Question

A project to build a new bridge seems to be going very well since the project...

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 65% complete. The planners were only expecting to be 55% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,424,000 and it was done for only $1,304,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,504,000 but was actually done for $9,004,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,504,000. To date they have spent $5,004,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)

Homework Answers

Answer #1

Actual Cost = 1,304,000 + 9,004,000 + 5,004,000 = $15,312,000

Planned Value = 1,424,000 + 10,504,000 + 55% of 8,504,000 = $16,605,200

Earned Value = 1,424,000 + 10,504,000 + 65% of 8,504,000 = $17,455,600

Schedule Variance =Earned Value – Planned Value

= 17,455,600 - 16,605,200

= $850,400

Schedule Performance Index = (Earned Value) / (Planned Value) = 17,455,600/16,605,200 = 1.051

Cost Performance Index = (Earned Value) / (Actual Cost) = 17,455,600/15,312,000 = 1.140

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Your project to obtain charitable donations is now 48 days into a planned 58-day project. The...
Your project to obtain charitable donations is now 48 days into a planned 58-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 44 days of the project and to bring in $24,600. Even though we are 48 days into the project, we still see that we have only 90% of this activity complete. The second activity relates to company donations and is scheduled to...
CASE STUDY Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company...
CASE STUDY Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a philosophy that the project manager would be assigned during proposal preparation, assist in the preparation of the proposal, and take on the role of the project manager after contract award, assuming the company would be awarded the contract. Usually, contract go-ahead would take place within a week or two after contract award. That made project staffing relatively easy for most of the...
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a...
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a philosophy that the project manager would be assigned during proposal preparation, assist in the preparation of the proposal, and take on the role of the project manager after contract award, assuming the company would be awarded the contract. Usually, contract go-ahead would take place within a week or two after contract award. That made project staffing relatively easy for most of the project managers....
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a...
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a philosophy that the project manager would be assigned during proposal preparation, assist in the preparation of the proposal, and take on the role of the project manager after contract award, assuming the company would be awarded the contract. Usually, contract go-ahead would take place within a week or two after contract award. That made project staffing relatively easy for most of the project managers....
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Mick is a project manager at Zarlink, a multinational manufacturer of semiconductors for a variety of...
Mick is a project manager at Zarlink, a multinational manufacturer of semiconductors for a variety of high-technology military, medical and consumer applications. Mick is also a part-time MBA student at his local university. As part of his MBA, Mick has to complete a dissertation on a management topic of his choice. Since Mick had recently been selected to embed a new quality management system called TS 16949 into his manufacturing site at Swindon in the West of England it seemed...
The Harborside Inn, located on the New England coast, is a 125-room luxury hotel. The inn's...
The Harborside Inn, located on the New England coast, is a 125-room luxury hotel. The inn's guests are predominantly upper middle class in that the going rate is about $100 per day per person. The hotel grounds include 30 acres of lawns and gardens. Their nine-hole golf course winds its way around a picturesque trout pond. The hotel grounds were meticulously cared for and yet efforts at cultivating beauty could not match the natural beauty which was so much a...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do several international Camp Noah projects. Last year the French government asked for resources for children in Southeastern France who had been affected by floods; LSS responded within 15 weeks with a French Camp Noah curriculum that met many of the project objectives. The Board of Directors of LSS commended the effort; international expansion was added to this year’s strategic objectives for the LSS organization....