- Which of the following best describes a project management
plan?
- The project charter, WBS, and project scope statement
- The schedule, management plans, and budget
- A formal, approved document used to control the project
- The project manager's plan for managing and controlling the
work
- The engineering department wants the project objective to be a
10 percent improvement in throughput. The information technology
department wants no more than 5 percent of its resources to be used
on the project. Management, who is also your sponsor, wants the
project team to decrease tax liability. The best thing you can do
is:
- Include the engineering and information technology objectives,
but hold further meetings regarding management's objective.
- Include only management's objective.
- Put a plan together that meets all the objectives.
- Have these people get together and agree on one objective.
- It is determined that the benefit of the internal ticket
tracking system project will be in the range of US $150,000 to US
$230,000. The overall cost of the project is approximately US
$250,000. Team members could learn new skills and the staff would
benefit from its use. Which of the following tools could be used by
management to determine whether this project should be done?
- Design of experiments
- Cost-benefit analysis
- Statistical sampling
- Cost of quality
- While constructing a new drug manufacturing plant, you discover
a leak in a pipe that has released chemicals into the ground. It
was difficult to acquire the necessary government approval and
community support for the plant, and management has told you to be
particularly careful to not upset the community. You are uncertain
of whether the chemicals could leak into the groundwater or cause
any damage. What should you do?
- Inform local officials, and ask for their help.
- Start to write articles in the local paper about how poorly
treated the local drinking water is.
- Wherever possible, communicate all the great benefits of the
plant to the community.
- Follow the instructions to avoid upsetting the community and do
nothing.
- A project manager is working on a complex project with people
from around the world. The project schedule is set, but the work
packages require detailed integration with other work packages done
by the buyer. What is the best thing the project manager could use
to control this situation?
- Historical information
- Work authorization system
- Configuration management
- Change control board
- Objectives documented in the project charter should:
- Be measurable
- Be free from risk
- Relate to the project scope
- Be broad enough to ensure all the stakeholders are
satisfied
- Which of the following rules should apply to international
dealings on your project?
- Always apply the business practices of your own country.
- Do not violate any basic fundamental human rights.
- You have your way, I have mine.
- Do whatever it takes to manage the project successfully.
- Your company has a policy that only a certain hotel chain may
be used for business travel. You discover that a more expensive
hotel is offering a discount on the days you need to be in town.
What should you do?
- Ask your manager for permission to use the other hotel
chain.
- Use the company's approved hotel chain.
- Provide justification on your expense report for using the
other hotel chain.
- Contact the hotel chain to negotiate a better rate.
- Your project is expected to be critical for your organization's
three-year growth strategy. It has the funding it needs and has
been allocated the people needed to build the product. Your project
team will be distributed throughout more than 10 locations
globally. There are, however, limited training resources. The
product will be developed, tested, and sold internationally. Which
of the following would best prevent cultural issues on your
project?
A. Training in the language of one of the
countries involved in the project
B. Training in the project management process
to be used
C. Training on mannerisms of the other
countries
D. Training in cultural differences between the
other countries
- A project manager is assigned to an environmental engineering
project chartered to build a reverse flow fish ladder on a river.
An environmental group is performing the project. This type of
project has never been done before. The project manager has decided
to build a basic project schedule and to detail the work of each
part as the current part nears completion. What best describes what
the project manager is doing?
A. The process of planning change control
B. The process of progressive elaboration
C. The process of reiterating a plan in the
same order from project to project
D. The controlling process of ensuring that
project objectives are met by taking corrective action when
necessary
- You have been involved in creating the project charter but
could not get it approved. Your manager and his manager have asked
that the project begin immediately. Which of the following is the
best thing to do?
- Show your manager the impact of proceeding without
approval.
- Start work on only the critical path activities.
- Focus on completing projects that have signed project
charters.
- Set up an integrated change control process.
33 You are leading the team during the course of your new
product development project for the defense industry client. You
notice that most of the changes occurring on the project come from
the research department. These changes have not yet negatively
affected your baselines, but you are concerned that they might in
the future. What should you do?
- Change your communications management plan, so only you are
assigned to interact with the research department.
- Ask the research department to assign one person to be your
liaison.
- Assign a team member to work solely with the research
department.
- Talk to the research department to understand the reasons for
the changes.
- You managing a project and are well into the development phase.
Approximately 35 percent of the interim deliverables have been
created, tested, and approved, and another 25 percent are nearing
completion, or are already in testing. Which of the following best
describes your role regarding project changes?
- Discover changes as early as possible.
- Prevent changes that affect the project scope.
- Have the sponsor approve all changes.
- Prevent the addition of profit in sellers' changes.
- Instead of celebrating the end of the project, the stakeholders
are breathing a sigh of relief. None of them were confident the
project would meet the end date. Which of the following is probably
not one of the reasons this project had difficulty?
- Lack of milestones
- Lack of a staffing management plan
- Lack of a communications management plan
- Lack of a payback period
- Your project is almost complete when a team member notifies you
she has added extra functionality to the product of the project,
and that she went ahead with the change since it could be made
quickly and not affect the major constraints. She tells you there
was no impact on the cost or schedule. What should you do as a
result of this change?
- Issue an approved change request.
- Instruct the team member to remove the extra
functionality.
- Implement change control processes to track the change.
- Understand what functionality was added.
- Halfway through the project, the client considers cancelling
the remaining work and the contract. It would be best to look at
which of the following to determine the purpose of the
project?
- The chart of accounts, to determine the estimate at
completion
- The WBS dictionary, to confirm the scope is correct
- The project charter, to review the project description and
need
- The risk response plan, to evaluate alternatives
- The project management process in which the majority of project
work is produced is:
- Define Scope
- Conduct Procurements
- Direct and Manage Project Work
- Develop Project Management Plan
- You are overseeing your team in the creation of deliverables on
a complex business process solutions project. Team members are
located throughout the country, so team meetings are conducted
virtually. The current SPI is 0.86, and the CPI is 0.79. You
attribute the low SPI and CPI measurements to the difficulties of
managing a large, geographically disbursed team. You have
implemented new processes and procedures designed to improve the
quality of interim deliverables, and hope to thereby increase the
efficiency of your team, and to reduce the amount of rework you
have been experiencing. When executing a project, you should pay
special attention to:
- Each individual knowledge area
- Cost
- Quality
- Schedule
- You have been assigned as the project manager for a
construction project that has had two previous project managers,
when you discover a deliverable will be late. Your analysis shows
the item can be purchased from another seller at a higher price
without affecting the schedule. What is the best thing to do?
- Change the project management plan to reflect the new due
date.
- Crash or fast track the project.
- Evaluate the impact of the decision.
- Discuss the impact with the customer and ask for a
decision.
- A project may be selected based on all of the following
except:
- The number of resources required
- Net present value (NPV)
- Value analysis
- Benefit measurement
- There are two projects for the organization to choose between:
Project A with an NPV of US $45,000 and Project B with an NPV of US
$85,000. What is the opportunity cost of selecting project B?
- $130,000
- $85,000
- $45,000
- $40,000
- Management has promised you part of the incentive fee from the
customer if you complete the project early. While finalizing a
major deliverable, your team informs you that the deliverable meets
the requirements in the contract, but will not provide the
functionality the customer needs. If this deliverable is late, the
project will not be completed early. What action should you
take?
- Cut other activities in a way that will be unnoticed to provide
more time to fix the deliverable.
- Start to compile a list of delays caused by the customer to
prepare for negotiations.
- Provide the deliverable as it is.
- Inform the customer of the situation, and work out a mutually
agreeable solution.
- Your organization is approached by company A to produce certain
software. In the middle of the project, a competitor of company A
asks your organization to produce similar software for them. What
should you do?
- Do not do the new project since it is a conflict of
interest.
- Review the intellectual property clause for the first project
to help determine the approach to take.
- Do the project with all new work.
- Do the project using some of the material created for company
A.
- Which of the following best describes when a project phase is
generally concluded?
- When the work for the next phase is ready to start
- When the deliverables are accepted
- When it is scheduled in the milestone schedule
- When the work is done
- When is it best to perform the Close Project or Phase
process?
- At the end of project planning
- At the beginning of the project with verification throughout
the project
- During project closure
- At the end of each project phase
- The organization has four projects from which to choose one.
Project A is being done over a six-year period and has a net
present value (NPV) of US $70,000. Project B is being done over a
three-year period and has an NPV of US $30,000. Project C is being
done over a five-year period and has an NPV of US $40,000. Project
D is being done over a one-year period and has an NPV of US
$60,000. Which project should they choose?
- Project D
- Project A
- Project C
- Project B