Question

Use the following data to select one best answer to the following question: Which method shall...

Use the following data to select one best answer to the following question: Which method shall be used to determine percent complete for the low-rise office building project?

A construction company began operations on January 2, 2010. During the year the company was awarded one construction contract of low-rise office building. The company incurred $100,000 operating expenses for the year for which $75,000 has been paid while the balance is owed as of December 31, 2010. Project data is summarized for the project in the following paragraphs.

The initial contract for the low-rise office building was signed on January 5, 2010 in the amount of $1,000,000. This amount included $800,000 for construction costs, $150,000 for overhead mark-up, and $50,000 for profit markup. The contractor broke ground on February 4, 2010. During the course of construction the client decided to upgrade the quality of the lighting and plumbing fixtures, resulting in a change order issued to the contractor in the amount of $100,000 on October 7, 2010. The change order price was calculated by the contractor as follows: $50,000 construction costs, $37,500 overhead markup, $12,500 profit markup.

At the end of 2010, construction was not complete. However, the client was renting out office space to other entities as well as using some of the offices for the client’s own business entity. Work remaining as of December 31, 2010 included surfacing the parking lot, erecting a portable parking attendant’s station, miscellaneous site concrete work and landscaping. This work was schedule to be completed by May 1, 2010, weather permitting.

A summary of accounting data as of December 31, 2010 included total construction costs in the amount of $800,000 for which $600,000 was paid. The balance reflected unpaid bills for the month of December, and retention withheld on subcontracts throughout the course of the project. The total progress billing as of December 31, 2010 was $1,000,000 of which $900,000 was collected with the balance outstanding as retention receivable. The project manager estimated that given the work left to be completed, approximately $200,000 of construction cost would be incurred.

Question 6 options:

A)

Work Quantity

B)

Cost to Cost

C)

Labor Hours

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Use the following data to select one best answer to the following question: What is the...
Use the following data to select one best answer to the following question: What is the gross profit for the low-rise office building project by applying Completed Contract method without absorption? A construction company began operations on January 2, 2010. During the year the company was awarded one construction contract of low-rise office building. The company incurred $100,000 operating expenses for the year for which $75,000 has been paid while the balance is owed as of December 31, 2010. Project...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2017. Expenditures on the project were as follows:   January 1, 2016 $ 1,000,000   March 1, 2016 800,000   June 30, 2016 1,500,000   October 1, 2016 1,000,000   January 31, 2017 300,000   April 30, 2017 600,000   August 31, 2017 900,000 On January 1, 2016, the company obtained a $8.000,000 construction loan with a 12% interest rate....
Green Earth Corp. is a construction company that uses the percentage of completion method. They won...
Green Earth Corp. is a construction company that uses the percentage of completion method. They won a contract to build an apartment building in 2019 for $60,000,000. Please record the journal entries relating to each of the events below. Also assume that the company has a December 31 year-end and records adjusting entries only at year-end. a) Actual costs incurred to the end of 2019 were $36,000,000 and all was paid with cash. b) Billings made to the client amounted...
Chance Company had two operating divisions, one manufacturing farm equipment and the other office supplies. Both...
Chance Company had two operating divisions, one manufacturing farm equipment and the other office supplies. Both divisions are considered separate components as defined by generally accepted accounting principles. The farm equipment component had been unprofitable, and on September 1, 2018, the company adopted a plan to sell the assets of the division. The actual sale was completed on December 15, 2018, at a price of $640,000. The book value of the division’s assets was $1,090,000, resulting in a before-tax loss...
Problem 10-1 At December 31, 2016, certain accounts included in the property, plant, and equipment section...
Problem 10-1 At December 31, 2016, certain accounts included in the property, plant, and equipment section of Monty Company’s balance sheet had the following balances. Land $239,000 Buildings 901,400 Leasehold improvements 660,000 Equipment 882,000 During 2017, the following transactions occurred. 1. Land site number 621 was acquired for $859,100. In addition, to acquire the land Monty paid a $51,100 commission to a real estate agent. Costs of $44,400 were incurred to clear the land. During the course of clearing the...
The following payments and receipts are related to land, land improvements, and buildings acquired for use...
The following payments and receipts are related to land, land improvements, and buildings acquired for use in a wholesale ceramic business. The receipts are identified by an asterisk next to the item letter. a. Fee paid to attorney for title search $ 2,395 b. Cost of real estate acquired as a plant site: Land 283,200 Cost of real estate acquired as a plant site: Building 57,400 c. Delinquent real estate taxes on property, assumed by purchaser 15,175 d. Cost of...
The plant asset and accumulated depreciation accounts of Pell Corporation had the following balances at December...
The plant asset and accumulated depreciation accounts of Pell Corporation had the following balances at December 31, 2017: Plant Asset Accumulated Depreciation Land $ 400,000 $ — Land improvements 205,000 50,000 Building 1,750,000 355,000 Machinery and equipment 1,168,000 410,000 Automobiles 175,000 117,000 Transactions during 2018 were as follows: On January 2, 2018, machinery and equipment were purchased at a total invoice cost of $285,000, which included a $6,000 charge for freight. Installation costs of $32,000 were incurred. On March 31,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Early in its fiscal year ending December 31, 2018, San Antonio Outfitters finalized plans to expand...
Early in its fiscal year ending December 31, 2018, San Antonio Outfitters finalized plans to expand operations. The first stage was completed on January 1 with the purchase of a tract of land on the outskirts of the city. The land and existing building were purchased for $880,000. San Antonio paid $240,000 and signed a noninterest bearing note requiring the company to pay the remaining $640,000 on January 1, 2020. An interest rate of 10% properly reflects the time value...
QUESTION 1 A method of estimating bad debts that focuses on the balance sheet rather than...
QUESTION 1 A method of estimating bad debts that focuses on the balance sheet rather than the income statement is the allowance method based on a. direct write-off b. aging the trade receivable accounts c. credit sales d. specific accounts determined to be uncollectible QUESTION 2 In a business combination, goodwill is defined as the excess of cost over the a. fair value of assets acquired b. fair value of assets acquired less the liabilities assumed c. book value of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT