee year $2,600,000 $3,900,000 $5,100,000 Southgate recognizes revenue using the completed contract method. What amount will Southgate show on...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,225,000. During 2021, costs of $2,090,000 were incurred, with estimated costs of $4,090,000 yet to be incurred. Billings of $2,608,000 were sent, and cash collected was $2,340,000. In 2022, costs incurred were $2,608,000 with remaining costs estimated to be $3,735,000. 2022 billings were $2,858,000, and $2,565,000 cash was collected. The project was completed in 2023 after additional costs of...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract price was $1,600,000. The Job was completed in 2018.                                                                                 2016                       2017                       2018 Costs incurred to date                                    400000                  935000                  1070000 Estimated costs to complete                       700000                  165000                  0 Billings to date                                                  300000                  900000                  1600000 Collections to date                                           270000                  810000                  1525000 Compute the amount of Gross Profit to be recognized for 2016 and 2017 assuming that ole is required to recognize revenue overtime. Compute the...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Evans Construction, Inc. experienced the following construction activity in 2018, the first year of operations. Contract...
Evans Construction, Inc. experienced the following construction activity in 2018, the first year of operations. Contract Total Contract Price Billings Through 12/31/18 Cash Collections Through 12/31/18 Costs Incurred Through 12/31/18 Estimated Additional Costs to Complete X $261,000 $171,000 $156,000 $184,000 $  64,000 Y 331,000 116,000 116,000 102,000 253,000 Z 234,000 234,000 200,000 160,000 -0- $826,000 $521,000 $472,000 $446,000 $317,000 Prepare a partial income statement to indicate how the above contract information would be reported. Evans uses the completed-contract method Prepare a...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017     $35 million Construction in progress (as of 12/31/2017)                                                                                                    $50 million Accounts Receivable from construction billings (as...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT