Question

A project is represented by the activity durations (in days, estimated at 90% likelihood of completion)...

A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many project buffers are needed if this project is managed using critical chain methodology?

Activity Predecessor Length Activity Predecessor Length
A -- 18 E C, D 13
B -- 16 F C 9
C A 22 G E, F 15
D B 14

options:

0

1

2

3

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity Completion (Days) Immediate Precedence A. Architectural Design 3 - B. Clearing of Land 6 A...
Activity Completion (Days) Immediate Precedence A. Architectural Design 3 - B. Clearing of Land 6 A C. Fencing of project site 7 A D. Digging of foundation 5 A E. Completion of foundation work 13 B,C F. Raising of pillars and block work. 8 C,D G. Roofing 11 D,F H. Furnishing of the cathedral 6 G,E a. Redraw the network diagram for the construction of the National Cathedral by using the above information provided in the table to complete the...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D A, B 8 E A, B 6 F C, D, E 14 G C, D, E 3 H F, G 6 The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is? B, C, F, H B, C, F, G, H...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are given in the following table. Assume that the activity times are independent Activity Immediate Predecessor Time (Weeks) a m b A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 a) Calculate the expected time and variance for each activity. b) What is the expected completion time of the critical path? What is the...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of each. 3(b). The following data relates to the activities required for a project. Since exact duration for each activity is not known for certain, three time estimates were made, namely: - the optimistic, most likely and pessimistic time estimates. The precedence relationships are also shown in the data below. You will need to analyze this problem using what you learned in Chapter 18 of...
Individual CPM Assignment SCENARIO: Big Organization, inc. wants to automate their warehouse and put you in...
Individual CPM Assignment SCENARIO: Big Organization, inc. wants to automate their warehouse and put you in charge of the project. You already put together your team and had several productive meetings with them. Among accomplishments, you created a WBS which identified activities to be done. Starting with the WBS and with input from your team you then identified each activity’s predecessor activities. Later, in a subsequent meeting with your team you estimated activity completion times for each activity. The table...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
The project of an interior design upgrade at one of the Citibank branches consists of six...
The project of an interior design upgrade at one of the Citibank branches consists of six activities. The tasks, durations (in days), and predecessor relationships are as follow: Activity Immediate Predecessors Activity Time A - 3 B A 4 C A 5 D B, C 4 E C 3 F D, E 3 Calculate the slack times and identify the critical path(s).
Given below are the durations of and the precedence relationships among the activities required to compute...
Given below are the durations of and the precedence relationships among the activities required to compute a project. 1) construct an AOA network of the project 2)what is the critical path? determine the expected duration of the project. 3)compute the standard deviation of the critical path Duration(days) Activity pre-decessor(s) a m b A - 4 7 12 B A 6 9 13 C A 5 7 9 D B,C 3 5 8 E B 7 8 10 F A 2...
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ___ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT
Active Questions
  • A system is to be developed for an airport. When passengers have boarded an aircraft, a...
    asked 7 minutes ago
  • After reading Module 5 PowerPoint 1 - The Philosophy of Human Existance and Health Care Policy,...
    asked 15 minutes ago
  • 1. Do you feel play has a place in supporting literacy development in early childhood? Explain...
    asked 19 minutes ago
  • How should roles be selected for the Emergency Operations Center (EOC)?  Is seniority less important than experience?...
    asked 32 minutes ago
  • Discuss routing issues and solutions namely, count-to-infinity, split horizon, split horizon with poison reverse, and hold-down...
    asked 32 minutes ago
  • Find an optimal parenthesization of a matrix-chain product whose sequence of dimensions is〈5,10,3,12,5,50,6〉.
    asked 1 hour ago
  • Water at 60 F (density=62.4lbm/ft^3 and dynamic viscosity = 7.5x10^-4 lbm/ft-s) is to be pumped through...
    asked 1 hour ago
  • ibuprofen an aspirin substitute has the following percent composition C, 75.69%; H,8.80%; O,15.51%. determine the empirical...
    asked 1 hour ago
  • Describe in brief some of the aspects of understanding words in the study of language
    asked 1 hour ago
  • Anticipated sales for Safety Grip Company were 75,000 passenger car tires and 23,000 truck tires. Rubber...
    asked 1 hour ago
  • QUESTION ONE a) Differentiate between traceable and common costs b) Assume that you are living in...
    asked 1 hour ago
  • How do do you think that online course is different than the regular classroom setting experience
    asked 1 hour ago