Partially completed job sheets for Freeley Co. appear below. These are the only jobs this company has. (SEND YOUR WORK) Job 10 Date Direct Materials Direct Labor Manufacturing Overhead Total 7/1 Beginning Balance $6,000 $8,000 $10,000 7/12 $15,000 7/19 $20,000 7/26 $10,000 7/29 $5,000 Job 11 Date Direct Materials Direct Labor Manufacturing Overhead Total 7/1 Beginning Balance $3,000 $6,000 $7,500 7/5 $8,000 7/15 $9,000 7/20 $7,000 7/31 $14,000 Job 10 was completed on July 29, 2020. What was the July 31, 2020 balance in Work In Process? _________________________

What was the amount of overhead applied?

Homework Answers

Answer #1
Job 10
Date Direct materials Direct labor Mfg.OH Total
Beginning Balance 1-Jul 6000 8000 10000 24000
12-Jul 3750 5000 6250 15000
19-Jul 5000 6667 8333 20000
26-Jul 2500 3333 4167 10000
29-Jul 1250 1667 2083 5000
Total 29-Jul 18500 24667 30833 74000
Total cost on all days split in the ratio of beginning balance ,ie.
6:8:10
Job 11
Beginning Balance 1-Jul 3000 6000 7500 16500
5-Jul 1455 2909 3636 8000
15-Jul 1636 3273 4091 9000
20-Jul 1273 2545 3182 7000
31-Jul 2545 5091 6364 14000
9909 19818 24773 54500
Total cost on all days split in the ratio of beginning balance ,ie.
3:6:7.5
ANSWERS:
July 31, 2020 balance in Work In Process
Job 11 54500
Amount of overhead applied
30833+24773=
55606
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469...
A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,000 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31 Date Direct Materials Direct Labor Manufacturing Overhead 7/10 700 12 900 15 400 480 22 300 360 24 1,640 27 1,560 31 700 840 Cost of completed job:          Direct materials          Direct labor           Manufacturing overhead        Total cost        Unit cost (a) Answer the following questions. (1)...
A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469...
A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,500 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31 Date Direct Materials Direct Labor Manufacturing Overhead 7/10 700 12 900 15 400 500 22 300 375 24 1,700 27 1,550 31 500 625 Cost of completed job:          Direct materials          Direct labor           Manufacturing overhead        Total cost        Unit cost A job cost sheet of Sandoval...
Current Attempt in Progress A job cost sheet of Sandoval Company is given below. Job Cost...
Current Attempt in Progress A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,500 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31 Date Direct Materials Direct Labor Manufacturing Overhead 7/10 700 12 900 15 400 500 22 300 375 24 1,700 27 1,550 31 500 625 Cost of completed job:        Direct materials        Direct labor         Manufacturing overhead      Total cost      Unit cost (1) What are the source documents for direct materials, direct labor, and...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was a $15,000...
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 7,000 7,000 4,900 8 7,000 12 7,000 5,600 25 2,300 27 4,000 3,200 16,300 18,000 13,700 Cost of completed job:    Direct materials $ 16,300    Direct labor 18,000    Manufacturing overhead 13,700 Total cost $ 48,000 Unit cost ($ 48,000 ÷ 2,000) $ 24.00 (a) On the basis of the foregoing data, answer the...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Job 86 Job 87 Direct materials $4,800 $1,600 Direct labor 1,200 3,000 Applied overhead 888 2,220 Balance, March 1 $6,888 $6,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...
The following cost data relate to the manufacturing activities of Black Company during the just completed...
The following cost data relate to the manufacturing activities of Black Company during the just completed year:     Manufacturing overhead costs incurred: Property taxes, factory $ 3,000 Utilities, factory 5,000 Indirect labor 10,000 Depreciation, factory 24,000 Insurance, factory 6,000 Total actual manufacturing overhead costs $ 48,000 Other costs incurred: Purchases of raw materials $ 32,000 Direct labor cost $ 40,000 Inventories: Raw materials, beginning $ 8,000 Raw materials, ending $ 7,000 Work in process, beginning $ 6,000 Work in process, ending...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
ENTRIES FOR FACTORY COSTS AND JOBS COMPLETED ****ONLY NEED ANSWER FOR C.****** Old School Publishing Inc....
ENTRIES FOR FACTORY COSTS AND JOBS COMPLETED ****ONLY NEED ANSWER FOR C.****** Old School Publishing Inc. began printing operations on January 1. Jobs 301 and 302 were completed during the month, and all costs applicable to them were recorded on the related cost sheets. Jobs 303 and 304 are still in process at the end of the month, and all applicable costs except factory overhead have been recorded on the related cost sheets. In addition to the materials and labor...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were worked on during November and December. Job 105 was completed on December 10; the other two jobs were still in production on December 31, the end of the company’s operating year. Data from the job cost sheets of the three jobs follow:    Job Cost Sheet    Job 105 Job 106 Job 107   November costs incurred:      Direct materials $ 16,500 $ 9,300 $ 0...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT