Question

Heston Preskell, Inc., a commercial contractor, signed a contract during Year 1 for $808,000 to build...

Heston Preskell, Inc., a commercial contractor, signed a contract during Year 1 for $808,000 to build an office building for the YMCA.

Heston Preskell completed 30% of the work during Year 1 and the remaining 70% during Year 2.

The cost of acquired production materials during Year 1 by Heston Preskell was $195,000 and an additional $330,000 during Year 2.

Heston Preskell billed the YMCA $225,000 in Year 1 and the final $580,000 in Year 2. The YMCA paid $210,000 in Year 1, $440,000 in Year 2, and the balance in Year 3.

Heston Preskell uses the percentage of completion method of revenue recognition.

Calculate the Account Receivable amount for the year ending December 31, Year 1:

Calculate the Production in Progress amount for the year ending December 31, Year 1:

Calculate the Revenue recognized amount for the year ending December 31, Year 1:

Calculate the Gross Profit amount for the year ending December 31, Year 1:

Homework Answers

Answer #1
  • All working forms part of the answer
  • Please note that Contract price mentioned by you is $ 808,000 [however amount billed is $ 805,000]
  • Requirement 1: Accounts receivables amount for year ending Dec 31, Year 1

Amount billed in Year 1 = $ 225,000

Amount received in Year 1= $ 210,000

ANSWER = 225000 – 210000 = $ 15,000

  • Requirement 2: Production in Progress for year ending Dec 31 Year 1

=Cost incurred in Year 1 + (Revenue recognised – Cost of Year 1)

= $ 195,000 + [(808000 x 30%) – 195000]

= 195000 + (242400 – 195000)

= $ 242,400

ANSWER = $ 242,400

  • Requirement 3: Revenue recognised in Year 1

= Contract amount x % completed in Year 1

= 808000 x 30%

= $ 242,400 = ANSWER

  • Requirement 4: Gross Profits in Year 1

=Revenue recognised – Cost incurred in Year 1

= 242400 – 195000

= $ 47,400 = ANSWER

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
On January 1, Year 1, a contractor began work on a $3.2 million construction contract that...
On January 1, Year 1, a contractor began work on a $3.2 million construction contract that is expected to be completed in 3 years. The contractor concludes that it is appropriate to recognize revenue over time using the input method based on costs incurred (cost-to-cost method). At the inception date, the estimated cost of construction was $2.4 million. The following data relate to the actual and expected construction costs: Year 1 Year 2 Year 3 Cost incurred $720,000 $1,170,000 $1,110,000...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,225,000. During 2021, costs of $2,090,000 were incurred, with estimated costs of $4,090,000 yet to be incurred. Billings of $2,608,000 were sent, and cash collected was $2,340,000. In 2022, costs incurred were $2,608,000 with remaining costs estimated to be $3,735,000. 2022 billings were $2,858,000, and $2,565,000 cash was collected. The project was completed in 2023 after additional costs of...
On December 15, 2019, Peter Painter signed a contract with Joe Newhouse in which Peter agreed...
On December 15, 2019, Peter Painter signed a contract with Joe Newhouse in which Peter agreed to both provide the paint and provide the painting service to Joe. If purchased separately, the elling price of thepaint would be $ 1,600, and the value of the painting service would be $ 2,400. However, since Joe Newhouse purchased both from Peter, Peter agreed to "bundle" the paint and painting for a total of $ 3,200.According to the terms of the contract, Joe...
Financial Statement Impact of a Lease GEORGE's Warehouse signed a six-year capital lease on January 1,...
Financial Statement Impact of a Lease GEORGE's Warehouse signed a six-year capital lease on January 1, 2016, with payments due every December 31. Interest is calculated annually at 10%, and the present value of the minimum lease payments is $11,455. Use the appropriate present value table: PV of $1 and PV of Annuity of $1 Required: 1. Calculate the amount of the annual payment that GEORGE's must make every December 31. Round your answer to the nearest whole dollar. Lease...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
Big Wheel Construction had the following two construction projects which began in year​ 1: Project 1...
Big Wheel Construction had the following two construction projects which began in year​ 1: Project 1 Project 2 Contract price $690,000 $425,000 Costs incurred during year 1 200,000 225,000 Estimated costs to complete 400,000 225,000 Billed to customers during year 1 230,000 175,000 Received from customers during year 1 100,000 150,000 What amount of gross profit​ (loss) would Big Wheel report on its year 1 income​ statement? Percentage of Completion Completed Contract A. ​$17,500 ​$(12,500) B. ​$5,000 ​$(25,000) C. ​$5,000...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017     $35 million Construction in progress (as of 12/31/2017)                                                                                                    $50 million Accounts Receivable from construction billings (as...
On July 28, 2017, Malden Cleaning Services signed a one-year contract with Bernard Crystal Palace to...
On July 28, 2017, Malden Cleaning Services signed a one-year contract with Bernard Crystal Palace to perform cleaning services for the customer at a rate of $1,800 per month beginning September 1. During 2017, Malden Cleaning Services provided the services required from September 1 through December 31 and received $10,800 in cash from Bernard Crystal Palace. What amount, if any, was reported as accounts receivable from Bernard Crystal Palace by Malden Cleaning Services in its GAAP balance sheet at December...
The board of directors of Ogle Construction Company is meeting to choose between the completed contract...
The board of directors of Ogle Construction Company is meeting to choose between the completed contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Ogle's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Ogle commenced doing business on January 1, 2018. 2. Construction activities for the year ended December 31, 2018, were...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT