As a project planner you have an activity that might take the following durations in days: (13 – 16 – 20). According to the management, the probability to complete the project with a duration of 13 days or 20 days is tremendously low. Use the most appropriate formula to estimate the duration of this activity and provide a description of the reason behind
your choice of formula.
solution:
Most Likely (Tm): This is the activity duration for most cases.
Optimistic (To): This is the activity duration in the most favorable case.
Pessimistic (Tp): This is the activity duration in the worst-case scenario.
t= activity duration.
REASON:
this is also my choice of formula to calculate activity duration.