Question

The total costs on job cost sheets for jobs that are completed but not yet sold...

The total costs on job cost sheets for jobs that are completed but not yet sold equals the balance in the Work in Process Inventory account. True or False

Homework Answers

Answer #1

The total costs on job cost sheets for jobs that are completed but not yet sold equals the balance in the Work in Process Inventory account.

The given statement is False. Work in process inventory refers to the job which has started and on which some work has been done but the job is still incomplete. Jobs completed are not a part of work in process inventory.

The completed jobs are a part of Finished goods inventory. Until a job is sold, it is considered as finished goods. Thus the total cost on job cost sheet for jobs that are completed but not yet sold equals the balance in finished goods inventory.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
There are two basic types of cost accounting systems: job order costing and periodic costing. T/F...
There are two basic types of cost accounting systems: job order costing and periodic costing. T/F The total costs on job cost sheets for jobs that are completed but not yet sold equals the balance in the Work in Process Inventory account. T/F The cost of all direct materials issued to production is debited to Work in Process Inventory. T/F Time tickets can be used to determine the amount of direct labor to charge to jobs. T/F The predetermined overhead...
Question 30 Which of the following represents the cost of the jobs sold during the period?...
Question 30 Which of the following represents the cost of the jobs sold during the period? Group of answer choices Work in process inventory Finished goods inventory Cost of goods sold Raw materials inventory Question 31 Finished Goods Inventory has and ending balance of $225,000. This indicates Group of answer choices Some jobs were started but not yet completed Some jobs will need to be started next period Some jobs were completed but not yet sold Some jobs that were...
Cooper Manufacturing is currently working on two jobs. The job order cost sheets for Job 101...
Cooper Manufacturing is currently working on two jobs. The job order cost sheets for Job 101 and Job 102 showed the following information: Job 101 Job 102 Direct Materials $ 12,000 $ 15,000 Direct labor 24,000 45,000 If overhead is applied to jobs at $0.80 per direct labor dollar, the total manufacturing overhead cost for the two jobs would be: Multiple Choice $96,000. $162,000. $55,200. $151,200. Gibbons Company uses a process cost system and the weighted average method. The company...
Entries and Schedules for Unfinished Jobs and Completed Jobs Mellow Company uses a job order cost...
Entries and Schedules for Unfinished Jobs and Completed Jobs Mellow Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $3,170. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $3,030 $3,160 102 3,700 4,270 103 2,450 2,090 104 8,300 7,840 105 5,270 5,970 106 3,850 3,790 For general factory use 1,030 4,680 Factory overhead costs incurred on account, $5,790....
The information below was taken from the job cost sheets of Igmund Manufacturing. Job Number Manufacturing...
The information below was taken from the job cost sheets of Igmund Manufacturing. Job Number Manufacturing Costs as of June 30 Manufacturing Costs in July 101 $ 6,600 102 5,280 103 960 $ 3,600 104 4,080 7,200 105 8,400 106 2,900 During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31. a. Compute the work in process inventory...
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing...
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing Costs as of June 30 Manufacturing Costs in July 101 $ 4,100 102 3,200 103 920 $ 2,000 104 2,100 4,500 105 5,700 106 3,800 During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31. a. Compute the work in process inventory...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Partially completed job sheets for Freeley Co. appear below. These are the only jobs this company...
Partially completed job sheets for Freeley Co. appear below. These are the only jobs this company has. (SEND YOUR WORK) Job 10 Date Direct Materials Direct Labor Manufacturing Overhead Total 7/1 Beginning Balance $6,000 $8,000 $10,000 7/12 $15,000 7/19 $20,000 7/26 $10,000 7/29 $5,000 Job 11 Date Direct Materials Direct Labor Manufacturing Overhead Total 7/1 Beginning Balance $3,000 $6,000 $7,500 7/5 $8,000 7/15 $9,000 7/20 $7,000 7/31 $14,000 Job 10 was completed on July 29, 2020. What was the July...
Entries for Factory Costs and Jobs Completed Munch Printing Inc. began printing operations on January 1....
Entries for Factory Costs and Jobs Completed Munch Printing Inc. began printing operations on January 1. Jobs 301 and 302 were completed during the month, and all costs applicable to them were recorded on the related cost sheets. Jobs 303 and 304 are still in process at the end of the month, and all applicable costs except factory overhead have been recorded on the related cost sheets. In addition to the materials and labor charged directly to the jobs, $510...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Month Completed 10 $5,700 $5,800 May 11 4,700 4,100 $4,000 June 12 2,100 April 13 6,300 4,600 June 14 6,600 3,800 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....