Question

Project Integration Management Questions Only A team member notifies you, after the fact, that she has...

Project Integration Management Questions Only

  1. A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change?
  1. Make sure marketing is aware of the change.
  2. Implement change control processes to track the change.
  3. Inform the customer.
  4. Understand what functionality was added.
  1. You are having difficulty getting a project underway. You have not been able to get the charter approved. A major stakeholder is not sure a project is necessary, and a few others cannot agree on acceptable high-level requirements. All of the following are purposes of the project charter except:
  1. It identifies the product acceptance criteria.
  2. It identifies high-level risks and constraints.
  3. It gives the project manager authority.
  4. It establishes the project.

  1. A project manager has made a change to the project. The change is not significant enough that it would cause a change to the project baselines, but it will affect several members of the team. What should she do next?
  1. Assign resources.
  2. Evaluate impact.
  3. Request change control board involvement.
  4. Revise the project management plan and/or project documents.

  1. The project manager is working to clearly describe the level of involvement expected from everyone on the project in order to prevent rework, conflict, and coordination problems. Which of the following best describes the project manager's efforts?
  1. Develop Project Management Plan and Plan Quality Management
  2. Validate Scope and Control Quality
  3. Manage Stakeholder Engagement and Direct and Manage Project Work
  4. Identify Risks and Develop Project Team

  1. The scope baseline has just been set when the customer requests a change to the project scope. There have been no other change requests thus far, and the customer indicates that he thinks this will be the only change. The best thing for the project manager to evaluate is the:
  1. Effect of the change on the project schedule, cost, quality, risk, resources, and customer satisfaction
  1. Effect of the change on the project scope
  2. Effect of the change on the project baselines
  3. Effect of the change on scope management
  1. All of the following are not parts of a project management plan except:

  1. Risk register
  2. Milestone list
  3. Lessons learned
  4. Baselines

  1. The requirements documentation and contracts are:

  1. Project documents
  2. Quality and procurement documents
  3. Historical records
  4. Parts of the project management plan

  1. A work authorization system can be used to:
  1. Manage who does each activity
  2. Manage when each activity is done
  3. Manage who does each activity and when it is done
  1. Four projects have been proposed to management. Project A has a payback period of 16 months. Project B has a payback period of 12 months. Project C has a payback period of 8 months. Project D has a payback period of 6 months. Which project should management choose?
  1. Project A
  2. Project B
  3. Project C
  4. Project D

  1. You need to make a major change to the equipment used on your project. Your brother owns a company that produces a product that would meet the new needs of the project. What should you do?
  1. Let the customer know of the family relationship.
  2. Eliminate your brother from bidding.
  3. Negotiate a good deal on the product with your brother.
  4. Submit the bid and allow your brother to negotiate with the procurement office.

  1. A project team member tells you she went to her project manager with a good idea for a useful change to the project. Instead of giving her approval to make the change, the project manager asked her to write a report describing the benefits of the change. What is the most appropriate advice for the situation?
  1. The team member should do what was asked because this sort of information must be given to the project sponsor to make the change.
  2. Remind the project manager that the cost-benefit analysis for the project was done during project planning.
  3. The project manager is being unreasonable and should do that kind of work herself.
  4. A project manager must be able to weigh the benefits of the change versus the costs and compare them to other possible changes. The team member should do what was asked.

  1. At various points during project execution, the project manager reviews the project charter. Which of the following best describes what a project charter may be used for when the work is being completed?
  1. To make sure that all the documentation on the project is completed
  2. To help determine if a scope change should be approved
  3. To make sure all the team members are rewarded
  4. To assess the effectiveness of the change control system

  1. You have recently joined an organization that is just beginning to follow formal project management practices. In a meeting, your manager verbally describes your next assignment, a project to build an internal website that will be used by the human resources department. You respond by requesting a signed charter. Why is it unethical to do a project without a charter?

