Background
Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a
philosophy that the project manager would be assigned during proposal preparation, assist in the
preparation of the proposal, and take on the role of the project manager after contract award,
assuming the company would be awarded the contract. Usually, contract go-ahead would take
place within a week or two after contract award. That made project staffing relatively easy for
most of the project managers. It also allowed the company to include in the proposal a detailed
schedule based upon resources that would be assigned upon contract award and go-ahead. During
proposal preparation, the functional managers would anticipate who would be available for
assignment to this project over the next few weeks. The functional managers could then estimate
with reasonable accuracy the duration and effort required based upon the grade level of the
resources to be assigned. Since the go-ahead date was usually within two weeks of contract award
and the contract award was usually within a week or so after proposal submittal, the schedule that
appeared in the proposal was usually the same schedule for the actual project with very few
changes. This entire process was based upon the actual availability of resources rather than the
functional managers assuming unlimited resources and using various estimating techniques.
While this approach worked well on most projects, Sarah’s new project had a go-ahead date of
three months after contract award. For the functional managers, this created a problem estimating
the effort and duration. Estimating now had to be made based upon the assumption of unlimited
availability rather than the availability of limited resources. Functional managers were unsure as
to who would be available three or four months from now, yet some type of schedule had to appear
in the proposal.
Sarah knew the risks. When the proposal was being prepared for Sarah’s proposal, the functional
managers assumed that the average worker in the department would be available and assigned to
the project after go-ahead. The effort and duration estimates were then made based upon the
average employee. If, after go-ahead, above-average employees would be assigned to her project,
she could possibly see the schedule accelerated but had to make sure that cost overruns did not
happen because the fully loaded salary of the workers may be higher that what was estimated in
the proposal. If below-average workers are assigned , a schedule slippage might occur and Sarah
would have to look at possible schedule compression techniques, hopefully without incurring
added costs.
Award of Contract
Sarah’s company was awarded the contract. Sarah had silently hoped that the company would not
get the contract, but it did. As expected, the go-ahead date was three months from now. This
created a problem for Sarah because she was unsure as to when to begin the preparation of the
detailed schedule. The functional managers told her that they could not commit to an effort and
duration based upon actual limited resource availability until somewhere around two to three
weeks prior to actual go-ahead date. The resources were already spread thin across several projects
and many of the projects were having trouble. Sarah was afraid that the worse case scenario would
come true and that the actual completion date would be longer than was in the proposal. Sarah was
certainly not happy about explaining this to the client should it be necessary to do so.
P a g e 3 | 4
Approaching Go-Ahead Date
As the go-ahead date neared , Sarah negotiated with the functional managers for resources.
Unfortunately, her worst fears came true when, for the most part, she was provided with only
average or above-average resources. The best resources were in demand elsewhere and it was
obvious that they would not be available for her project.
Using the efforts and durations provided by the functional managers, Sarah prepared the new
schedule. Much to her chagrin, she would be at least two weeks late on the four-month project.
The client would have to be told about this. But before telling the client, Sarah decided to look at
ways to compress the schedule. Working overtime was a possibility, but Sarah knew that overtime
could lead to burned-out workers and the possibility of mistakes being made would increase. Also,
Sarah knew that the workers really did not want to work overtime. Crashing the project by adding
more resources was impossible because there were no other resources available. Outsourcing some
of the work was not possible as well because of the statement of work identified proprietary
information provided by the client and that the contract would not allow any outsourcing of the
work to third party. Because of the nature of the work, doing some of the work in parallel rather
series was not possible. There was always a chance that the assigned resources could get the job
done ahead of schedule but Sarah believed that a schedule delay was inevitable
Time for a decision
Sarah had to make a decision about when and how to inform the client of the impending schedule
delay. If she told the truth to the client right now, the client might understand but might also believe
that her company lied in the proposal. That would be an embarrassment for her company. If she
delayed informing the client, there might a chance that the original schedule in the proposal would
be adhered to, however slim. If the client is informed at the last minute about the delay, it could
be costly for the client and equally embarrassing for her company
Is it possible to convince a client that the schedule is just a
rough guess during
competitive bidding and finalization of the schedule can be made
only after go-ahead?
This should not be essential to prove the client a thing as good planning would have prohibited this. While there is a option for a good faith approximation, they assumes that the approximation was made in fairness. Sarah was aware of the risks that a three-month lead until the go-ahead date would bring with it. she let the functional managers simply estimate average-experience workers, at average effort, and average duration, in its place of taking the time to assess the likelihood and influence of these suppositions. not holding true and then formulating possible risk responses in advance. If at any time it becomes deceptive that the customer’s milestones cannot be met, the customer should be informed of this directly. Through effective planning and risk management, the project manager should always try to plan for all possibilities and not simply hope for the best.
Get Answers For Free
Most questions answered within 1 hours.