Question

If a previously profitable construction contract being accounted for with the percentage-of-completion method is later projected...

If a previously profitable construction contract being accounted for with the percentage-of-completion method is later projected to be unprofitable, then the Net Loss in that period will be equal to:

Select one:

a. All previously recognized Gross Profit on the contract

b. The projected Net Loss on the entire contract

c. All previously recognized Gross Profit plus the percentage of completion times the projected Net Loss on the entire contract

d. All previously recognized Gross Profit on the contract plus the projected Net Loss on the entire contract

e. The projected Net Loss on the entire contract times the percentage of completion.

Homework Answers

Answer #1

Answer : Option B

If a previously profitable construction contract being accounted for with the percentage-of-completion method is later projected to be unprofitable, then the Net Loss in that period will be equal to the projected Net Loss on the entire contract. If a net loss is expected under the contract, the entire loss is recognized immediately in the income statement. Revenue and contract costs are recognized in the income statement on the basis of Stage of Completion of the contract.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Widjaja Company is accounting for a long-term construction contract using percentage-of-completion method. It is a 4-year...
Widjaja Company is accounting for a long-term construction contract using percentage-of-completion method. It is a 4-year contract that is currently in its second year. The latest estimates of total contract costs indicate that the contract will be completed at a loss to Widjaja Company. a. What theoretical justification is there for Widjaja Company's use of the percentage-of-completion method? b. How would the company account for the projected loss?
The Leto Construction Company began work on a $12,000 contract on 1/1/15. Planned completion was in...
The Leto Construction Company began work on a $12,000 contract on 1/1/15. Planned completion was in 2017. The Percentage-of Completion method is used. .......................................................................2015.................2016................2017...... costs incurred to date................................$2,500...............4,200................11,550.... estimated costs to complete......................$7500...............6300................0........... billing to date...............................................$4000................5100................12,000.... collection to date........................................3800..................5000................11900.... The Gross Profit or (loss) recognized in 2017 is: Select one: a. $(150) b. $150 c. $450 d. $(450)
Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood...
Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood began work on a $4,300,000 fixed-fee construction contract, which was completed in 2024. Cost Incurred Estimated Additional Cost to Complete 2021 $800,000 $3,200,000 2022 $1,000,000 $2,200,000 2023 $936,000 $1,064,000 For the year 2023, Redwood should have recognized gross profit on this contract of: A)500,000 B)300,000 C)225,00 D)135,000
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
Ivanhoe Construction Company uses the percentage-of-completion method of accounting. In 2021, Ivanhoe began work on a...
Ivanhoe Construction Company uses the percentage-of-completion method of accounting. In 2021, Ivanhoe began work on a contract it had received which provided for a contract price of $39500000. Other details follow: 2021 Costs incurred during the year $18800000 Estimated costs to complete as of December 31 12800000 Billings during the year 17500000 Collections during the year 9700000 What should be the gross profit recognized in 2021? $7900000 $4700000 $20700000 $1566667
Long Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Long...
Long Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Long began work on a $400 million fixed-fee construction contract, which was completed in 2024. Cost incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Cost Incurred Estimated Costs to Complete as of December 31 2021 $60 $240 2022 $84 $176 For the year 2022, Long should have recognized gross profit on this contract...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office building for $60,000,000. The scheduled construction costs follow. Year Cost 2016 $12,000,000 2017 18,000,000 2018 10,000,000 Total $40,000,000 The building is completed in 2018. For each year, compute the revenue, expense, and gross profit reported for this construction project using each of the following methods. a. Percentage-of-completion method 2016 2017 2018 Revenue $Answer $Answer $Answer Expense $Answer $Answer $Answer Gross Profit $Answer $Answer $Answer...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 –0– Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 (a) What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $...
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract...
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract #E2-D2, which provided for a contract price of $2,165,000. Other details follow: 2020 2021 Costs incurred during the year $590,520 $1,409,000 Estimated costs to complete, as of December 31 1,005,480 –0– Billings during the year 428,000 2,165,000 Collections during the year 349,000 1,509,000 What portion of the total contract price would be recognized as revenue in 2020? In 2021? Revenue recognized in 2020 $...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract #E2-D2, which provided for a contract price of $2,170,000. Other details follow: 2020 2021 Costs incurred during the year $615,810 $1,422,000 Estimated costs to complete, as of December 31 963,190 –0– Billings during the year 426,000 2,170,000 Collections during the year 343,000 1,520,000 (a) New attempt is in progress. Some of the new entries may impact the last attempt grading.Your answer is incorrect. What...