Question

As a project planner you have an activity that might take the following durations in days:...

As a project planner you have an activity that might take the following durations in days: (13 – 16 – 20). According to the management, the probability to complete the project with a duration of 13 days or 20 days is tremendously low. Use the most appropriate formula to estimate the duration of this activity and provide a description of the reason behind

your choice of formula.

Homework Answers

Answer #1

solution:

  • according to the data given the most appropriate technique is three point estimates.
  • In three-point estimates, we use three parameters:
  • Most Likely (Tm): This is the activity duration for most cases.

  • Optimistic (To): This is the activity duration in the most favorable case.

  • Pessimistic (Tp): This is the activity duration in the worst-case scenario.

  • t= activity duration.

​​​​​​REASON:

  • It uses three estimates to calculate the average value of an activity’s duration.
  • It reduces bias, risks, and uncertainties from the duration calculation.
  • It is more accurate than analogous and parametric estimation.

this is also my choice of formula to calculate activity duration.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A project is represented by the activity durations (in days, estimated at 90% likelihood of completion)...
A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many project buffers are needed if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length A -- 18 E C, D 13 B -- 16 F C 9 C A 22 G E, F 15 D B 14 ​ ​ ​ options: 0 1 2 3
Assume that activity F has the following times: Early start time (ES) = 7 days Early...
Assume that activity F has the following times: Early start time (ES) = 7 days Early finish time (EF) = 13 days Latest start time (LS) = 15 days Latest finish time (LF) = 21 days Which of the following statements is TRUE about activity F? Activity F takes 14 days to complete Activity F is on the critical path Activity F has 8 days of slack time Activity F is the first activity of the project None of the...
(Use the case of “Global Treps”) You have been selected as the project manager for the...
(Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
1) Which of the following is NOT a value-creating activity associated with the differentiation strategy? a....
1) Which of the following is NOT a value-creating activity associated with the differentiation strategy? a. intensive training programs to improve employee efficiency b. strong capability in new product development. c. rapid and timely deliveries to customers. d. procurement systems focused on finding the highest quality raw materials. 2) A certain marble quarry provides a unique type of marble that is richly colored and strikingly veined. It has been used for churches and public buildings throughout the world. The architect...
1) Which of the following is not a valid way that a CRM system can collect...
1) Which of the following is not a valid way that a CRM system can collect information? A. accounting system B. order fulfillment system C. inventory system D. customer’s personal computer 2)Which of the following is a common marketing CRM metric? A. number of new prospective customers B. average number of service calls per day C. average time to resolution D. cost per interaction by marketing campaign 3)Which question below represents a CRM reporting technology example? A. Why did sales...
As the newly appointed financial analyst for Coverdale Office Machines Ltd., you have been asked to...
As the newly appointed financial analyst for Coverdale Office Machines Ltd., you have been asked to evaluate two alternative capital investment opportunities. The company’s corporate income tax rate is 24%. First, you must re-calculate the company’s cost of capital. The company recently paid its annual dividend of $2.75 per common share. According to your calculations, the company’s beta is 0.80. The company’s common shares currently trade for $25.80 each on the TSX. The market return is estimated at 16% and...
DIRECTIONS: This is an open book, take home examination. You may look up the answers and...
DIRECTIONS: This is an open book, take home examination. You may look up the answers and discuss them, if you wish. The Multiple Choice questions will be worth 1 point each and the essay questions will be worth 25 points each. This examination is over Chapters 6 through 9. MULTIPLE CHOICE: 1. During Piaget's concrete operational stage, children a. are more egocentric than they were during the preoperational period. b. often confuse appearances with reality. c. are unable to reverse...
Jocko Johnson Age Gender Height Weight Body Fat % 30 Male 73 inches 200 18 Jocko...
Jocko Johnson Age Gender Height Weight Body Fat % 30 Male 73 inches 200 18 Jocko was an athlete in high school playing a variety of sports including football, track (100- 400 meter events) and baseball. He has come to you because he has recently had his 30 th birthday and wants to get back in shape. While he is in decent shape already, Jocko wishes to get in excellent shape with an eye on perhaps competing in a local...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT