Question

In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The...

In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.4 million and was expected to be completed in July 2022 at a total estimated cost of $82.4 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer to the customer until completion. Sandhill’s year-end was September 30 and follows ASPE.

By the end of September, 2020, Sandhill had incurred $8,240,000 in costs and had invoiced $10,200,000 in progress billings. $8,300,000 of the progress billings had been collected.

By September 30, 2021, Sandhill had incurred $43,175,000 in total costs and had invoiced $45,500,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,500,000 in total had been collected. Also, Sandhill reviewed its cost estimates on the project, and now believed the parking garage would cost $78.5

1. Using the completed-contract method, prepare all journal entries required for the year ended September 30, 2020. Use Materials, Cash, Payables for costs incurred to date.

2.Using the completed-contract method, prepare all journal entries required for the year ended September 30, 2021. Use Materials, Cash, Payables for costs incurred to date.

3. Prepare the journal entry to record revenue and cost of construction on completion of the project, assuming all billings are completed and the total actual cost is the same as the 2021 estimate. Use Materials, Cash, Payables for costs incurred to date.

Homework Answers

Answer #1
Facts of the Question
Start of construction Feb-20
Total Contract Price $9,04,00,000
Total Estimated Cost $8,24,00,000
Revised estimated cost on 2021 $7,85,00,000
Expected completion Jul-22
1 Using the completed-contract method, prepare all journal entries required for the year ended September 30, 2020. Use Materials, Cash, Payables for costs incurred to date.
Construction in Process Debit $82,40,000
     To Payable (or Cash/Bank) Credit $82,40,000
(Being cost incurred for the construction project is accumulated in an asset account i.e. Construction in Process)
Contracts Receivable Debit $1,02,00,000
     To Progress Billings Credit $1,02,00,000
(Being progress billing is recorded to contra account to Construction in Progress)
Cash/Bank Debit $83,00,000
     To Contracts Receivable Credit $83,00,000
(Being partial amount collected for progress billing made on 2020)
2 Using the completed-contract method, prepare all journal entries required for the year ended September 30, 2021. Use Materials, Cash, Payables for costs incurred to date.
Construction in Process Debit $3,49,35,000
     To Payable (or Cash/Bank) Credit $3,49,35,000
(Being cost incurred for the construction project is accumulated in an asset account i.e. Construction in Process. Cost incurred in year 2021 is $43,175,000 - Cost recognized in 2020 i.e, $82,40,000)
Contracts Receivable Debit $3,53,00,000
     To Progress Billings Credit $3,53,00,000
(Being progress billing is recorded to contra account to Construction in Progress. Amount billed in 2021 is $45,500,000 - amount billed in 2020 i.e. $1,02,00,000)
Cash/Bank Debit $2,22,00,000
     To Contracts Receivable Credit $2,22,00,000
(Being partial amount collected for progress billing made on 2021. Amount collected in year 2021 is $30,500,000- collection of 2020 i.e. 83,00,000)
3 Prepare the journal entry to record revenue and cost of construction on completion of the project, assuming all billings are completed and the total actual cost is the same as the 2021 estimate. Use Materials, Cash, Payables for costs incurred to date.
Construction in Process Debit $3,53,25,000
     To Payable (or Cash/Bank) Credit $3,53,25,000
(Being cost incurred for the construction project is accumulated in an asset account i.e. Construction in Process. Cost incurred in year the year of completion is $7,85,00,000 - cost incurred in 2020 and 2021)
Contracts Receivable Debit $4,49,00,000
     To Progress Billings Credit $4,49,00,000
(Being progress billing is recorded to contra account to Construction in Progress. Amount billed in the year of completion is $9,04,00,000 i.e. total contract price - amount billed in 2020 and 2021)
Cash/Bank Debit $5,99,00,000
     To Contracts Receivable Credit $5,99,00,000
(Being partial amount collected for progress billing made on 2021. Amount collected in the year of collection is total revenue billed - amount collected in year 2020 and 2021)
Construction in Process Debit $1,19,00,000
Construction cost Debit $7,85,00,000
     To Construction Revenue Credit $9,04,00,000
(Being revenue for the completed contract recognized)
Progress Billings Debit $9,04,00,000
     To Construction in Process Credit $9,04,00,000
(Being construction in progress account and progress billing account closed on completion of project)
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building....
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building. Lion estimated that the total cost would be $ 320,000. Construction started immediately because the required completion date was August 31, 2021. Lion’s relevant data relating to this construction project were as follows:      2020             2021 Actual costs incurred $ 120,000      $ 204,000 Estimated costs to complete 200,000               -0- Progress billings 112,000        248,000 Collections 110,000        250,000 Instructions (show all supporting calculations) Calculate how much...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of $5,820,000. Bramble estimated total construction costs would be $4,016,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date. $1,506,000 $2,652,000 $4,610,000 Estimated costs to complete. 2,510,000 1,768,000 -0- Customer billings to date 2,220,000 4,016,000 5,620,000 Collections to date 2,020,000 3,520,000 5,520,000 Fill in the...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $40,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           8,000          18,000         28,000 Collections to date                     5,000           15,000         26,000 If the company uses the percentage-of-completion method, the gross profit to be recognized in 2021 is___________________________ .
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Correct answer iconYour answer is correct. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           9,000          21,000         29,000 Collections to date                     4,000           14,000         25,000 If the company uses the percentage-of-completion method, an inventory/current liability of $___________should be shown on the balance sheet at December 31, 2021 related...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           9,000          21,000         29,000 Collections to date                     4,000           14,000         25,000 If the company uses the percentage-of-completion method, an inventory/current liability of $___________should be shown on the balance sheet at December 31, 2021 related...
PRACTICAL QUESTION                                       &nb
PRACTICAL QUESTION                                                                                          Tiger Construction Ltd signs a contract on 1 May 2018 to build a theme park. The construction is scheduled to commence on 1 July 2018 and the estimated date of completion is 30 June 2021. The total contract price is $5m and the cost of the park is initially estimated at $4.5m. The following data relates to the construction period: For the year ended 30 June 2019 2020 2021 $ $ $ Costs to date 1,700,000 3,000,000 4,800,000...
A company began work in 2020 on a contract for $7,800. Other data are as follows:...
A company began work in 2020 on a contract for $7,800. Other data are as follows:                                                        2020                         2021 Costs incurred to date                 $3,000 $5,600 Estimated costs to complete         2,000       — Billings to date    3,100                   7,800 Collections to date                       1,000                      4,400 If the company uses the percentage-of-completion method, for the journal entry that records construction revenue, construction expense, and gross profit for 2020, how much will be recorded for Construction in Process?
Curtis Co. entered into a long-term contract in 2020. The contract price was $2,250,000. The following...
Curtis Co. entered into a long-term contract in 2020. The contract price was $2,250,000. The following data pertain to the first two years that the contract was in process. 2020                              2021               Costs incurred to date                                    $   570,000                  $1,557,500    Estimated costs to complete as of 12/31       1,330,000                         667,500 Billings to date                                                     650,000                     1,250,000    Cash collections to date                                     600,000                     1,150,000 1. Using the percentage-of-completion method: A. Compute gross profit to be reported in each...