Question

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,225,000. During 2021, costs of $2,090,000 were incurred, with estimated costs of $4,090,000 yet to be incurred. Billings of $2,608,000 were sent, and cash collected was $2,340,000.

In 2022, costs incurred were $2,608,000 with remaining costs estimated to be $3,735,000. 2022 billings were $2,858,000, and $2,565,000 cash was collected. The project was completed in 2023 after additional costs of $3,890,000 were incurred. The company’s fiscal year-end is December 31. This project does not qualify for revenue recognition over time.

Required:
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2021
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2022

Homework Answers

Answer #1

Answer to requested parts of the question:

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
In 2021, the Southgate Construction Company entered into a contract to construct a bridge for $12,000,000....
In 2021, the Southgate Construction Company entered into a contract to construct a bridge for $12,000,000. The bridge was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $1,840,000 $3,760,000 $4,500,000 Estimated costs to complete as of year-end $6,160,000 $4,400,000 $0 Billings during the year $3,000,000 $4,000,000 $5,000,000 Cash collections during thee year $2,600,000 $3,900,000 $5,100,000 Southgate recognizes revenue using the completed contract method. What amount will Southgate show on...
Chance Company had two operating divisions, one manufacturing farm equipment and the other office supplies. Both...
Chance Company had two operating divisions, one manufacturing farm equipment and the other office supplies. Both divisions are considered separate components as defined by generally accepted accounting principles. The farm equipment component had been unprofitable, and on September 1, 2018, the company adopted a plan to sell the assets of the division. The actual sale was completed on December 15, 2018, at a price of $640,000. The book value of the division’s assets was $1,090,000, resulting in a before-tax loss...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           9,000          21,000         29,000 Collections to date                     4,000           14,000         25,000 If the company uses the percentage-of-completion method, an inventory/current liability of $___________should be shown on the balance sheet at December 31, 2021 related...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           9,000          21,000         29,000 Collections to date                     4,000           14,000         25,000 If the company uses the percentage-of-completion method, an inventory/current liability of $___________should be shown on the balance sheet at December 31, 2021 related...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.4 million and was expected to be completed in July 2022 at a total estimated cost of $82.4 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017                                                                                                                                                              $35 million Construction in progress (as of 12/31/2017)                                                                                                   $50 million Accounts Receivable from construction billings (as of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT