Question

Assume that activity F has the following times: Early start time (ES) = 7 days Early...

Assume that activity F has the following times:

Early start time (ES) = 7 days

Early finish time (EF) = 13 days

Latest start time (LS) = 15 days

Latest finish time (LF) = 21 days

Which of the following statements is TRUE about activity F?

  1. Activity F takes 14 days to complete
  2. Activity F is on the critical path
  3. Activity F has 8 days of slack time
  4. Activity F is the first activity of the project
  5. None of the above are true

Assume that activity J has the following times:

Early start time (ES) = 6 days

Early finish time (EF) = 11 days

Latest start time (LS) = 9 days

Latest finish time (LF) = 14 days

If disaster strikes and activity J will take 20 days to complete rather than the original activity duration (assume that it started at the ES time), by how long will the completion of the project be delayed?           a. 12 days

                b. 5 days

                c. 20 days

                d. 3 days

A person is making three specialty cakes. Due to differences in cooking temperatures, only one cake can use the oven at a time (each requires 45 minutes in the oven). Further, assume that mixing the ingredients before baking requires 15 minutes for each of the cakes (they use different ingredients and have to be done separately). Once removed from the oven, a cake has to sit for 15 minutes before icing is applied (which also requires 15 mins). Assuming that it is possible to mix and/or ice a cake while another is in the oven, how long will it be before the last cake finished (i.e., has icing on it)?

                A .3 hours

                b. 2 hours and 30 minutes

                c. 3 hours and 45 minutes

                d. 4 hours

Homework Answers

Answer #1

Question 1: c. Activity F has 8 days of slack time

Slack time = LS - ES = 15 - 7 = 8 days

Question 2: a. 12 days

Duration of Activity J before disaster = EF - ES = 5 days

Duration of Activity J after disaster = 20 days

Delay in Activity J = Duration of Activity J after disaster - Duration of Activity J before disaster = 20 - 5 = 15 days

Slack = LS - ES = 3 days

Delay in project duration = Delay in Activity J - Slack = 12 days

Question 3: a. 3 hours

Throughput time = Sum of all task times = Time for mixing + baking + siting after baking + icing = 15 + 45 + 15 + 15 = 90 minutes

First Cake will be out after 90 minutes

Cycle time = Max (All task times) = Time for baking = 45 minutes

Second cake will be out after 90+45 = 135 minutes

Third cake will be out after 135+45 = 180 minutes

Total time to prepare 3 cakes = 180 minutes = 3 hours

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A -...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Determine the following for each activity: Expected Duration (round to the nearest whole number) Early Start...
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ___ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ____ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)      &nbsp
Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)          to           tml                tp                                 te     A                     -----                        1                      2                      3                           B                      A                           2                      4                      6     C                      B                            1                      4                      7     D                      B                            3                      4                      5     E                      C                            1                      3                      5     F                      D, E                       2                      3                      4 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.] 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time and the standard deviation (σ) for the project— round off the standard deviation to the nearest...
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J