A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many project buffers are needed if this project is managed using critical chain methodology?
Activity | Predecessor | Length | Activity | Predecessor | Length |
A | -- | 18 | E | C, D | 13 |
B | -- | 16 | F | C | 9 |
C | A | 22 | G | E, F | 15 |
D | B | 14 | | | |
options:
0
1
2
3