A. No one would be aware that the project is occurring.

B. It wastes company time, money, and resources.

C. It is not an issue of ethics, it is part of the process of project management.

D. Resources may become overloaded since the project is not official.

  1. There are always more project ideas submitted to an organization than can be selected and executed, based on limited resources organizations have available to put into projects. Which factor would not be considered when an organization is choosing between two projects to undertake?
  1. Payback period
  2. Benefit-cost ratio (BCR)
  3. Law of diminishing returns
  4. Net present value (NPV)
  1. During construction of a new manufacturing facility in another country, one of your team members complains to you that the wage paid to the workers is below the acceptable wage in your home country. In this situation, it is best to:
  1. Pay the workers at the new facility the same wage as your country.
  2. Pay the workers an appropriate wage for the country in which they work.
  3. Ignore the issue as you have not heard the workers complain.
  4. Pay the workers at the new facility a little less than the acceptable wage in your country.

  1. What does a benefit-cost ratio (BCR) of 2.1 mean?
  1. The profit is 2.1 times the costs.
  2. The payback is 2.1 times the costs.
  3. The costs are 2.1 times the benefits.
  4. The cost is 2.1 times the profit.

  1. After a great deal of effort, the project team has finally determined the specifications for a major scope change to the project. In light of this, what should the project manager do first?
  1. Gain sign-off on this change.
  2. Notify the stakeholders about the new scope.
  3. Look for other changes.
  4. Calculate the risks associated with this change.
  1. The CEO of the company has assigned a project manager to a project the CEO has wanted to do for a long time. What should the project manager do first?
  1. Assist the CEO in putting together a cost-benefit analysis to show the need for the project.
  2. Guide the creation of a project charter.
  3. Work with the CEO to get buy-in from the other stakeholders.
  4. Produce a ranking of all feasible projects, including the assigned project, in a weighted scoring of decision variables.

  1. The project for the accounting department has been going well when the company says it must reduce the cost of the project without changing the quality requirements. The project manager has looked to trim any resources, paid more attention to risk on upcoming activities, and even has reduced product scope, but the project remains over the new budget limit. Which of the following should the project manager do next?
  1. Cut 10 percent off the cost estimate of each remaining activity.
  2. Review expensive customer requirements that add the least benefit.
  3. Get an extension of time.
  4. Suggest the project be terminated.

  1. Your department is currently working on four urgent projects when it is assigned a major new project. To staff the new project, one of the four urgent projects needs to be terminated. The benefit-cost ratios (BCRs) for the four projects are listed. Which would you select for termination?
  1. 1.9
  2. 0.8
  3. 0.9
  4. 1.1
  1. There have been numerous changes on your project. All approved changes are best reflected in the:
  1. Change control procedures
  2. Validate Scope process
  3. Performance measurement variance
  4. Project management plan

  1. You have been assigned to create a project charter for a project to implement an internal website in your company. This project is expected to use a software platform new to your IT department. Stakeholders identified to date have expressed conflicting opinions about the website's basic functions. While confirming its high priority, management is hesitant to commit sufficient funds. You are meeting tomorrow with a seller who seems most qualified to design and implement the website. What should you do first?
  1. Put out a fixed-price invitation for bid to best control costs.
  2. Create a preliminary project schedule.
  3. Create a high-level work breakdown structure to help you estimate costs.
  4. Perform a high-level risk analysis of the project.

Homework Answers

Answer #1

1)Implement change control processes to track the change. since the change needs to be documented and approved.

2)It identifies the product acceptance criteria since this is an operational decision.

3)Option C. Request change control board involvement. since changes need to be authorised by change control board.

4)Option C Manage Stakeholder Engagement and Direct and Manage Project Work . Project manager is assigning and managing activities.

5)Option A Effect of the change on the project schedule, cost, quality, risk, resources, and customer satisfaction

6) Option D. Baselines . baseline is a the specified target in project management.

