Question

Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...

Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture of the down payment. Occasionally, homes remain unsold for as long as three months after construction. In these situations, sales price reductions are used to promote the sale.

During 2018, Citation began construction of an office building for Altamont Corporation. The total contract price is $25 million. Costs incurred, estimated costs to complete at year-end, billings, and cash collections for the life of the contract are as follows:

2018 2019 2020
Costs incurred during the year $ 5,000,000 $ 11,875,000 $ 5,625,000
Estimated costs to complete as of year-end 15,000,000 5,625,000
Billings during the year 2,500,000 12,500,000 10,000,000
Cash collections during the year 2,250,000 11,150,000 11,600,000


Also during 2018, Citation began a development consisting of 12 identical homes. Citation estimated that each home will sell for $900,000, but individual sales prices are negotiated with buyers. Deposits were received for eight of the homes, three of which were completed during 2018 and paid for in full for $900,000 each by the buyers. The completed homes cost $675,000 each to construct. The construction costs incurred during 2018 for the nine uncompleted homes totaled $4,050,000.

Required:

1. Which method is most equivalent to recognizing revenue at the point of delivery?
2. Answer the following questions assuming that Citation uses the completed contract method for its office building contracts:
2-a. How much revenue related to this contract will Citation report in its 2018 and 2019 income statements?
2-b. What is the amount of gross profit or loss to be recognized for the Altamont contract during 2018 and 2019?
2-c. What will Citation report in its December 31, 2018, balance sheet related to this contract? (Ignore cash.)
3. Answer the following questions assuming that Citation uses the percentage-of-completion method for its office building contracts.
3-a. How much revenue related to this contract will Citation report in its 2018 and 2019 income statements?
3-b. What is the amount of gross profit or loss to be recognized for the Altamont contract during 2018 and 2019?
3-c. What will Citation report in its December 31, 2018, balance sheet related to this contract? (Ignore cash.)
4. Assume the same information for 2018 and 2019, but that as of year-end 2019 the estimated cost to complete the office building is $11,250,000. Citation uses the percentage-of-completion method for its office building contracts.
4-a. How much revenue related to this contract will Citation report in the 2019 income statement?
4-b. What is the amount of gross profit or loss to be recognized for the Altamont contract during 2019?
4-c. What will Citation report in its 2019 balance sheet related to this contract? (Ignore cash.)
5. Which method of accounting should Citation Builders, Inc adopt for its single-family houses?
6. What will Citation report in its 2018 income statement and 2018 balance sheet related to the single-family home business (ignore cash in the balance sheet)?

Which method is most equivalent to recognizing revenue at the point of delivery? Answer the following questions assuming that Citation uses the completed contract method for its office building contracts: How much revenue related to this contract will Citation report in its 2018 and 2019 income statements? What is the amount of gross profit or loss to be recognized for the Altamont contract during 2018 and 2019? (Leave no cells blank - be certain to enter "0" wherever required. Loss amounts should be indicated with a minus sign.)

Show less

1. Recognizing revenue at the point of delivery?
2018 2019
2a. Revenue recognized
2b. Gross profit or loss to be recognized

What will Citation report in its December 31, 2018, balance sheet related to this contract? (Ignore cash.)

Balance Sheet (Partial)
At December 31, 2018
Current assets:
Current liabilities:

Answer the following questions assuming that Citation uses the percentage-of-completion method for its office building contracts. How much revenue related to this contract will Citation report in its 2018 and 2019 income statements? What is the amount of gross profit or loss to be recognized for the Altamont contract during 2018 and 2019? (Loss amounts should be indicated with a minus sign.)

Show less

2018 2019
Revenue reported
Gross profit or loss to be recognized

What will Citation report in its December 31, 2018, balance sheet related to this contract? (Ignore cash.)

Balance Sheet (Partial)
At December 31, 2018
Current assets:
Current liabilities:

Assume the same information for 2018 and 2019, but that as of year-end 2019 the estimated cost to complete the office building is $11,250,000. Citation uses the percentage-of-completion method for its office building contracts. How much revenue related to this contract will Citation report in the 2019 income statement? What is the amount of gross profit or loss to be recognized for the Altamont contract during 2019? (Loss amounts should be indicated with a minus sign.)

Show less

2019
Revenue reported
Gross profit or loss to be recognized

What will Citation report in its 2019 balance sheet related to this contract? (Ignore cash.)

Balance Sheet (Partial)
At December 31, 2019
Current assets:
Current liabilities:

Which method of accounting should Citation Builders, Inc adopt for its single-family houses?

Citation Builders, Inc adopt for its single-family houses?

What will Citation report in its 2018 income statement related to the single-family home business (ignore cash in the balance sheet)?

Income Statement (Partial)
2018

What will Citation report in its 2018 balance sheet related to the single-family home business (ignore cash in the balance sheet)?

Balance Sheet (Partial)
At December 31, 2018
Current assets:
Current liabilities:

Homework Answers

Answer #1

1. For recognizing the revenue at the point of delivery, completed contract method is best method nof accounting. This is due to the fact that under completed contract method, the revenue is recognized only when the construction is completed and sold to the customer.

2a. In relation to office building contract Citation will not book it's revenue unless and until the project is fully completed and sold. Therefore, no revenue will be booked by Citation.

2b. Since no revenue is booked in the year 2018 & 2019, related expenses will be also be not recorded and will be deferred by Citation. Therefore, no gross profit or loss will be recorded.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
On May 1, 2017, Collin Company contracted to construct a factory building for a total contract...
On May 1, 2017, Collin Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below. 2017 2018 2019 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0- Billings 1,200,000 4,100,000 4,300,000 Instructions(a) Using...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows:...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows: 2018     2019 Costs incurred to date €9,000,000 €14,000,000 Estimated costs to complete 6,000,000 — Billings to date 7,000,000 21,000,000 Collections to date 5,000,000 18,000,000 8. If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2018 is A. €3,600,000. B. €4,000,000. C. €5,400,000. D. €6,000,000. 9. If Kiner uses the cost-recovery method, the gross profit to be recognized in 2019 is...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office building for $60,000,000. The scheduled construction costs follow. Year Cost 2016 $12,000,000 2017 18,000,000 2018 10,000,000 Total $40,000,000 The building is completed in 2018. For each year, compute the revenue, expense, and gross profit reported for this construction project using each of the following methods. a. Percentage-of-completion method 2016 2017 2018 Revenue $Answer $Answer $Answer Expense $Answer $Answer $Answer Gross Profit $Answer $Answer $Answer...