On January 1, 2018, the Mason Manufacturing Company began
construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began
construction of a building to be used as its office headquarters.
The building was completed on September 30, 2019. Expenditures on
the project were as follows:
January 1, 2018 $ 1,820,000
March 1, 2018 1,440,000
June 30, 2018 1,640,000
October 1, 2018 1,440,000
January 31, 2019 396,000
April 30, 2019 729,000
August 31, 2019 1,026,000
On January 1, 2018, the company obtained a $4,400,000
construction loan with a 14% interest rate....
On January 1, 2018, the Highlands Company began construction on
a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on
a new manufacturing facility for its own use. The building was
completed in 2019. The company borrowed $2,050,000 at 11% on
January 1 to help finance the construction. In addition to the
construction loan, Highlands had the following debt outstanding
throughout 2018:
$6,000,000, 16% bonds
$4,000,000, 11% long-term
note
Construction expenditures incurred during 2018 were as
follows:
January 1
$
840,000
March 31
1,440,000
June 30
1,088,000
September 30
840,000...
On January 1, 2018, the Shagri Company began construction on a
new manufacturing facility for its...
On January 1, 2018, the Shagri Company began construction on a
new manufacturing facility for its own use. The building was
completed in 2019. The only interest-bearing debt the company had
outstanding during 2018 was long-term bonds with a book value of
$11,500,000 and an effective interest rate of 10%. Construction
expenditures incurred during 2018 were as follows:
January 1
$
650,000
March 1
690,000
July 31
570,000
September
30
750,000
December 31
450,000
Date
Expenditure
Weight
Average
January 1...
On January 1, 2018, the Mills Conveying Equipment
Company began construction of a building to be...
On January 1, 2018, the Mills Conveying Equipment
Company began construction of a building to be used as its office
headquarters. The building was completed on June 30, 2019.
Expenditures on the project, mainly payments to subcontractors,
were as follows:
January 1, 2018 $500,000
March 31, 2018 $400,000
September 30, 2018 $600,000
Accumulated expenditures at December 31, 2018
$1,500,000
(before interest capitalization)
January 31, 2019 $600,000
April 30, 2019 $300,000
On January 1, 2018, the company obtained a $1,000,000
construction...
XYZ Corp began construction on a building on January 1, 2016. On
that date, it made...
XYZ Corp began construction on a building on January 1, 2016. On
that date, it made its first $500,000 payment. An additional
$600,000 were paid on 4/1/2016 and $300,000 was paid on 7/1/2016. A
final payment of $100,000 was made on 12/31/2016, which is also the
date when the construction project was finished and the building
was ready to use.
To finance the project, XYZ Corp issued a $800,000 10% note.
Furthermore, XYZ Corp had a $2,000,000 5% note outstanding...
On January 1, 2018, ABC Company began construction of a building
to be used as its...
On January 1, 2018, ABC Company began construction of a building
to be used as its warehouse. The building was completed on November
1, 2019. Expenditures for the project during 2018 were as
follows:
January 1, 2018
900,000
April 1, 2018
700,000
July 1, 2018
650,000
October 1, 2018
840,000
On January 1, 2018, ABC Company obtained a $4,000,000
construction loan with 9% interest rate payable in 5 years. The
Company’s other debts included a note of $1,000,000 at 11%...
On January 1, 2018, the Marjlee Company began construction of an
office building to be used...
On January 1, 2018, the Marjlee Company began construction of an
office building to be used as its corporate headquarters. The
building was completed early in 2019. Construction expenditures for
2018, which were incurred evenly throughout the year, totaled
$6,000,000. Marjlee had the following debt obligations which were
outstanding during all of 2018:
Construction loan, 14%
$
1,500,000
Long-term note, 13%
2,000,000
Long-term note, 10%
4,000,000
Required:
Calculate the amount of interest capitalized in 2018 for the
building using the...
Thornton Industries began construction of a warehouse on July 1,
2018. The project was completed on...
Thornton Industries began construction of a warehouse on July 1,
2018. The project was completed on March 31, 2019. No new loans
were required to fund construction. Thornton does have the
following two interest-bearing liabilities that were outstanding
throughout the construction period:
$6,000,000, 8% note
$9,000,000, 3% bonds
Construction expenditures incurred were as follows:
July 1, 2018
$
580,000
September 30, 2018
870,000
November 30, 2018
870,000
January 30, 2019
810,000
The company’s fiscal year-end is December 31.
Required:
Calculate...
Matrix Inc. borrowed $1,000,000 at 8% to finance the
construction of a new building for its...
Matrix Inc. borrowed $1,000,000 at 8% to finance the
construction of a new building for its own use. Construction began
on January 1, 2016, and was completed on October 31, 2016.
Expenditures related to this building were: January 1 $258,000
(includes cost of purchasing land of $150,000) May 1 310,000 July 1
420,000 October 31 275,000 In addition, Matrix had additional debt
(unrelated to the construction) of $500,000 at 9% and $800,000 at
10%. All debt was outstanding for the...
Harrisburg Furniture Company started construction of a
combination office and warehouse building for its own use...
Harrisburg Furniture Company started construction of a
combination office and warehouse building for its own use at an
estimated cost of $5,000,000 on January 1, 2017. Harrisburg
expected to complete the building by December 31, 2017. Harrisburg
has the following debt obligations outstanding during the
construction period.
Construction loan-12% interest, payable semiannually, issued
December 31, 2016 $2,000,000
Short-term loan-10% interest, payable monthly, and principal
payable at maturity on May 30, 2018 1,400,000
Long-term loan-11% interest, payable on January 1 of...