7)Option B Quality and procurement documents

8)Option C. Manage who does each activity and when it is done

9)Option D. Project D which has the least payback period.

10)Option D Submit the bid and allow your brother to negotiate with the procurement office since this is ethical action.

11)Option D A project manager must be able to weigh the benefits of the change versus the costs and compare them to other possible changes. The team member should do what was asked.

12Option )To help determine if a scope change should be approved

13)Option C. It is not an issue of ethics, it is part of the process of project management.

14)Option C, Law of diminishing returns

15)Option B Pay the workers an appropriate wage for the country in which they work

16)Option A The profit is 2.1 times the costs.

17)Option D Calculate the risks associated with this change.

18)option B Guide the creation of a project charter.

19)Option B Review expensive customer requirements that add the least benefit.

20)Option B 0.8

21)Option A Change control procedures

22)Option D Perform a high-level risk analysis of the project.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Question: Based on the WBS for a project with the requirement to lower a restaurant’s food...
Question: Based on the WBS for a project with the requirement to lower a restaurant’s food cost, preliminary work performance date indicate that the initial target has not ben achieved. The project manager is reviewing suggestions to identify suitable actions for closing the gap. Once the desired scope change has been selected, the project manager will update the project plan. Which scope describes the actions that the project manager should take? Answer Choices: The change in scope is funded in...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Nike's management team is considering two projects, a golf club project and a helmet project. A....
Nike's management team is considering two projects, a golf club project and a helmet project. A. Using the table below, calculate firm’s weighted average cost of capital: Nike: % of debt in capital structure 25% % of equity in capital structure 75% Before-tax required cost of debt 6% Tax rate 30% Cost of equity 11% B. Capital Budgeting Project information: Golf club project Helmet project Upfront costs (10,000,000) (8,000,000) Annual cash flows Year 1 $0 $3,000,000 Year 2 $0 $3,000,000...
You are the project manager of a complicated construction project, which involves building highways in the...
You are the project manager of a complicated construction project, which involves building highways in the whole state of North Carolina. You have several groups working with you in the project. To plan resources for this project and determine connection between individuals you should preferably use: Staffing pool description Staffing management plan Responsibility assignment matrix (RAM) Organization matrix You are the project manager of a project team that includes several new recruits. You notice that most of the team members...
The project manager receives yet another suggestion from their boss to add to the project's scope....
The project manager receives yet another suggestion from their boss to add to the project's scope. Earlier requests were easy to address. They cost little in time, effort or money so the project manager simply addressed it within the team by calling in favors and working a few extra hours. This latest request from the boss is substantial. It comes as a result of seeing the great results your team has produced so far. This new suggestion has potential for...
Question 1 A) Why are accurate cost estimates critical to effective project management? how would you...
Question 1 A) Why are accurate cost estimates critical to effective project management? how would you go about estimating cost for a typical project? B) What are the elements of a comprehensive reporting system to help in the ongoing management and control of a project? C) A number of projects are put forward from different departments in your organization. what would your approach be,as a senior manager,in determining priorities for selecting and prioritizing projects?
4a)  A fellow project manager has approached you for advice to manage risk in the procurement of...
4a)  A fellow project manager has approached you for advice to manage risk in the procurement of IT services without a well -defined specification. According to the fellow project manager, he and his team does not want to entertain any risk, hence his decision in choosing a Fixed Price Contract. Are there any inherent risks in the selected contract type? Critically evaluate the situation and bring out all the inherent risks you foresee. 4b) How can organizations use weighted scoring model...
1. The Project Management Institute (PMI) manages which international standard for the conduct of project management?...
1. The Project Management Institute (PMI) manages which international standard for the conduct of project management? All of the above PMBOK PRINCE2 Competence Baseline 2. A project can be define as having limited money and time all are correct delivering a product or service when finished involving a number of people and is unique 3. "Project Managers are trained and not born." This statement implies that you must constantly retrain project managers because of the rapidly change IT world having...