Question

Case Scenario LSS is engaged in flood relief support nationally and has been asked to do...

Case Scenario

LSS is engaged in flood relief support nationally and has been asked to do several international Camp Noah projects. Last year the French government asked for resources for children in Southeastern France who had been affected by floods; LSS responded within 15 weeks with a French Camp Noah curriculum that met many of the project objectives. The Board of Directors of LSS commended the effort; international expansion was added to this year’s strategic objectives for the LSS organization.

The French Camp Noah project was not completed on time, the scope had to be reduced to meet even the delayed time frame, the cost was 30% higher than expected, and quality control measurements indicated that there were many small disappointments within the project. During the French Camp Noah project, the project manager had been unable to keep the team focused on the planning process. Initiation took longer than expected, and executing work on the project was well under-way before detailed planning even began. Many team members skipped planning meetings in favor of just using the time to do the project work. The gap between the plans and the execution became so large that the project manager finally just started having ad hoc meetings and documenting the notes from the meetings, and stopped looking at the plans.

At a post-project review meeting, the team agreed that, although they felt they had done everything possible given the short time-frame, they would not want to repeat the experience without improving the project management process. Many of them had missed family and other commitments while responding heroically to this challenge; they were stressed-out, burned-out, and feeling overwhelmed from the French Camp Noah project.

LSS announced that it was funding a six-month-long project to proactively create a Latino Camp Noah that can be deployed in any Spanish-speaking country. To avoid tight deadlines and scrambling, the Latino product will not be available until the end of the project, whether or not a flood occurs in a Spanish speaking area. The project called "Campamento de Noé" was chartered, and by the end of the first month, detailed planning was completed. Two months ago, the team started executing the project plan and they expect to complete the project on time by completing the remaining tasks to be executed within two months.

In general, the great planning paid off. Many things are working smoothly and the work is getting done. There are, however, a few problems that Amina, the project manager, would like your help within the Execution, Monitoring and Control, and Closure stages of the project. Changes to the project scope, cost and schedule on the "Campamento de Noé" project have become troublesome and Amina is worried about the potential for scope creep. Amina is uneasy about the level of team performance and team communications - at some level, everyone just isn’t working together smoothly.   

Questions:

Q1: There is no clearly defined process at LSS to deal with changes to the project baselines, and Amina is determined to prevent scope creep. When someone approaches her about an idea for a change, Amina listens carefully to the person. Then, Amina tells the person that, although it sounds like a great idea, it is not consistent with the project plan. Recently, Jenna, one of the functional leads, told Amina she wanted to purchase a new graphics software package. Amina told Jenna that she agreed that a new graphics software would be beneficial to the "Campamento de Noé" project; but, unfortunately, it was not in the project plan. Jenna purchased the graphics software and had it charged to the project. Jenna says this is an approved change because she talked to Amina about it but Amina says it is a variance. Who is correct? What caused this problem and how should Amina change the project management processes to prevent future problems?

Q2: About one-third of the team members on the "Campamento de Noé" project had participated in the French Camp Noah project. However, two-thirds of the team members are new to the project. Amina recently left a team meeting feeling surprised at the level of disagreement between team members: it feels like storming, not performing. For example, during a meeting, Ben, who manages ongoing Camp Noah operations, was surprised to hear that he needed to integrate the new Latino products into his operation – he thought the "Campamento de Noé" team would continue to support the product indefinitely. After that uncomfortable and unproductive meeting, Amina’s manager suggested that she come up with better approaches to dealing with conflict.   a) How do you recommend that Amina deal with conflict as it arises during meetings?   b) Describe the steps to implement an ongoing issue log and the rationale Amina could use to help her team understand the purpose and value of an issue log.

Q3: Formal project reporting is new to this organization, and unfortunately Amina made the early mistake of requiring lengthy, detailed status reports. No one on the project team turns them inconsistently, and no one in management reads her reports. What should Amina do? She is considering a) giving up on status reporting,   or b) enforcing the detailed reporting or c) creating a new shorter, more focused status report template. Support your recommendation and describe the key elements of the report that you suggest she uses.

Q4: Quality planning went well, and the team also did a good job performing quality assurance. Recommend at least three (3) quality control techniques, or procedures that Amina could incorporate into this project to help it be successful. Explain how each one might be applied to a specific problem or metric.

Q5: As the project nears closure, Amina is considering her options for learning from the project. Recommend an approach for learning from the project and describe both what she should do and why she should do it.

Q6: Procurement is one area in which Amina has very little experience. She needs to Close Procurements for the contract for discounted airline flights that they had negotiated with a travel agency. Using the process flow diagram in the PMBOK Guide for Close Procurements, (PMI, 2013) explains how the close procurements process applies to the airline flight contract, and why each step is important to successful project closure.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Mary Kate is a project manager in the IT department for a university. She has been...
Mary Kate is a project manager in the IT department for a university. She has been asked to manage a project to create a faculty intranet. The university has multiple campuses in various locations, and professors and other faculty need to be able to easily post questions, schedules and other documents to share in a secure environment. Mary Kate performed the following steps to begin the intranet project. She performed a needs analysis. Mary Kate interviewed the university faculty to...
Mary Kate is a project manager in the IT department for a university. She has been...
Mary Kate is a project manager in the IT department for a university. She has been asked to manage a project to create a faculty intranet. The university has multiple campuses in various locations, and professors and other faculty need to be able to easily post questions, schedules and other documents to share in a secure environment. Mary Kate performed the following steps to begin the intranet project. She performed a needs analysis. Mary Kate interviewed the university faculty to...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
Case Study 1: A Day in the Life Rachel, the project manager of a large information...
Case Study 1: A Day in the Life Rachel, the project manager of a large information systems project, arrives at her office early to get caught up with work before her co- workers and project team arrive. However, as she enters the office she meets Neil, one of her fellow project managers, who also wants to get an early start on the day. Neil has just completed a project overseas. They spend 10 minutes socializing and catching up on personal...
Case Study 1:  A Day in the Life Rachel, the project manager of a large information systems...
Case Study 1:  A Day in the Life Rachel, the project manager of a large information systems project, arrives at her office early to get caught up with work before her co- workers and project team arrive. However, as she enters the office she meets Neil, one of her fellow project managers, who also wants to get an early start on the day. Neil has just completed a project overseas. They spend 10 minutes socializing and catching up on personal news....
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
(Use the case of “Global Treps”) You have been selected as the project manager for the...
(Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
CASE 3.2 Horizon Consulting Patti Smith looked up at the bright blue Carolina sky before she...
CASE 3.2 Horizon Consulting Patti Smith looked up at the bright blue Carolina sky before she entered the offices of Horizon Consulting. Today was Friday, which meant she needed to prepare for the weekly status report meeting. Horizon Consulting is a custom software development company that offers fully integrated mobile application services for iPhonetm, Androidtm, Windows Mobile® and BlackBerry® platforms. Horizon was founded by James Thrasher, a former marketing executive, who quickly saw the potential for digital marketing via smartphones....
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT