Question

Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract...

Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract #E2-D2, which provided for a contract price of $2,170,000. Other details follow:

2020

2021

Costs incurred during the year $615,810 $1,422,000
Estimated costs to complete, as of December 31 963,190 –0–
Billings during the year 426,000 2,170,000
Collections during the year 343,000 1,520,000

(a)

New attempt is in progress. Some of the new entries may impact the last attempt grading.Your answer is incorrect.

What portion of the total contract price would be recognized as revenue in 2020? In 2021?

Revenue recognized in 2020

$

Revenue recognized in 2021

$

Homework Answers

Answer #1

Solution

Gross profit recognized in 2020 $      230,490
Gross profit recognized in 2021 $      (98,300)

Working

2020 2021
A Contract Price $ 2,170,000 $ 2,170,000
B Cost Incurred to Date $ 615,810 $ 2,037,810
C Estimated cost yet to be incurred to complete the contract $ 963,190 $ 0
D = B+C Total Cost $ 1,579,000 $ 2,037,810
E = (D/B) x 100 % of Completion 39% 100%
F = A x E Revenue to date $ 846,300 $ 2,170,000
G Revenue of Previous year $ 0 $ 846,300
H = F - G Net Revenue this year $ 846,300 $ 1,323,700
I Cost to date $ 615,810 $ 2,037,810
J Cost to date of previous year $ 0 $ 615,810
K = I - J Net Cost for the year $ 615,810 $ 1,422,000
L = H - K Gross Profits $ 230,490 -$ 98,300
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract...
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract #E2-D2, which provided for a contract price of $2,165,000. Other details follow: 2020 2021 Costs incurred during the year $590,520 $1,409,000 Estimated costs to complete, as of December 31 1,005,480 –0– Billings during the year 428,000 2,165,000 Collections during the year 349,000 1,509,000 What portion of the total contract price would be recognized as revenue in 2020? In 2021? Revenue recognized in 2020 $...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 –0– Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 (a) What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $...
Ivanhoe Construction Company uses the percentage-of-completion method of accounting. In 2021, Ivanhoe began work on a...
Ivanhoe Construction Company uses the percentage-of-completion method of accounting. In 2021, Ivanhoe began work on a contract it had received which provided for a contract price of $39500000. Other details follow: 2021 Costs incurred during the year $18800000 Estimated costs to complete as of December 31 12800000 Billings during the year 17500000 Collections during the year 9700000 What should be the gross profit recognized in 2021? $7900000 $4700000 $20700000 $1566667
Exercise 6-29 (Part Level Submission) Sandhill Construction Company uses the percentage-of-completion method of accounting. In 2017,...
Exercise 6-29 (Part Level Submission) Sandhill Construction Company uses the percentage-of-completion method of accounting. In 2017, Sandhill began work under a non-cancellable contract #E2-D2, which provided for a contract price of $2,024,000. Other details follow: 2017 2018 Costs incurred during the year $588,800 $1,311,000 Estimated costs to complete, as at December 31 883,200 0 Billings during the year (non-refundable) 386,400 1,545,600 Collections during the year 322,000 1,380,000 Collapse question part (a) How much revenue should be recognized in 2017 and...
A company began work in 2020 on a contract for $6,800. Other data are as follows:...
A company began work in 2020 on a contract for $6,800. Other data are as follows:                                                        2020                         2021 2020 2021 costs incurred to date $3,100 $5,600 Estimated Costs to complete 2,000 ----------- Billings to date 3,400 6,800 Collections to date 2,000 4,800 If the company uses the percentage-of-completion method, the gross profit to be recognized in 2021 is                          .
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Correct answer iconYour answer is correct. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized...
Windham Construction Company uses the percentage of completion method of accounting. In 2018 Windham started work...
Windham Construction Company uses the percentage of completion method of accounting. In 2018 Windham started work on a two-year contract with a total price of $15,000,000. Data for 2018 and 2019 are presented below: (Follow GAAP)                                                                  2018                            2019                       Costs incurred to date             $7,200,000                  $12,050,000             Estimated costs to complete   4,800,000                         - 0 -             Billings during the year          6,000,000                      9,000,000             Collections during the year     4,200,000                      8,900,000 (a)       How much...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract price was $1,600,000. The Job was completed in 2018.                                                                                 2016                       2017                       2018 Costs incurred to date                                    400000                  935000                  1070000 Estimated costs to complete                       700000                  165000                  0 Billings to date                                                  300000                  900000                  1600000 Collections to date                                           270000                  810000                  1525000 Compute the amount of Gross Profit to be recognized for 2016 and 2017 assuming that ole is required to recognize revenue overtime. Compute the...
A company began work in 2020 on a contract for $7,800. Other data are as follows:...
A company began work in 2020 on a contract for $7,800. Other data are as follows:                                                        2020                         2021 Costs incurred to date                 $3,000 $5,600 Estimated costs to complete         2,000       — Billings to date    3,100                   7,800 Collections to date                       1,000                      4,400 If the company uses the percentage-of-completion method, for the journal entry that records construction revenue, construction expense, and gross profit for 2020, how much will be recorded for Construction in Process?
A company began work in 2020 on a contract for $7,700. Other data are as follows:...
A company began work in 2020 on a contract for $7,700. Other data are as follows: 2020 2021 Costs incurred to date $3,000 $5,600 Estimated Costs to complete 2,000 ---------- Billings to date 3,700 7,700 Collections to date 1,000 4,800 On the company’s balance sheet at December 31, 2020, under the percentage-of-completion method, an inventory (or current liability) of $_____________ will be reported related to this project.