Question

Use the following data to select one best answer to the following question: Which method shall...

Use the following data to select one best answer to the following question: Which method shall be used to determine percent complete for the low-rise office building project?

A construction company began operations on January 2, 2010. During the year the company was awarded one construction contract of low-rise office building. The company incurred $100,000 operating expenses for the year for which $75,000 has been paid while the balance is owed as of December 31, 2010. Project data is summarized for the project in the following paragraphs.

The initial contract for the low-rise office building was signed on January 5, 2010 in the amount of $1,000,000. This amount included $800,000 for construction costs, $150,000 for overhead mark-up, and $50,000 for profit markup. The contractor broke ground on February 4, 2010. During the course of construction the client decided to upgrade the quality of the lighting and plumbing fixtures, resulting in a change order issued to the contractor in the amount of $100,000 on October 7, 2010. The change order price was calculated by the contractor as follows: $50,000 construction costs, $37,500 overhead markup, $12,500 profit markup.

At the end of 2010, construction was not complete. However, the client was renting out office space to other entities as well as using some of the offices for the client’s own business entity. Work remaining as of December 31, 2010 included surfacing the parking lot, erecting a portable parking attendant’s station, miscellaneous site concrete work and landscaping. This work was schedule to be completed by May 1, 2010, weather permitting.

A summary of accounting data as of December 31, 2010 included total construction costs in the amount of $800,000 for which $600,000 was paid. The balance reflected unpaid bills for the month of December, and retention withheld on subcontracts throughout the course of the project. The total progress billing as of December 31, 2010 was $1,000,000 of which $900,000 was collected with the balance outstanding as retention receivable. The project manager estimated that given the work left to be completed, approximately $200,000 of construction cost would be incurred.

Question 6 options:

A)

Work Quantity

B)

Cost to Cost

C)

Labor Hours

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Use the following data to select one best answer to the following question: What is the...
Use the following data to select one best answer to the following question: What is the gross profit for the low-rise office building project by applying Completed Contract method without absorption? A construction company began operations on January 2, 2010. During the year the company was awarded one construction contract of low-rise office building. The company incurred $100,000 operating expenses for the year for which $75,000 has been paid while the balance is owed as of December 31, 2010. Project...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2017. Expenditures on the project were as follows:   January 1, 2016 $ 1,000,000   March 1, 2016 800,000   June 30, 2016 1,500,000   October 1, 2016 1,000,000   January 31, 2017 300,000   April 30, 2017 600,000   August 31, 2017 900,000 On January 1, 2016, the company obtained a $8.000,000 construction loan with a 12% interest rate....
The plant asset and accumulated depreciation accounts of Pell Corporation had the following balances at December...
The plant asset and accumulated depreciation accounts of Pell Corporation had the following balances at December 31, 2017: Plant Asset Accumulated Depreciation Land $ 400,000 $ — Land improvements 205,000 50,000 Building 1,750,000 355,000 Machinery and equipment 1,168,000 410,000 Automobiles 175,000 117,000 Transactions during 2018 were as follows: On January 2, 2018, machinery and equipment were purchased at a total invoice cost of $285,000, which included a $6,000 charge for freight. Installation costs of $32,000 were incurred. On March 31,...
P3-33A Journalizing adjusting entries and subsequent journal entries Laughter Landscaping has collected the following data for...
P3-33A Journalizing adjusting entries and subsequent journal entries Laughter Landscaping has collected the following data for the December 31 adjusting entries: A. Each Friday, Laughter pays employees for the current week’s work. The amount of the weekly payroll is $8,000 for a five-day workweek. This year, December 31 falls on a Tuesday. Laughter will pay its employees on January 3. B. On January 1 of the current year, Laughter purchases an insurance policy that covers two years, $8,000. c. The...
Exercise 8-07 On December 31, 2021, when its Allowance for Doubtful Accounts had a debit balance...
Exercise 8-07 On December 31, 2021, when its Allowance for Doubtful Accounts had a debit balance of $1,469, Ivanhoe Company estimates that 11% of its accounts receivable balance of $77,700 will become uncollectible and records the necessary adjustment to Allowance for Doubtful Accounts. On May 11, 2022, Ivanhoe Company determined that B. Jared’s account was uncollectible and wrote off $1,139. On June 12, 2022, Jared paid the amount previously written off. Prepare the journal entries on December 31, 2021, May...
Portfolio Project Option #1 is for accounting students who are sensing learners, and learn best from...
Portfolio Project Option #1 is for accounting students who are sensing learners, and learn best from concrete materials and examples. If this is your learning style preference, you are practical and careful with detail. For this assignment, you are required to complete all three accounting cases: Arizona Consultants Inc., Power and Demolition Company, and Warnerwood. You will then present Parts 1, 2, and 3 of the Portfolio Project in Excel as journal entries, following the exact instructions that accompany each...
Can someone please provide the solutions. No explanation needed, just the answers so I can double...
Can someone please provide the solutions. No explanation needed, just the answers so I can double check my work.      2.   Firms with tangible long-term assets and less predictable cash flows, such as auto manufacturers and steel companies, whose sales vary with changes in economic conditions, tend to use a. a more nearly equal mix of long-term debt and shareholders’ equity financing. b. a greater amount of long-term debt [80%] than shareholders’ equity financing [20%]. c. a smaller amount of...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
You are a Junior Accountant for X-RAY Inc., and you receive from the CFO the following...
You are a Junior Accountant for X-RAY Inc., and you receive from the CFO the following information which affects the Financial Statements of the company. X-RAY Incorporate Unadjusted Trial Balance 31.12.2016 Debit Credit Cash 43.820 Accounts receivable 22.000 Supplies 1.230 Prepaid Expenses 5.200 Prepaid Interests 18.750 Vehicles 10.000 Computers 3.000 Furniture 8.000 Building 55.000 Accumulated Depreciation 7.000 ST Debt (Loan) 25.000 LT Debt (Loan) 100.000 Accounts payable 2.000 Unearned Revenue 10.000 Common stock 5.000 Retained earnings 18.000 Loss/Profit Total 167.000...
Question 2 Smith Ltd manufactures and sells one product. You are presented with the following information...
Question 2 Smith Ltd manufactures and sells one product. You are presented with the following information for the preparation of the annual operating budget for the period ending 31 December 2021: Estimated sales in units are 50,000 units for Quarter 1, 53,000 units for Quarter 2, 62,000 units for Quarter 3, and 65,000 units for Quarter 4. The estimated per unit selling price is $9 for Quarters 1-3, and $10 for Quarter 4. Smith Ltd has set the desired ending...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT