Question

Use the following data to select one best answer to the following question: What is the...

Use the following data to select one best answer to the following question:

What is the gross profit for the low-rise office building project by applying Completed Contract method without absorption?

A construction company began operations on January 2, 2010. During the year the company was awarded one construction contract of low-rise office building. The company incurred $100,000 operating expenses for the year for which $75,000 has been paid while the balance is owed as of December 31, 2010. Project data is summarized for the project in the following paragraphs.

The initial contract for the low-rise office building was signed on January 5, 2010 in the amount of $1,000,000. This amount included $800,000 for construction costs, $150,000 for overhead mark-up, and $50,000 for profit markup. The contractor broke ground on February 4, 2010. During the course of construction the client decided to upgrade the quality of the lighting and plumbing fixtures, resulting in a change order issued to the contractor in the amount of $100,000 on October 7, 2010. The change order price was calculated by the contractor as follows: $50,000 construction costs, $37,500 overhead markup, $12,500 profit markup.

At the end of 2010, construction was not complete. However, the client was renting out office space to other entities as well as using some of the offices for the client’s own business entity. Work remaining as of December 31, 2010 included surfacing the parking lot, erecting a portable parking attendant’s station, miscellaneous site concrete work and landscaping. This work was schedule to be completed by May 1, 2010, weather permitting.

A summary of accounting data as of December 31, 2010 included total construction costs in the amount of $800,000 for which $600,000 was paid. The balance reflected unpaid bills for the month of December, and retention withheld on subcontracts throughout the course of the project. The total progress billing as of December 31, 2010 was $1,000,000 of which $900,000 was collected with the balance outstanding as retention receivable. The project manager estimated that given the work left to be completed, approximately $200,000 of construction cost would be incurred.

Question 10 options:

A)

400,000

B)

100,000

C)

200,000

D)

300,000

Homework Answers

Answer #1

As we need to calculate the gross profit applying cash method for recognizing revenue, we will take into account  only the amount of money thar has actually been collected /paid by the contractor upto the end of the year.the value of gross profit can be calculateed as below:

Gross profit (cash basis)=cash collected as at the end of the year-construction costs paid as the end of the year

using the value provided in the question,we get.

gross profit(cash basis)=900,000-600,000=$300,000

NOTE

AS we need to determine the value of gross profit,opertaing expenses paid by the contractor during the year will not be considered

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Use the following data to select one best answer to the following question: Which method shall...
Use the following data to select one best answer to the following question: Which method shall be used to determine percent complete for the low-rise office building project? A construction company began operations on January 2, 2010. During the year the company was awarded one construction contract of low-rise office building. The company incurred $100,000 operating expenses for the year for which $75,000 has been paid while the balance is owed as of December 31, 2010. Project data is summarized...
Harrisburg Furniture Company started construction of a combination office and warehouse building for its own use...
Harrisburg Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,000,000 on January 1, 2017. Harrisburg expected to complete the building by December 31, 2017. Harrisburg has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2016 $2,000,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,400,000 Long-term loan-11% interest, payable on January 1 of...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2017. Expenditures on the project were as follows:   January 1, 2016 $ 1,000,000   March 1, 2016 800,000   June 30, 2016 1,500,000   October 1, 2016 1,000,000   January 31, 2017 300,000   April 30, 2017 600,000   August 31, 2017 900,000 On January 1, 2016, the company obtained a $8.000,000 construction loan with a 12% interest rate....
Multiple Choice: Please select the correct answer 1. Progress payments are generally issued A - whenever...
Multiple Choice: Please select the correct answer 1. Progress payments are generally issued A - whenever the contractor submits the bill B - whenever the subcontractor submits the bill C - every 45 days D - every 30 days 2. In order to pay the progress payment, who must certify the amount? A - the contractor B - purchasing agent C - design professional D - the owner 3. Retainage is generally withheld from each process payment. The process of...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Heston Preskell, Inc., a commercial contractor, signed a contract during Year 1 for $808,000 to build...
Heston Preskell, Inc., a commercial contractor, signed a contract during Year 1 for $808,000 to build an office building for the YMCA. Heston Preskell completed 30% of the work during Year 1 and the remaining 70% during Year 2. The cost of acquired production materials during Year 1 by Heston Preskell was $195,000 and an additional $330,000 during Year 2. Heston Preskell billed the YMCA $225,000 in Year 1 and the final $580,000 in Year 2. The YMCA paid $210,000...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Stellar Furniture Company started construction of a combination office and warehouse building for its own use...
Stellar Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $2,500,000 on January 1, 2020. Stellar expected to complete the building by December 31, 2020. Stellar has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $1,000,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 700,000 Long-term loan-11% interest, payable on January 1 of...
Prepare journal entries for the following select transactions for Be-Fit Corporation. In addition to completing the...
Prepare journal entries for the following select transactions for Be-Fit Corporation. In addition to completing the journal entries, include a separate sheet showing all work clearly labeled by date and description for partial credit. 01/01/2017-12/31/2017: BeFit borrowed $7 million at 10% on 1/1/17 to build the new recreation center, with principal and interest to be paid at maturity in 2 years. The building is expected to take 18 months to complete. The following are the cash expenditures for the construction...
The board of directors of Ogle Construction Company is meeting to choose between the completed contract...
The board of directors of Ogle Construction Company is meeting to choose between the completed contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Ogle's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Ogle commenced doing business on January 1, 2018. 2. Construction activities for the year ended December 31, 2018, were...